Question

In: Finance

A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...

A project has the following cash flows :

Year Cash Flows
0 −$12,000
1 5,290
2 7,630
3 5,040
4 −1,580


Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach?

19.21%

15.23%

13.96%

11.63%

17.77%

Solutions

Expert Solution

Year Cash Flow Calculations Future Value
1 $          5,290 =5290*1.10^3 $     7,040.99
2 $          7,630 =7630*1.10^2 $     9,232.30
3 $          5,040 =5040*1.10^11 $     5,544.00
4 $         -1,580 =-1580*1.10^0 $   -1,580.00
Total $   20,237.29
We need to calculate at which rate present value of $20237.3 will become 12000
It can be calculated by using following formula
PV= FV/(1+r)^n
Where,
FV= Future Value
PV = Present Value
r = Interest rate
n= periods in number
12000=$20237.30/(1+r)^4
r =13.96%
Therefore MIRR is 13.96%

Related Solutions

A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2...
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2 7,360 3 4,800 4 −1,640 Assuming the appropriate interest rate is 7 percent, what is the MIRR for this project using the discounting approach?
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800...
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800 3 51,600 4 28,100 The required return is 8.3 percent. What is the profitability index for this project?
1) A project has the following cash flows: Year 0 -$22,500, Year 1 $12,650, Year 2...
1) A project has the following cash flows: Year 0 -$22,500, Year 1 $12,650, Year 2 $10,900, and Year 3 $6,500. What is the IRR of the project? Please round your answer to two decimal places. 2) Following question 1, suppose the cost of capital is 15%. Would you accept or reject the project according to the IRR criterion? Accept or Reject 3) Following questions 1 and 2, which of the following statements about the IRR rule is false? -...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2 7,600 3 6,100     What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)      NPV $       What is the NPV at a discount rate of 9 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $   ...
A project has the following cash flows. What is the payback period? Year 0 1 2...
A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 cash flow -$14500 $2200 $4800   $6500 $7500 A project has the following cash flows. What is the internal rate of return? Year 0 1 2 3 Cash flows -$89300 $32900 $64200 $5800 A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 Cash flow -$28000 $11600 $11600 $6500 $6500 And how to solve this...
Yellow Day has a project with the following cash flows: Year Cash Flows 0 −$27,000 1...
Yellow Day has a project with the following cash flows: Year Cash Flows 0 −$27,000 1 10,550 2 20,300 3 9,720 4 −3,600 What is the MIRR for this project using the reinvestment approach? The interest rate is 7 percent
POD has a project with the following cash flows: Year Cash Flows 0 −$255,000 1 146,800...
POD has a project with the following cash flows: Year Cash Flows 0 −$255,000 1 146,800 2 164,300 3 129,400 The required return is 9.6 percent. What is the profitability index for this project?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT