Question

In: Finance

There are two projects with the following cash flows. Years: 0 1 2 3 4 5...

There are two projects with the following cash flows.

Years: 0 1 2 3 4 5

Project 1: -210 125 125 175 175 -400

Project 2:  300 -95 -75 -125 -400 600

a. What are the NPVs of these two projects if market interest rate is 3%?

b. With the interest rate of 6%, please modified these two projects to let them have only one IRR for each one of them. (That means the sign of cash flows of each project only changes for one time.) And then, calculate the Modified IRRs.

c. With the interest rate of 6%, compute the discounted payback periods of both projects.

d. Please calculate the IRR of incremental cash flows based on two projects.

Solutions

Expert Solution

a) NPV can be calculated by NPV function in excel

NPV of Project 1 = -$0.2248

NPV of Project 2 = $184.85

b) We modify the cash-flows

For project 1, the negative cash-flow is discounted back to year 0 using 6% rate so that the sign changes only once

For project 2, the positive cash-flow is discounted back to year 0 using 6% rate so that the sign changes only once

Here, MIRR for Project 1 = 6.30%

MIRR for Project 2 = 13.06%

c. The discounted payback period is the time period taken for the cumulative discounted cash-flows to become 0

In Project 1, cumulative discounted cash-flows to become 0 after year 1

In Project 2, cumulative discounted cash-flows is positive upfront. Hence the discounted payback period cannot be estimated.

d)

Since, the incremental cash-flows have sign change more than once, IRR cannot be calculated.


Related Solutions

Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 -$ 152 $22 $39 $58 $82 Project 2          −826 0 0 7,010 −6,506 Project 3 21 41 61 80   −247 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest1%​). c. What is the NPV of each project if the cost of capital is 5%​?20 %50%​? a. For which of these...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 −$151 $ 21 $ 39 $ 59 $ 80 Project 2                                                −824 00 00 6,999 −6,501 Project 3 2020 40 62 81 −245 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1%​). c. What is the NPV of each project if the cost of capital is 5%​? 20%​? 50%​? a....
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4...
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4 CFA −$2,050    $750    $760    $770    $780 CFB −$4,300 $1,500 $1,518 $1,536 $1,554 Both projects have a required return of 10.25%. What are NPV and IRR of the two projects? If project A and B are mutually exclusive, what is your decision with regard to accepting vs. rejecting each project? Why? What is the crossover rate?
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 If project B is risker than project A, in which project A has WACC = 6.00% while project B has WACC = 8.50%. If these two projects are mutually exclusive, which project should the company accept? Compute: NPV, IRR, MIRR, payback, and discounted payback period for each project. # please with details.
You have 3 projects with the following cash​ flows: Year    0       1   2     ...
You have 3 projects with the following cash​ flows: Year    0       1   2      3         4 Project 1   -$149   $19   $42   $61      $79 Project 2   -827      0   0   7,002   -6,508 Project 3   18          39   62   81      -247 a. For which of these projects is the IRR rule​ reliable?_______. b. Estimate the IRR for each project​ (to the nearest 1 %​).________. c. What is the NPV of each project if the cost of capital is 5...
Use these cash flows to answer the following questions: Year 0 1 2 3 4 5...
Use these cash flows to answer the following questions: Year 0 1 2 3 4 5 6 A (4,000) 800 1,400 1,300 1,200 1,100 1,000 B (2,000) 700 1,300 1,200 0 0 0 a. Calculate the NPV for projects A and B using a 20 percent discount rate (write the calculate keys that you use to get the answer). b Calculate the Equivalent Annual Annuity (EAA) for projects A and B using a 20 percent discount rate (write the calculate...
Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000...
Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000 $2,200 $3,300 $2,500 $2,500 $2,300 $2,100 A. Payback The company requires all projects to payback within 3 years. Calculate the payback period. Should it be accepted or rejected? B. Discounted Payback Calculate the discounted payback using a discount rate of 10%. Should it be accepted or rejected? C. IRR Calculate the IRR for this project. Should it be accepted or rejected? D. NPV Calculate...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5
  Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT