Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began...

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:

2018 2019
Costs incurred during the year $ 324,000 $ 1,800,000
Estimated costs to complete as of 12/31 1,296,000 0
Billings during the year 410,000 1,680,000
Cash collections during the year 262,000 1,780,000


Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming Nortel recognizes revenue over time according to percentage of completion.
4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognition over time.

Solutions

Expert Solution

Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.
Contract % Completion
Part 1 Part 1: Amount of Gross profit recognized each year
Year 2018
Cost incurred during the year $           324,000
Add: Estimated cost to complete as of year end $       1,296,000
Estimated Total cost $       1,620,000
% Completion 20%
2079000/7700000
Revenue to be recognized 2300000*20% $           460,000
Less: Cost incurred $           324,000
Gross Profit to be recognized $           136,000
Year 2019
Cost incurred during the year (324000+1800000) A $       2,124,000
Add: Estimated cost to complete as of year end $                       -  
Estimated Total cost B $       2,124,000
% Completion A/B 100.00%
Revenue to be recognized 2300000*100% $       2,300,000
Already recognized till 2018 $           460,000
To be recognized in 2019 $       1,840,000
Less: Cost incurred $       1,800,000
Gross Profit to be recognized $             40,000
Part 2 2018 2019
Gross Revenue 0 $       2,300,000
Gross Profit 0 $           176,000
Part 3
2018
Current Assets:
Accounts Receivable 410000-262000 $           148,000
Construction in Progress $           460,000
Less Billings $           410,000
Costs and profit in excess of billing $             50,000
Part 4
2018
Current Assets:
Accounts Receivable 410000-262000 $           148,000
Current Liabilities:
Construction in Progress $           460,000
Less Billings $           324,000
Costs and profit in excess of billing $           136,000

Related Solutions

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 300,000 $ 1,575,000 Estimated costs to complete as of 12/31 1,200,000 0 Billings during the year 380,000 1,620,000 Cash collections during the year 250,000 1,750,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,050,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,050,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 304,000 $ 1,595,000 Estimated costs to complete as of 12/31 1,216,000 0 Billings during the year 385,000 1,630,000 Cash collections during the year 260,000 1,755,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 360,000 $ 2,155,000 Estimated costs to complete as of 12/31 1,440,000 0 Billings during the year 500,000 1,770,000 Cash collections during the year 445,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 268,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 268,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 254,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 360,000 $ 2,155,000 Estimated costs to complete as of 12/31 1,440,000 0 Billings during the year 500,000 1,770,000 Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below: 2016 2017   Costs incurred during the year $ 360,000 $ 2,155,000   Estimated costs to complete as of 12/31 1,440,000 0   Billings during the year 500,000 1,770,000   Cash collections during the year 280,000 1,825,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT