Question

In: Finance

You have 3 projects with the following cash​ flows: Year    0       1   2     ...

You have 3 projects with the following cash​ flows:

Year    0       1   2      3         4
Project 1   -$149   $19   $42   $61      $79
Project 2   -827      0   0   7,002   -6,508
Project 3   18          39   62   81      -247

a. For which of these projects is the IRR rule​ reliable?_______.

b. Estimate the IRR for each project​ (to the nearest 1 %​).________.

c. What is the NPV of each project if the cost of capital is 5 %? 20 %? 50 %​?________.

a. For which of these projects is the IRR rule​ reliable?  ​(Select from the​ drop-down menus.)

The IRR rule is reliable for▼project 1 project 2 project 3. Unless all of the ▼positive negative cash flows of the project precede the ▼negative

positive​ones, the IRR rule may give the wrong answer and should not be used.​ Furthermore, there may be multiple IRRs or the IRR may not exist.

Solutions

Expert Solution

a.

IRR rule is reliable for Project 1. Unless all of the negative cash flow of the project precedes positive ones.

b.

Computation of IRRs using excel:

A

B

C

D

1

Year

Project 1

Project 2

Project 3

2

0

($149)

($827)

$18

3

1

$19

$0

$39

4

2

$42

$0

$62

5

3

$61

$7,002

$81

6

4

$79

($6,508)

($247)

7

IRR

10.70%

10.65%

11.01%

If excel sheet look like above table,

Insert formula “=IRR(B2:B6)” in Cell B7 to get IRR of project 1 as 10.70 %

Insert formula “=IRR(C2:C6)” in Cell C7 to get IRR of project 2 as 10.65 %

Insert formula “=IRR(D2:D6)” in Cell D7 to get IRR of project 3 as 11.01 %

c.

Computation of NPV @ 5 %:

Year

Computation of PV factor

PV Factor @ 5 % (F)

Cash Flow Project 1 C1

PV Project 1 (=C1 x F)

Cash Flow Project 2 C2

PV Project 2 (=C2 x F)

Cash Flow Project 3 C3

PV Project 3 (=C3 x F)

0

1/(1+0.05)^0

1

($149)

($149.00)

($827)

($827.00)

$18

$18.0000

1

1/(1+0.05)^1

0.952380952

$19

$18.09524

$0

$0.0000

$39

$37.1429

2

1/(1+0.05)^2

0.907029478

$42

$38.09524

$0

$0.0000

$62

$56.2358

3

1/(1+0.05)^3

0.863837599

$61

$52.69409

$7,002

$6,048.5909

$81

$69.9708

4

1/(1+0.05)^4

0.822702475

$79

$64.99350

($6,508)

($5,354.1477)

($247)

($203.2075)

NPV

$24.87807

NPV

($132.55684)

NPV

($21.85798)

NPV of Project 1, 2 and 3 at discount rate of 5 % is $24.88, -$ 132.56, -$21.86 respectively.

Computation of NPV @ 20 %:

Year

Computation of PV factor

PV Factor @ 20 % (F)

Cash Flow Project 1 C1

PV Project 1 (=C1 x F)

Cash Flow Project 2 C2

PV Project 2 (=C2 x F)

Cash Flow Project 3 C3

PV Project 3 (=C3 x F)

0

1/(1+0.20)^0

1

($149)

($149.00000)

($827)

($827.0000)

$18

$18.0000

1

1/(1+0.20)^1

0.833333333

$19

$15.83333

$0

$0.0000

$39

$32.5000

2

1/(1+0.20)^2

0.694444444

$42

$29.16667

$0

$0.0000

$62

$43.0556

3

1/(1+0.20)^3

0.578703704

$61

$35.30093

$7,002

$4,052.0833

$81

$46.8750

4

1/(1+0.20)^4

0.482253086

$79

$38.09799

($6,508)

($3,138.5031)

($247)

($119.1165)

NPV

($30.60108)

NPV

$86.58025

NPV

$21.31404

NPV of Project 1, 2 and 3 at discount rate of 20 % is -$30.60, $ 86.58, -$21.31 respectively.

Computation of NPV @ 50 %:

Year

Computation of PV factor

PV Factor @ 50 % (F)

Cash Flow Project 1 C1

PV Project 1 (=C1 x F)

Cash Flow Project 2 C2

PV Project 2 (=C2 x F)

Cash Flow Project 3 C3

PV Project 3 (=C3 x F)

0

1/(1+0.50)^0

1

($149)

($149.00000)

($827)

($827.0000)

$18

$18.0000

1

1/(1+0.50)^1

0.666666667

$19

$12.66667

$0

$0.0000

$39

$26.0000

2

1/(1+0.50)^2

0.444444444

$42

$18.66667

$0

$0.0000

$62

$27.5556

3

1/(1+0.50)^3

0.296296296

$61

$18.07407

$7,002

$2,074.6667

$81

$24.0000

4

1/(1+0.50)^4

0.197530864

$79

$15.60494

($6,508)

($1,285.5309)

($247)

($48.7901)

NPV

($83.98765)

NPV

($37.86420)

NPV

$46.76543

NPV of Project 1, 2 and 3 at discount rate of 50 % is - $83.99, -$ 37.86, -$46.77 respectively.


Related Solutions

You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 -$ 152 $22 $39 $58 $82 Project 2          −826 0 0 7,010 −6,506 Project 3 21 41 61 80   −247 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest1%​). c. What is the NPV of each project if the cost of capital is 5%​?20 %50%​? a. For which of these...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 −$151 $ 21 $ 39 $ 59 $ 80 Project 2                                                −824 00 00 6,999 −6,501 Project 3 2020 40 62 81 −245 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1%​). c. What is the NPV of each project if the cost of capital is 5%​? 20%​? 50%​? a....
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4...
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4 CFA −$2,050    $750    $760    $770    $780 CFB −$4,300 $1,500 $1,518 $1,536 $1,554 Both projects have a required return of 10.25%. What are NPV and IRR of the two projects? If project A and B are mutually exclusive, what is your decision with regard to accepting vs. rejecting each project? Why? What is the crossover rate?
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 If project B is risker than project A, in which project A has WACC = 6.00% while project B has WACC = 8.50%. If these two projects are mutually exclusive, which project should the company accept? Compute: NPV, IRR, MIRR, payback, and discounted payback period for each project. # please with details.
There are two projects with the following cash flows. Years: 0 1 2 3 4 5...
There are two projects with the following cash flows. Years: 0 1 2 3 4 5 Project 1: -210 125 125 175 175 -400 Project 2:  300 -95 -75 -125 -400 600 a. What are the NPVs of these two projects if market interest rate is 3%? b. With the interest rate of 6%, please modified these two projects to let them have only one IRR for each one of them. (That means the sign of cash flows of each project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
Projects A and B have the following cash flows: year A B 0 -5000 -5000 1...
Projects A and B have the following cash flows: year A B 0 -5000 -5000 1 2000 5000 2 0 1500 3 3000 1500 4 5000 1500 What is the IRR of the project A? Please write an answer in decimals. For example, 12.34% would be 0.1234. Also, round your answer to the fourth decimal.
⦁   The net cash flows associated with two projects are as follows: Year   0 1 2...
⦁   The net cash flows associated with two projects are as follows: Year   0 1 2 3 4 5 6 A   (90,000)   0 30,000   40,000   45,000   50,000   50,000 B   (60,000)   24,000   23,000   20,000   18,000   15,000   12,000 The required rate of return for both projects is 9.00%. ⦁   If the projects are independent, which projects would be accepted? ⦁   If the projects are mutually exclusive and have no replacement, which project is preferred? ⦁   If the projects are mutually exclusive and...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2...
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2 7,360 3 4,800 4 −1,640 Assuming the appropriate interest rate is 7 percent, what is the MIRR for this project using the discounting approach?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT