In: Finance
Projects A and B have the following cash flows:
| 
 year  | 
 A  | 
 B  | 
| 
 0  | 
 -5000  | 
 -5000  | 
| 
 1  | 
 2000  | 
 5000  | 
| 
 2  | 
 0  | 
 1500  | 
| 
 3  | 
 3000  | 
 1500  | 
| 
 4  | 
 5000  | 
 1500  | 
What is the IRR of the project A?
Please write an answer in decimals. For example, 12.34% would be 0.1234.
Also, round your answer to the fourth decimal.
Internal Rate of Return (IRR) for the Project
Step – 1, Firstly calculate NPV at a guessed discount Rate, Say 25%
| 
 Year  | 
 Annual Cash Flow ($)  | 
 Present Value factor at 25%  | 
 Present Value of Cash Flow ($)  | 
| 
 1  | 
 2,000  | 
 0.80000  | 
 1,600.00  | 
| 
 2  | 
 0  | 
 0.64000  | 
 0  | 
| 
 3  | 
 3,000  | 
 0.51200  | 
 1,536.00  | 
| 
 4  | 
 5,000  | 
 0.40960  | 
 2,048.00  | 
| 
 TOTAL  | 
 5,184.00  | 
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $5,184.00 - $5,000
= $184
Step – 2, NPV at 25% is positive, Calculate the NPV again at a higher discount rate, Say 27%
| 
 Year  | 
 Annual Cash Flow ($)  | 
 Present Value factor at 27%  | 
 Present Value of Cash Flow ($)  | 
| 
 1  | 
 2,000  | 
 0.78740  | 
 1,574.80  | 
| 
 2  | 
 0  | 
 0.62000  | 
 0  | 
| 
 3  | 
 3,000  | 
 0.48819  | 
 1,464.57  | 
| 
 4  | 
 5,000  | 
 0.38440  | 
 1,922.01  | 
| 
 TOTAL  | 
 4,961.38  | 
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $4,961.38 -- $5,000
= -$38.62 (Negative NPV)
Therefore IRR = R1 + NPV1(R2-R1)
NPV1-NPV2
= 0.25 + [$184 x (0.27 – 0.25)]
$184 – (-$38.62)
= 0.25 + 0.0165
= 0.2665
= 26.65%
“Therefore, the Internal Rate of Return (IRR) for the Project = 0.2665 (in decimals)”
NOTE
The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.