Question

In: Operations Management

Consider the following work breakdown structure: Given a due date of 210 days, what is the...

Consider the following work breakdown structure: Given a due date of 210 days, what is the earliest you can start activity D without delaying the project?

Time Estimates (days)

Activity

Precedes

Optimistic

Most Likely

Pessimistic

Start

A,B

-

-

-

A

C,D

44

50

56

B

D

45

60

75

C

E

42

45

48

D

F

31

40

49

E

F

27

36

39

F

End

58

70

82

50

60

70

100

140

Solutions

Expert Solution

We find the expected duration for each activity as shown below:

Based on the expected durations and predecessor relationships, we prepare a project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly, LFT & LST are calculated during the backward pass.

Project duration = 200 as seen from the network diagram.

Required duration = 210.

As seen from above, the Earliest start for Activity D = EST in the box for D = 60.

Hence,

The Earliest we can start activity D without delaying the project = Earliest start for D = 60

Answer: 60

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!


Related Solutions

Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should...
Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should include at least three tasks with at least three subtasks each.
Project management How to create a intergration of a work breakdown structure and organizational breakdown structure...
Project management How to create a intergration of a work breakdown structure and organizational breakdown structure on a baby sensor project that prevents babies from being left in a car ?
Explain the purpose and structure of a work breakdown structure Discuss the advantages and disadvantages of...
Explain the purpose and structure of a work breakdown structure Discuss the advantages and disadvantages of using a Gantt Chart
From the information given below, compute the time in days for the following notes: Date of...
From the information given below, compute the time in days for the following notes: Date of Note Due Date Time in Days 1. June 28, 2010 August 10, 2010 days 2. March 5, 2010 August 12, 2010 days 3. April 20, 2010 July 17, 2010 days 4. January 12, 2010 May 15, 2010 days 5. December 17, 2010 February 2, 2011 days From the information given below, determine the due date for the following notes:        Date of Note       Time...
4. What is the Work Breakdown Structure (WBS)? Explain the relation between time management and WBS.
4. What is the Work Breakdown Structure (WBS)? Explain the relation between time management and WBS.
Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20...
Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20 30 B 30 50 C 10 25 D 16 80 E 18 12 Calculate for each job the relative critical ratio. Analyze the calculated critical ratio. Basing on the calculated CR, specify the scheduling order of each job. Justify your answer. Specify and explain a second dispatch rule that can be adopted.    Among the two rules which seems to be the most effective....
You owe suppliers balances at 90 days + past due for contract work. -What is the...
You owe suppliers balances at 90 days + past due for contract work. -What is the purpose of a Mechanics Lien for vendors demanding payment?
Looking for a detailed work breakdown structure for a football stadium. Please do not answer it...
Looking for a detailed work breakdown structure for a football stadium. Please do not answer it with a definition. The more details the better.
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of...
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of them and discuss how they relate to each other. Given the system goals, requirements, and scope as they are currently understood, is the project schedule reasonable? Why or why not?
Use Zeller’s algorithm to figure out the days of the week for a given date in...
Use Zeller’s algorithm to figure out the days of the week for a given date in c. W = (d + 13(m+1)/5 + y + y/4 + c/4 - 2c + 6) mod 7 Y is the year minus 1 for January or February, and the year for any other month y is the last 2 digits of Y c is the first 2 digits of Y d is the day of the month (1 to 31) m is the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT