In: Finance
You have 3 projects with the following cash flows:
Year 0 1
2
3 4
Project 1 -$149 $19
$42 $61 $79
Project 2 -827 0
0 7,002 -6,508
Project 3
18
39 62 81 -247
a. For which of these projects is the IRR rule reliable?_______.
b. Estimate the IRR for each project (to the nearest 1 %).________.
c. What is the NPV of each project if the cost of capital is 5 %? 20 %? 50 %?________.
a. For which of these projects is the IRR rule reliable? (Select from the drop-down menus.)
The IRR rule is reliable for▼project 1 project 2 project 3. Unless all of the ▼positive negative cash flows of the project precede the ▼negative
positiveones, the IRR rule may give the wrong answer and should not be used. Furthermore, there may be multiple IRRs or the IRR may not exist.
a.
IRR rule is reliable for Project 1. Unless all of the negative cash flow of the project precedes positive ones.
b.
Computation of IRRs using excel:
A |
B |
C |
D |
|
1 |
Year |
Project 1 |
Project 2 |
Project 3 |
2 |
0 |
($149) |
($827) |
$18 |
3 |
1 |
$19 |
$0 |
$39 |
4 |
2 |
$42 |
$0 |
$62 |
5 |
3 |
$61 |
$7,002 |
$81 |
6 |
4 |
$79 |
($6,508) |
($247) |
7 |
IRR |
10.70% |
10.65% |
11.01% |
If excel sheet look like above table,
Insert formula “=IRR(B2:B6)” in Cell B7 to get IRR of project 1 as 10.70 %
Insert formula “=IRR(C2:C6)” in Cell C7 to get IRR of project 2 as 10.65 %
Insert formula “=IRR(D2:D6)” in Cell D7 to get IRR of project 3 as 11.01 %
c.
Computation of NPV @ 5 %:
Year |
Computation of PV factor |
PV Factor @ 5 % (F) |
Cash Flow Project 1 C1 |
PV Project 1 (=C1 x F) |
Cash Flow Project 2 C2 |
PV Project 2 (=C2 x F) |
Cash Flow Project 3 C3 |
PV Project 3 (=C3 x F) |
0 |
1/(1+0.05)^0 |
1 |
($149) |
($149.00) |
($827) |
($827.00) |
$18 |
$18.0000 |
1 |
1/(1+0.05)^1 |
0.952380952 |
$19 |
$18.09524 |
$0 |
$0.0000 |
$39 |
$37.1429 |
2 |
1/(1+0.05)^2 |
0.907029478 |
$42 |
$38.09524 |
$0 |
$0.0000 |
$62 |
$56.2358 |
3 |
1/(1+0.05)^3 |
0.863837599 |
$61 |
$52.69409 |
$7,002 |
$6,048.5909 |
$81 |
$69.9708 |
4 |
1/(1+0.05)^4 |
0.822702475 |
$79 |
$64.99350 |
($6,508) |
($5,354.1477) |
($247) |
($203.2075) |
NPV |
$24.87807 |
NPV |
($132.55684) |
NPV |
($21.85798) |
NPV of Project 1, 2 and 3 at discount rate of 5 % is $24.88, -$ 132.56, -$21.86 respectively.
Computation of NPV @ 20 %:
Year |
Computation of PV factor |
PV Factor @ 20 % (F) |
Cash Flow Project 1 C1 |
PV Project 1 (=C1 x F) |
Cash Flow Project 2 C2 |
PV Project 2 (=C2 x F) |
Cash Flow Project 3 C3 |
PV Project 3 (=C3 x F) |
0 |
1/(1+0.20)^0 |
1 |
($149) |
($149.00000) |
($827) |
($827.0000) |
$18 |
$18.0000 |
1 |
1/(1+0.20)^1 |
0.833333333 |
$19 |
$15.83333 |
$0 |
$0.0000 |
$39 |
$32.5000 |
2 |
1/(1+0.20)^2 |
0.694444444 |
$42 |
$29.16667 |
$0 |
$0.0000 |
$62 |
$43.0556 |
3 |
1/(1+0.20)^3 |
0.578703704 |
$61 |
$35.30093 |
$7,002 |
$4,052.0833 |
$81 |
$46.8750 |
4 |
1/(1+0.20)^4 |
0.482253086 |
$79 |
$38.09799 |
($6,508) |
($3,138.5031) |
($247) |
($119.1165) |
NPV |
($30.60108) |
NPV |
$86.58025 |
NPV |
$21.31404 |
NPV of Project 1, 2 and 3 at discount rate of 20 % is -$30.60, $ 86.58, -$21.31 respectively.
Computation of NPV @ 50 %:
Year |
Computation of PV factor |
PV Factor @ 50 % (F) |
Cash Flow Project 1 C1 |
PV Project 1 (=C1 x F) |
Cash Flow Project 2 C2 |
PV Project 2 (=C2 x F) |
Cash Flow Project 3 C3 |
PV Project 3 (=C3 x F) |
0 |
1/(1+0.50)^0 |
1 |
($149) |
($149.00000) |
($827) |
($827.0000) |
$18 |
$18.0000 |
1 |
1/(1+0.50)^1 |
0.666666667 |
$19 |
$12.66667 |
$0 |
$0.0000 |
$39 |
$26.0000 |
2 |
1/(1+0.50)^2 |
0.444444444 |
$42 |
$18.66667 |
$0 |
$0.0000 |
$62 |
$27.5556 |
3 |
1/(1+0.50)^3 |
0.296296296 |
$61 |
$18.07407 |
$7,002 |
$2,074.6667 |
$81 |
$24.0000 |
4 |
1/(1+0.50)^4 |
0.197530864 |
$79 |
$15.60494 |
($6,508) |
($1,285.5309) |
($247) |
($48.7901) |
NPV |
($83.98765) |
NPV |
($37.86420) |
NPV |
$46.76543 |
NPV of Project 1, 2 and 3 at discount rate of 50 % is - $83.99, -$ 37.86, -$46.77 respectively.