Question

In: Accounting

On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing...

On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700 2,117,000 –0– Billings to Fabrik during the year 3,240,000 3,460,000 1,690,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

Solutions

Expert Solution


Related Solutions

On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract Costs Incurred during the year $2,208,000 $2,230,000 $2,190,000 Estimated Costs to Complete the Contract at 12/31 $3,520,000 $2,190,000 -0- Billings...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,410,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,916,400 $2,079,200 $2,244,400 Estimated costs to complete the contract at 12/31 3,423,600 2,244,400 –0– Billings...
Problem 18-10 On March 1, 2017, Sandhill Construction Company contracted to construct a factory building for...
Problem 18-10 On March 1, 2017, Sandhill Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,310,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,871,000 $2,304,900 $2,114,100 (2019 Row) Estimated costs to complete the contract at 12/31...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                                                                                                                                    2020                                    2021                      2022 Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000 Estimated costs to complete the contract at Dec 31          ...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2019 2020 Costs incurred during the year $ 290,000 $ 150,000 Estimated additional cost to complete 145,000 — Billings during the year 260,000 265,000 Cash collections during the year 240,000 285,000 Required: Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT