Question

In: Operations Management

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? $______________

Activity                        Normal Time (days) Crash Time (days) Normal Cost      Total Cost with Crashing Immediate Predecessor(s)
A 6 5 $800 $1,100 -
B 8 6 $300 $400 -
C 6 5 $600 $650 -
D 6 3 $750 $1,500 A
E 5 3 $1,200 $1,650 C
a.

$ 3550

b.

$ 1550

c.

$ 3800

d.

$ 2500

Solutions

Expert Solution

Paths from start to end of project network is as follows:

Path

Duration

A-D

6 + 6 = 12 days

B

8 days

C-E

6 + 5 =11 days

Critical Path: A-D and project duration is 12 days.

Crashing principle: Crash only critical activities and prefer to crash the activity with lowest crashing cost per day.

The crashing cost per day is calculated is as follows:

Activity

Normal Time (days)

Crash Time (days)

Normal Cost     

Total Cost with Crashing

Immediate Predecessor(s)

Allowable Crashing

Crashing Cost

Crashing cost per day

A

6

5

$800

$1,100

-

1

$300

300

B

8

6

$300

$400

-

2

$100

50

C

6

5

$600

$650

-

1

$50

50

D

6

3

$750

$1,500

A

3

$750

250

E

5

3

$1,200

$1,650

C

2

$450

225

A-D is critical path, and lowest cras

The crashing schedule is as shown below:

Crashing Sequence

0

1

2

3

4

Critical Paths

A-D

A-D

A-D

C-E

A-D

C-E

A-D

C-E

Lowest crashing cost per week activity (crashing cost)

D ($250/ DAY)

D ($250/ DAY)

C ($50/ DAY)

D ($250/ DAY)

E ($225/ DAY)

A ($300/ DAY)

E ($225/ DAY)

Activity Crashed

None

D

D, C

D, E

A, E

Crashing Duration

0

1

1

1

1

Project duration

12

11

10

9

8

A-D

12

11

10

9

8

B

8

8

8

8

8

C- E

11

11

10

9

8

Crash cost

$0

$250

$300

$475

$525

Cum. Crash cost

$0

$250

$550

$1025

$1550

Thus, to crash the project duration by 4 DAYS, the minimum additional cost required = $1550


Related Solutions

24. What is project crashing ? What are the 4 steps involved in the project crashing?...
24. What is project crashing ? What are the 4 steps involved in the project crashing? Explain. What is the LP formulation of the project crashing problem? What are the decision variables, constraints and the objective function of the LP formulation of crashing problem? Please answer question fully for a rating
Roger Productions is evaluating a film project. The president of Roger estimates that the film will...
Roger Productions is evaluating a film project. The president of Roger estimates that the film will cost $20,000,000 to produce. In its first year, the film is expected to generate $16,307,000 in net revenue, after which the film will be released to video. Video is expected to generate $9,538,000 in net revenue in its first year, $2,496,100 in its second year, and $1,011,500 in its third year. For tax purposes, amortization of the cost of the film will be $12,000,000...
Considering quantitative risk assessment, what is one of the most significant disadvantages to project crashing? reference...
Considering quantitative risk assessment, what is one of the most significant disadvantages to project crashing? reference to source question https://www.chegg.com/homework-help/questions-and-answers/question-4-production-manager-electronic-toys-company-et-co-begin-project-design-productio-q29681067 This is not an incomplete question it is asking in genereal what is the disadvantages of project crashing. where disadvantages are that it is expensive and can cause failure to activities and effect the whole project. the part i do not understand is answering the question with reference to quantitative risk assessment.
Construct the following network(AOA) and determine the minimum total cost to complete the project if indirect...
Construct the following network(AOA) and determine the minimum total cost to complete the project if indirect cost is Rs.1500 per day. Activity NT CT NC CC 1-2 6 4 6000 7800 1-3 7 4 3000 4200 2-3 4 1 5000 9200 2-5 6 5 6000 7500 3-4 7 3 2000 6800 4-5 3 1 2000 4000 4-6 7 3 4000 5600 5-6 5 4 3000 4100
What is the payback period for a project with the following characteristics, given a minimum attractive...
What is the payback period for a project with the following characteristics, given a minimum attractive rate of return (MARR) of 12%? First Cost $20,000 Annual Benefits $8,000 Annual Maintenance $2,000 in year 1, then increases by $500 per year Salvage value $2,000 Useful Life 10 years
You are thinking about shortening (i.e. crashing) the entire project. The information of the normal job...
You are thinking about shortening (i.e. crashing) the entire project. The information of the normal job times (i.e.e the minimum job time the job can be crashed to), and the costs needed for shortening each job by one day is provided below (Table 2). You were just provided with a fund of $1,500 (besides the fund of completing the project w/o crashing). The objective is to crash the project as much as possible within $1,500. Under the objective, if there...
Define the roles and responsibilities of a project manager. Show how the project manager manages the...
Define the roles and responsibilities of a project manager. Show how the project manager manages the triple constraints of a project.
Question 1 What of the following project is a non-normal cash flow project? Project cost (negative...
Question 1 What of the following project is a non-normal cash flow project? Project cost (negative CF) is followed by a series of positive cash inflows. Project cost (negative CF) is followed by a series of positive cash inflows and a final negative cash flow when closing the project. Project cost (negative CF) is followed a negative cash flows and then a series of positive cash inflows. Project cost (negative CF) is followed two years’ negative cash flows and then...
Solano Company has sales of $700,000, cost of goods sold of $470,000, other operating expenses of...
Solano Company has sales of $700,000, cost of goods sold of $470,000, other operating expenses of $50,000, average invested assets of $2,100,000, and a hurdle rate of 9 percent. Required: 1. Determine Solano’s return on investment (ROI), investment turnover, profit margin, and residual income. 2. Several possible changes that Solano could face in the upcoming year follow. Determine each scenario’s impact on Solano’s ROI and residual income. (Note: Treat each scenario independently.) a. Company sales and cost of goods sold...
Solano Company has sales of $760,000, cost of goods sold of $500,000, other operating expenses of...
Solano Company has sales of $760,000, cost of goods sold of $500,000, other operating expenses of $40,000, average invested assets of $2,250,000, and a hurdle rate of 11 percent. 1. Determine Solano’s return on investment (ROI), investment turnover, profit margin, and residual income. (Do not round your intermediate calculations. Enter your ROI and Profit Margin percentage answer to the nearest 2 decimal places, (i.e., 0.1234 should be entered as 12.34%). Round your Investment Turnover answer to 4 decimal places.) 2....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT