Question

In: Accounting

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below:

2021 2022
Costs incurred during the year $ 360,000 $ 2,155,000
Estimated costs to complete as of 12/31 1,440,000 0
Billings during the year 500,000 1,770,000
Cash collections during the year 445,000 1,825,000


Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to percentage of completion.
4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming this project does not qualify for revenue recognition over time.

omplete this question by entering your answers in the tabs below.

  • Required 1
  • Required 2
  • Required 3
  • Required 4

Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion. (Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.)

Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
2021 ÷ = 0
2022 ÷ = 0
2021
To date Recognized in prior years Recognized in 2021
Construction revenue $0
Construction expense $0
Gross profit (loss) $0
2022
To date Recognized in prior years Recognized in 2022
Construction revenue $0
Construction expense $0
Gross profit (loss) $0

Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time. (Loss amounts should be indicated with a minus sign.)

Revenue Gross Profit (Loss)
2021
2022

Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to percentage of completion.

Balance Sheet (Partial)
At December 31, 2021
Current assets:
Current liabilities:

repare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming this project does not qualify for revenue recognition over time.

Balance Sheet (Partial)
At December 31, 2021
Current assets:
Current liabilities:


Solutions

Expert Solution

Part 1

Revenue

Gross profit

2021

600000

268000

2022

1800000

(50000)

Percentages of completion

Choose numerator

÷

Choose denominator

=

% complete to date

Actual costs to date

÷

Estimated total costs

2021

360000

÷

1440000

=

25%

2022

2515000

÷

2515000

=

100%

360000+2155000 = 2182000

2021

To date

Recognized in prior years

Recognized in 2021

Construction revenue

687500

687500

Construction expense

(360000)

(360000)

Gross profit (loss)

327500

327500

Revenue = (360000/1440000)*2750000 = 687500

2022

To date

Recognized in prior years

Recognized in 2022

Construction revenue

2750000

687500

2062500

Construction expense

(2515000)

(360000)

(2155000)

Gross profit (loss)

235000

327500

(92500)

Part 2

Revenue

Gross profit

2021

2022

2750000

235000

Gross profit = 2750000-2515000 = 235000

Part 3

Balance sheet (partial)

At the December 31, 2021

Current assets:

Accounts receivable (500000-445000)

55000

Costs and profit in excess of billings (360000+327500)-500000

187500

Current liabilities:

Part 4

Balance sheet (partial)

At the December 31, 2021

Current assets:

Accounts receivable (500000-445000)

55000

Current liabilities:

Billings in excess of costs (500000-360000)

140000


Related Solutions

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 360,000 $ 2,155,000 Estimated costs to complete as of 12/31 1,440,000 0 Billings during the year 500,000 1,770,000 Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below: 2016 2017   Costs incurred during the year $ 360,000 $ 2,155,000   Estimated costs to complete as of 12/31 1,440,000 0   Billings during the year 500,000 1,770,000   Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 300,000 $ 1,575,000 Estimated costs to complete as of 12/31 1,200,000 0 Billings during the year 380,000 1,620,000 Cash collections during the year 250,000 1,750,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 324,000 $ 1,800,000 Estimated costs to complete as of 12/31 1,296,000 0 Billings during the year 410,000 1,680,000 Cash collections during the year 262,000 1,780,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,050,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,050,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 304,000 $ 1,595,000 Estimated costs to complete as of 12/31 1,216,000 0 Billings during the year 385,000 1,630,000 Cash collections during the year 260,000 1,755,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 268,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 268,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 254,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT