Question

In: Accounting

On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:

January 1, 2016 $300,000

September 1, 2016 $450,000

December 31, 2016 $450,000

March 31, 2017 $450,000

September 30, 2017 $300,000

Dreamworld had $5,000,000 in 12% bonds outstanding through both years.

Dreamworld's capitalized interest in 2016 was:

a.

$72,000

b.

$63,000

c.

$54,000

d.

$36,000

Solutions

Expert Solution

Step-1: Determine the average accumulated expenditures during the year.

Here, we will time weight the expenditures, which means, we will multiply the expenditure incurred with the months left in the year after it incurred and divide it by the total number of months in a year.

In year 2016, expenditures incurred are as follows:

January 1,2016- 300000*(12/12)= $300,000

September 1,2016- 450,000*(4/12)= $150,000

Total average accumulated expenditure= 300,000+150,000= $450,000

Step-2: Calculate the amount of interest to capitalize

  • Multiply the interest rate by average accumulated expenditures.
  • Interest calculated is limited to interest incurred.

Interest on accumulated expenditures= 12% of 450,000 i.e. $54,000

Interest incurred = 12% of 500,000= $60,000(on bonds)

As Interest on accumulated expenditures is within the limit of interest incurred, therefore, Capitalised interest rate will be $54,000 during the year 2016.

The correct option will be C i.e. $54,000


Related Solutions

On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $50,000 None...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 336,000 September 1, 2018 $ 504,000 December 31, 2018 $ 504,000 March 31, 2019 $ 504,000 September 30, 2019 $ 336,000 Dreamworld had $6,800,000 in 10% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 307,000 September 1, 2018 $ 459,000 December 31, 2018 $ 459,000 March 31, 2019 $ 459,000 September 30, 2019 $ 307,000 Dreamworld had $5,300,000 in 13% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building was completed on June 30, 2016. Cash outlays for the $5 million project were as follows: 2015 January 1                        $1,000,000 March 1                          $600,000 June 30                           $800,000 September 30               $750,000 December 1                   $600,000 2016 March 31                        $800,000 June 30                           $450,000 (final payment) Total payments             $5,000,000 On January 1, 2015 Costco obtained a $3 million dollar construction loan with a 5% interest rate. Costco’s other long-term...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016 and was completed in 2017. Data relating to the contract are summarized below:                                                                                    2016                  2017       Costs incurred during the year.................      $   360,000         $1,650,000       Estimated costs to complete as of 12/31.        1,560,000                   -             Billings during the year ..........................           430,000         2,170,000       Cash collections during the year..............           320,000         2,280,000 Required: 1.   Compute the amount of gross...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made its first $500,000 payment. An additional $600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A final payment of $100,000 was made on 12/31/2016, which is also the date when the construction project was finished and the building was ready to use. To finance the project, XYZ Corp issued a $800,000 10% note. Furthermore, XYZ Corp had a $2,000,000 5% note outstanding...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT