Question

In: Operations Management

Project management How to create a intergration of a work breakdown structure and organizational breakdown structure...

Project management

How to create a intergration of a work breakdown structure and organizational breakdown structure on a baby sensor project that prevents babies from being left in a car ?

Solutions

Expert Solution

Creating a piece breakdown structure (WBS) helps you be each complete and distinctive when managing a undertaking: thinking in element is central when planning your challenge, but you also need to don't forget the huge snapshot. When you fail to identify a predominant part of your projects work, you gained have the hazard to element it. A work breakdown constitution is vital.

The diagram here shows that the entire assignment, represented as a level 1 element, can be subdivided into level 2 accessories, and some or all level 2 accessories can also be subdivided into stage 3 accessories.

That you would be able to continue to subdivide all the add-ons within the equal method except you attain a point at which you suppose the components you defined are sufficiently precise for planning and management functions. At this factor, you now have level n components, the place n is the quantity of the lowest-level component in a distinct WBS branch. Stage n components are referred to as work programs.


Develop a piece breakdown structure to check the hierarchy of a undertaking.
Believe you're dependable for creating and imparting a new coaching application to your institution. To get started, you'd improve a WBS for this project as follows:

assess the principal deliverables or merchandise to be produced.
Ask your self, What important intermediate or ultimate merchandise or deliverables have to be produced to gain the task targets?
you may determine the next items:
coaching software wishes assertion
training software design
Participant notebooks
knowledgeable teacher
program trying out
training program presentation
Divide each of these essential deliverables into its factor deliverables within the same method.
Opt for any individual of those deliverables to begin with. Feel you prefer coaching software wishes statement.
Ask, What intermediate deliverables have got to i've so i will be able to create the wants statement?
you may determine that you require the next:
Interviews of capabilities contributors
A assessment of substances discussing the needs for the software
A record summarizing the wishes this program will deal with
Divide each of these work pieces into its factor components.
Consider you decide upon to with Interviews of competencies participants.
Ask, What deliverables must I have got to entire these interviews?
you may also make a decision that you have got to produce the next deliverables:
chosen interviewees
Interview questionnaire
Interview time table
completed interviews
file of interview Creating a work breakdown structure (WBS) helps you be both comprehensive and specific when managing a project: Thinking in detail is critical when planning your project, but you also need to consider the big picture. If you fail to identify a major part of your project’s work, you won’t have the chance to detail it. A work breakdown structure is key.

The diagram here shows that the entire project, represented as a Level 1 component, can be subdivided into Level 2 components, and some or all Level 2 components can be subdivided into Level 3 components.

You can continue to subdivide all the components in the same manner until you reach a point at which you think the components you defined are sufficiently detailed for planning and management purposes. At this point, you now have Level “n” components, where n is the number of the lowest-level component in a particular WBS branch. Level “n” components are called work packages.


Develop a work breakdown structure to determine the hierarchy of a project.
Suppose you’re responsible for creating and presenting a new training program for your organization. To get started, you’d develop a WBS for this project as follows:

Determine the major deliverables or products to be produced.
Ask yourself, “What major intermediate or final products or deliverables must be produced to achieve the project’s objectives?”
You may identify the following items:
Training program needs statement
Training program design
Participant notebooks
Trained instructor
Program testing
Training program presentation
Divide each of these major deliverables into its component deliverables in the same manner.
Choose any one of these deliverables to begin with. Suppose you choose Training program needs statement.
Ask, “What intermediate deliverables must I have so I can create the needs statement?”
You may determine that you require the following:
Interviews of potential participants
A review of materials discussing the needs for the program
A report summarizing the needs this program will address
Divide each of these work pieces into its component parts.
Suppose you choose to start with Interviews of potential participants.
Ask, “What deliverables must I have to complete these interviews?”
You may decide that you have to produce the following deliverables:
Selected interviewees
Interview questionnaire
Interview schedule
Completed interviews
Report of interview findings


Related Solutions

Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should...
Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should include at least three tasks with at least three subtasks each.
Book: Operations And Supply Chain Management Jacobs & Chase 14e Explain Work Breakdown structure, how it...
Book: Operations And Supply Chain Management Jacobs & Chase 14e Explain Work Breakdown structure, how it is used to organize a project. (approx.100 words)
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of...
Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of them and discuss how they relate to each other. Given the system goals, requirements, and scope as they are currently understood, is the project schedule reasonable? Why or why not?
Developing a detailed work breakdown structure (WBS) for a system development project is a basic function...
Developing a detailed work breakdown structure (WBS) for a system development project is a basic function of project management. What part should be played by systems engineering in the definition of the WBS in addition to detailing the section named “System’s Engineering”.
Week 3 Discussion: Creating a Work Breakdown Structure (WBS) * The project is building and opening...
Week 3 Discussion: Creating a Work Breakdown Structure (WBS) * The project is building and opening up a small 24 hour coffee shop* The work breakdown structure can be confusing, especially for new project managers. Despite its name, it doesn’t actually involve breaking down work; it involves breaking down deliverables. This, among others, is one of several reasons why you need a thorough understanding of the work breakdown structure before you can create your own. What is a WBS or...
Create an implementation plan (work breakdown structure) that walks through the process step-by-step and provides a...
Create an implementation plan (work breakdown structure) that walks through the process step-by-step and provides a schedule for each milestone. Explain your strategies for implementing the change within the organization, such as training or process change. Explain your strategies for monitoring the project. Explain any risks or challenges that you anticipate, and how you plan to overcome those risks. THIS IS FOR THE MAYO CLINIC ANY HELP IS NEEDED!
4. What is the Work Breakdown Structure (WBS)? Explain the relation between time management and WBS.
4. What is the Work Breakdown Structure (WBS)? Explain the relation between time management and WBS.
Question 1 Organizational structure impact greatly on the management of projects: a. Given that a project...
Question 1 Organizational structure impact greatly on the management of projects: a. Given that a project is to be undertaken by either the Ministry of Agriculture (a highly functional organization) or the Hunger Project (a projectized organization) with the aid of diagrams, critically assess the potential impact the organizational   structures could have on the management of the project in the respective organizations b. Using a diagram to illustrate that organizational structure is a continuum, critically analyze the effectiveness of a...
Explain the purpose and structure of a work breakdown structure Discuss the advantages and disadvantages of...
Explain the purpose and structure of a work breakdown structure Discuss the advantages and disadvantages of using a Gantt Chart
How can you make a work breakdown structure in covid-19 safeguard system?
How can you make a work breakdown structure in covid-19 safeguard system?