Question

In: Accounting

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 268,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming Nortel recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognition over time.

Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion

Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time.

Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming Nortel recognizes revenue over time according to percentage of completion.

Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognition over time.

Solutions

Expert Solution

1 2018 2019
Contract price (1) 2450000 2450000
Actual cost to date (a) 336000 2206000
(336000+1870000)
Estimated cost to complete (b) 1344000 0
Total estimated cost ©=(a)+(b) 1680000 2206000
Percentage of completion (a)/© 20% 100%
Expected gross profit (1)-© 770000 244000
Revenue to be recognized=(Contract price*Percentage of completion)-Revenue recognized earlier
Gross profit to be recognized=(Expected gross profit*Percentage of completion)-Gross profit already recognized
2018
Revenue to be recognized=(2450000*20%)-0=$ 490000
Gross profit to be recognized=(770000*20%)-0=$ 154000
2019
Revenue to be recognized=(2450000*100%)-490000=$ 1960000
Gross profit to be recognized=(244000*100%)-154000=$ 90000
2 If the project does not qualify for revenue recognition over time,recognize revenue on completion of contract
2018
Revenue to be recognized=0
Gross profit to be recognized=0
(Since contract has not completed)
2019
Revenue to be recognized=Contract price=$ 2450000
Gross profit to be recognized=Contract price-Actual cost to date=2450000-2206000=$ 244000
3 Partial balance sheet-2018
Current assets:
Accounts receivable
Billings made during the year 446000
Less: Cash collections 268000 178000
Cost and profit in excess of billings
Cost incurred 336000
Add:Gross profit recognized 154000
490000
Less: Billings 446000 44000
4 Partial balance sheet-2018
Current assets:
Accounts receivable
Billings made during the year 446000
Less: Cash collections 268000 178000
Current liability:
Billings in excess of cost
Billings made during the year 446000
Less: Cost incurred 336000 110000

Related Solutions

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 300,000 $ 1,575,000 Estimated costs to complete as of 12/31 1,200,000 0 Billings during the year 380,000 1,620,000 Cash collections during the year 250,000 1,750,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 324,000 $ 1,800,000 Estimated costs to complete as of 12/31 1,296,000 0 Billings during the year 410,000 1,680,000 Cash collections during the year 262,000 1,780,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,050,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,050,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 304,000 $ 1,595,000 Estimated costs to complete as of 12/31 1,216,000 0 Billings during the year 385,000 1,630,000 Cash collections during the year 260,000 1,755,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 360,000 $ 2,155,000 Estimated costs to complete as of 12/31 1,440,000 0 Billings during the year 500,000 1,770,000 Cash collections during the year 445,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 268,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 254,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 360,000 $ 2,155,000 Estimated costs to complete as of 12/31 1,440,000 0 Billings during the year 500,000 1,770,000 Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below: 2016 2017   Costs incurred during the year $ 360,000 $ 2,155,000   Estimated costs to complete as of 12/31 1,440,000 0   Billings during the year 500,000 1,770,000   Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT