In: Finance
Projects A and B have the following cash flows:
year |
A |
B |
0 |
-5000 |
-5000 |
1 |
2000 |
5000 |
2 |
0 |
1500 |
3 |
3000 |
1500 |
4 |
5000 |
1500 |
What is the IRR of the project A?
Please write an answer in decimals. For example, 12.34% would be 0.1234.
Also, round your answer to the fourth decimal.
Internal Rate of Return (IRR) for the Project
Step – 1, Firstly calculate NPV at a guessed discount Rate, Say 25%
Year |
Annual Cash Flow ($) |
Present Value factor at 25% |
Present Value of Cash Flow ($) |
1 |
2,000 |
0.80000 |
1,600.00 |
2 |
0 |
0.64000 |
0 |
3 |
3,000 |
0.51200 |
1,536.00 |
4 |
5,000 |
0.40960 |
2,048.00 |
TOTAL |
5,184.00 |
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $5,184.00 - $5,000
= $184
Step – 2, NPV at 25% is positive, Calculate the NPV again at a higher discount rate, Say 27%
Year |
Annual Cash Flow ($) |
Present Value factor at 27% |
Present Value of Cash Flow ($) |
1 |
2,000 |
0.78740 |
1,574.80 |
2 |
0 |
0.62000 |
0 |
3 |
3,000 |
0.48819 |
1,464.57 |
4 |
5,000 |
0.38440 |
1,922.01 |
TOTAL |
4,961.38 |
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $4,961.38 -- $5,000
= -$38.62 (Negative NPV)
Therefore IRR = R1 + NPV1(R2-R1)
NPV1-NPV2
= 0.25 + [$184 x (0.27 – 0.25)]
$184 – (-$38.62)
= 0.25 + 0.0165
= 0.2665
= 26.65%
“Therefore, the Internal Rate of Return (IRR) for the Project = 0.2665 (in decimals)”
NOTE
The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.