Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of...

Show a work breakdown structure and a project schedule as a Gantt Chart. Explain both of them and discuss how they relate to each other.

Given the system goals, requirements, and scope as they are currently understood, is the project schedule reasonable? Why or why not?

Solutions

Expert Solution

Work Breakdown Structure :

It is a systematic approach of organizing work. It divides the total work in to number of sub parts in a hierarchical manner for better planning, monitoring and controlling. It facilitates the better management practices to complete a particular project successfully. It clearly states the each and every element of project such as cost, resources, time schedule, tasks, risk associated with the project etc. I t is the work plan of whole project

Gantt Chart :

It is to be developed on the basis of work break down structure. It is nothing but a bar chart that helps to see the work status whether it is completed or not or what percentage of work is completed and not completed. It is very much helpful to find the critical paths in your project and delays in project .

Relationship between Work break down structure and Gantt Chart :

Work breakdown structure is to be developed by using the main aspects of project. The total project work is to be divided in to branches depending upon its nature and tasks are to be assigned to each branch in systematically. To prepare this we need full pledged information of project. And then work will be started. Now we need to develop gantt chart which is the part of work break down chart. This gantt chart is a bar chart tells you the progress of work. It is a daily report of work which helps us to make changes in break down structure if need to complete the project by a stipulated time.

Sample work break down structure and gantt chart :

To see it follow these two links :

https://tex.stackexchange.com/questions/81809/work-breakdown-structure-wbs-tikz

https://www.rff.com/gantt2.php

Given the system goals, requirements, and scope as they are currently understood, is the project schedule reasonable? Why or why not?

System goals are the project objectives which are the roots of project to make planning and scheduling. It defines the requirements to complete the project. Scope defines the boundaries of the project which states the internal and external factors effect the project and also included and excluded aspects in a project. These are all part of planning and scheduling the project.

For this analysis it is better to develop matrix structure to analyse the elements of project for better understanding, planning, scheduling and implementing to yield the best results. That particular matrix will prioritise the elements pertaining to scope, requirements etc.

It is very important to understand the system goals , requirements and scope of project to plan, schedule project and to complete successfully with our rising costs. But sometimes there may be inconsistency among the such elements at the time of planning and scheduling and another reason may be scarce resources. It may not be fine to adopt change at every time.


Related Solutions

Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following...
1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following set of tasks. Use the task number, duration, and dependencies of each task given and construct a schedule so that the project is completed in the least number of days possible. Include a management reserve of approximately 10%. Task Subject Duration Dependencies Slack (3 pts) 1.0 Project Kickoff 2 none 2.1 Install & Test Database Software 2 1.0 2.2 Configure & Test Database Web...
Gantt chart for home renovation project
Gantt chart for home renovation project
Project management How to create a intergration of a work breakdown structure and organizational breakdown structure...
Project management How to create a intergration of a work breakdown structure and organizational breakdown structure on a baby sensor project that prevents babies from being left in a car ?
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup...
Based on the information below, create a project schedule (Gantt Chart). Assign tasks to either Workgroup or Individual. Project: Vacation Team: "Workgroup 1", "Individual" Start/End: February 19 - May 26 START A. February 19: Vacation participation must be confirmed Time allotted: 7 days i. Confirm participation Time needed: 1 day ii. Research vacation deals Time needed: 1 days iii. Decide on destination Time needed: 2 days iv. Create travel list Time needed: 1 day Slack available: 2 days B. February...
Explain the purpose and structure of a work breakdown structure Discuss the advantages and disadvantages of...
Explain the purpose and structure of a work breakdown structure Discuss the advantages and disadvantages of using a Gantt Chart
Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should...
Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should include at least three tasks with at least three subtasks each.
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a...
Draw a Gantt chart for A Computerised Administrative System. It Is a new project for a computerised Human Resource Information system. The company is switching to paper less. A WBS has to be created/invented for the new project
Consider the following work breakdown structure: What is the probability of finishing the project at exactly...
Consider the following work breakdown structure: What is the probability of finishing the project at exactly 201 days? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B - - - A C,D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 1. 0. 0.9. 0.6. 2.5.
Compare the main strengths and weaknesses of the Gantt chart and PERT for project management, and...
Compare the main strengths and weaknesses of the Gantt chart and PERT for project management, and give your opinion on which you believe is the most effective for project management.