Question

In: Accounting

The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016...

The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016 and was completed in 2017. Data relating to the contract are summarized below:

                                                                                   2016                  2017

      Costs incurred during the year.................      $   360,000         $1,650,000

      Estimated costs to complete as of 12/31.        1,560,000                   -      

      Billings during the year ..........................           430,000         2,170,000

      Cash collections during the year..............           320,000         2,280,000

Required:

1.   Compute the amount of gross profit or loss to be recognized in 2016 and 2017 using the percentage-of-completion method (over time method).

2.   Compute the amount of gross profit or loss to be recognized in 2016 and 2017 using the completed contract method (at point in time).

Using Excel, complete this construction handout using the either the format in the textbook or the format in the ABC Construction Contract Worksheet Example posted in Bb. Include all necessary journal entries to record the cost of construction, progress billings, entry to recognize revenue and gross profit and entry to record final approval of the contract.

Solutions

Expert Solution

1 2016 2017
Contract price (a) $2,600,000 $2,600,000
Actual costs to date $360,000 $2,010,000
Estimated costs to complete $1,560,000                   -  
Total estimated costs (b) $1,920,000 $2,010,000
Estimated (actual) gross profit (a-b) $680,000 $590,000
Percentage-of-completion = $ 360,000/$1,920,000 = 18.75%
Gross Profit recognition: $127,500 $462,500
(18.75% x $680,000), ($590,000 - $127,500)
2 2016 2017
Completed contract method, Gross Profit                 -   $590,000
Date Accounts and Explanation Debit Credit
2016 Work-in-progress $360,000
Accounts payable and others $360,000
(To record the cost incurred)
2016 Accounts receivable $430,000
Billings $430,000
(To record the amount billed)
2016 Cash $320,000
Accounts Receivable $320,000
(To record the collections)
2017 Work-in-progress $1,650,000
Accounts payable and others $1,650,000
(To record the cost incurred)
2017 Accounts receivable $2,170,000
Billings $2,170,000
(To record the amount billed)
2017 Cash $2,280,000
Accounts Receivable $2,280,000
(To record the collections)
2017 Billings $2,600,000
Construction Contracts Revenue $2,600,000
(To record the revenue)
2017 Cost of construction $2,010,000
Work-in-progress $2,010,000
(o expense out the work-in-progress)

Related Solutions

On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's capitalized interest in 2016 was: a. $72,000 b. $63,000 c. $54,000 d. $36,000
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher’s accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5 Construction costs incurred during the year, $180,000; estimated costs to complete, $630,000; progress billings during the year, $153,000; and collections, $140,000. 20X6...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2019 2020 Costs incurred during the year $ 290,000 $ 150,000 Estimated additional cost to complete 145,000 — Billings during the year 260,000 265,000 Cash collections during the year 240,000 285,000 Required: Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in early 2010 and was completed in 2011. The following additional information is available:                                                                                                    2010                       2011        Costs incurred............................................................. $ 2,430,000            $ 2,700,000        Estimated costs to complete............................................. 2,600,000                         —        Collections during the year.............................................. 2,400,000               3,600,000          Billings for the year …………………………………………..     2,800,000                3,200,000 Used the percentage-of-completion method. Instructions Under the contract-based approach, a)     How much revenue should be reported...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                                                                                                                                    2020                                    2021                      2022 Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000 Estimated costs to complete the contract at Dec 31          ...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available: 2019 2020 Cost Incurred $1,458,000 $1,620,000 Estimated costs to complete 1,560,000 - Billed 1,700,000 1,900,000 Collections during the year 1,440,000 2,160,000 Miller uses the percentage-of-completion method. Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019 and 2020? b) Prepare all journal entries for 2019...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available:                                                                                           2019               2020        Costs incurred...................................................... $1,458,000          $1,620,000        Estimated costs to complete.................................. 1,560,000                         —        Billed ……………………………………………….    1,700,000           1,900,000        Collections during the year.................................... 1,440,000            2,160,000 Miller uses the percentage-of-completion method. Instructions Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700 2,117,000 –0– Billings...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract Costs Incurred during the year $2,208,000 $2,230,000 $2,190,000 Estimated Costs to Complete the Contract at 12/31 $3,520,000 $2,190,000 -0- Billings...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT