Question

In: Finance

You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...

You have 3 projects with the following cash​ flows:

Year

0

1

2

3

4

Project 1

-$ 152

$22

$39

$58

$82

Project 2

         −826

0

0

7,010

−6,506

Project 3

21

41

61

80

  −247

a. For which of these projects is the IRR rule​ reliable?

b. Estimate the IRR for each project​ (to the nearest1%​).

c. What is the NPV of each project if the cost of capital is

5%​?20 %50%​?

a. For which of these projects is the IRR rule​ reliable?  ​(Select from the​ drop-down menus.)

The IRR rule is reliable for___?Unless all of the____? negative/positive? cash flows of the project precede the negative/positive?​ones, the IRR rule may give the wrong answer and should not be used.​ Furthermore, there may be multiple IRRs or the IRR may not exist.

2.You are considering making a movie. The movie is expected to cost $ 10.0million upfront and take a year to produce. After​ that, it is expected to make $ 5.0 million in the year it is released and $ 2.0$ million for the following four years. What is the payback period of this​ investment? If you require a payback period of two​ years, will you make the​ movie? Does the movie have positive NPV if the cost of capital is 10.0%​?

Solutions

Expert Solution

1.a) The IRR rule is reliable for Project 1. Unless all of the positive cash flows of the project precede the negative ​ones, the IRR rule may give the wrong answer and should not be used.​ Furthermore, there may be multiple IRRs or the IRR may not exist.

1 b)

1. c)

2)


Related Solutions

You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year 0 1 2 3 4 Project 1 −$151 $ 21 $ 39 $ 59 $ 80 Project 2                                                −824 00 00 6,999 −6,501 Project 3 2020 40 62 81 −245 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1%​). c. What is the NPV of each project if the cost of capital is 5%​? 20%​? 50%​? a....
You have 3 projects with the following cash​ flows: Year    0       1   2     ...
You have 3 projects with the following cash​ flows: Year    0       1   2      3         4 Project 1   -$149   $19   $42   $61      $79 Project 2   -827      0   0   7,002   -6,508 Project 3   18          39   62   81      -247 a. For which of these projects is the IRR rule​ reliable?_______. b. Estimate the IRR for each project​ (to the nearest 1 %​).________. c. What is the NPV of each project if the cost of capital is 5...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100...
​​ Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 If project B is risker than project A, in which project A has WACC = 6.00% while project B has WACC = 8.50%. If these two projects are mutually exclusive, which project should the company accept? Compute: NPV, IRR, MIRR, payback, and discounted payback period for each project. # please with details.
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4...
Projects A and B have the following cash flows respectively: Year 0 1 2 3 4 CFA −$2,050    $750    $760    $770    $780 CFB −$4,300 $1,500 $1,518 $1,536 $1,554 Both projects have a required return of 10.25%. What are NPV and IRR of the two projects? If project A and B are mutually exclusive, what is your decision with regard to accepting vs. rejecting each project? Why? What is the crossover rate?
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
There are two projects with the following cash flows. Years: 0 1 2 3 4 5...
There are two projects with the following cash flows. Years: 0 1 2 3 4 5 Project 1: -210 125 125 175 175 -400 Project 2:  300 -95 -75 -125 -400 600 a. What are the NPVs of these two projects if market interest rate is 3%? b. With the interest rate of 6%, please modified these two projects to let them have only one IRR for each one of them. (That means the sign of cash flows of each project...
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT