Question

In: Finance

Two public infrastructure projects have the economic profiles that follow: Option B. Year Capital Cost Operating...

Two public infrastructure projects have the economic profiles that follow:

Option B.

Year Capital Cost Operating and Maintenance Cost Benefits
1 2,500,000 0 0
2 500,000 50,000 750,000
3 100,000 750,000
4 100,000 750,000
5 100,000 750,000
6 100,000 750,000
7 100,000 750,000
8 100,000 750,000
9 100,000 750,000
10 100,000 300,000

Option A

Year Capital Cost Operating and Maintenance Cost Benefits
1 2,000,000 0 0
2 1,000,000 10,000 0
3 500,000 70,000 120
4 90,000 600,000
5 90,000 800,000
6 90,000 800,000
7 90,000 800,000
8 90,000 800,000
9 100,000 800,000
10 100,000 500,000

Use this data to compute for each (a) the Net Present Value at discount rates of 10 and 5 percent (c) the internal rate of return for each. Describe the facts about the projects that would dictate which criterion is appropriate, and which project is preferable under each circumstance.

Solutions

Expert Solution

Option B

NPV 10% 643430.64
NPV 5% 1401438.65
IRR 15.87%

Option A

NPV 10% -818879.82
NPV 5% -131795.41
IRR 4.22%

The NPV is negative in both cases for Option A. This implies that the option is not suitable and is loss making.

As per IRR method, the option with the higher IRR is selected. Hence Option B is again preferred over Option A.

WORKINGS


Related Solutions

You have two mutually exclusive projects A and B and have constructed the NPV profiles for...
You have two mutually exclusive projects A and B and have constructed the NPV profiles for these projects. You find that the IRR of A is greater than the IRR of B but at an 8% cost of capital using the NPV method you would prefer project B. What is causing the NPV profile pattern that you are observing? Which project do you prefer and why? Essentially you are preferring one method over another so you need to discuss the...
Consider the following two projects. The cost of capital for both projects is 15%. Project Year...
Consider the following two projects. The cost of capital for both projects is 15%. Project Year 0 1 2 3 4 5 Alpha -55,000 15,000 14,000 22,000 30,000 35,000 Gamma -80,000 40,000 30,000 25,000 25,000 20,000 Calculate the IRR for each project and determine which one is better. Calculate the NPV for each project and determine which one is better. Based on profitability index method, which project is better? Overall, which project should be accepted assuming they are mutually exclusive?...
_______ 1. We have two projects A and B that each have a cost of $10,000....
_______ 1. We have two projects A and B that each have a cost of $10,000. Project A has cash flows of $3,250, $3,250, $3,510, $3,510. Project B has cash flows of $800, $770, $4,600, and $9,000. The payback is: PROJECT A PAYBACK = 2.797 YEARs; PROJECT B PAYBACK = 3.654 YEARs. T OR F ______ 2. Using the information from #1, the NPV is $850.52 for A and -1,363.33 for project B. T OR F ______ 3. Net present...
B Industries is considering two projects for inclusion in its capital budget, and you have been...
B Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. B's WACC is 9%. 0 1 2 3 4 Project A -950 650...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. If r = 10%, which project should be selected under the NPV method? b. If r = 20%, which project should be selected under the NPV method? c. Calculate each project’s PI...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. Calculate each project’s payback (PB) period if r = 10% (up to 2 decimal places). Which project should be accepted? b. Calculate each project’s discounted payback (DPB) period if r = 10%...
Question We have two investment projects A&B. Both projects cost $250, and we require a 15%...
Question We have two investment projects A&B. Both projects cost $250, and we require a 15% return of the two investments. Year A B 1 $100 $100 2 $100 $200 3 $100 0 4 $100 0 a) Based on the payback period rule, which project would you pick? Explain. b) Based on the NPV rule, which project would you pick? Explain. c) Do a) and b) give you the same conclusion? If not, why? Please elaborate. d) What other methods...
You are considering an investment in two projects, A and B. Both projects will cost $115,000,...
You are considering an investment in two projects, A and B. Both projects will cost $115,000, and the projected cash flows are as follows: YEAR PROJECT A PROJECT B 1 $7,188    $51,750 2 $21,562    $38,812 3 $40,250    $28,750 4 $50,315    $21,563 5    $57,500 $14,375 Using Excel and show formulas a. Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR, and MIRR. If the projects are mutually exclusive, which...
The cash flow in respect of two projects is given below. The cost of capital is...
The cash flow in respect of two projects is given below. The cost of capital is 8.5%. Year Project A Project B 0 (200) (300) 1 65 100 2 65 100 3 65 90 4 60 70 5 60 70 Answer the following question using the above information. I           What is the NPV of Project A? Should this project be accepted? II         What is the NPV of Project B? Should this project be accepted? (Please state based on what the...
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000....
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000. 1 600. 800. 2 800. 600. 3 1,200. 200. 4 Each project has a cost of $ 2,000 and the total cost of capital is 10%. Determine which project should be accepted ?Using Net present value (NPV)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT