In: Finance
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 10 percent. |
Year | Dry Prepreg | Solvent Prepreg | ||||
0 | –$ | 1,830,000 | –$ | 815,000 | ||
1 | 1,113,000 | 440,000 | ||||
2 | 926,000 | 730,000 | ||||
3 | 763,000 | 416,000 | ||||
a. |
What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.) |
b. |
What is the NPV for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.) |
c. |
What is the IRR for both projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) |
d. |
Calculate the incremental IRR for the cash flows. (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) |
a.
Calculation of Payback Period of both Projects:
Payback period helps to determine the time required to recover initial investment.
It is calculated as:
Payback Period: Total Initial Investment/ Annual Net Cash Inflow.
In case annual cash inflow is not uniform, we have to first calculate cummulative cash flow as given in solution:
Project Dry | ||
Year | Annual Cash Flow | Cummulative Cash Flow |
1 | 1113000 | 1113000 |
2 | 926000 | 2039000 |
3 | 763000 | 2802000 |
In the given project, you can see that initial investment is $ 1830000, which can be recovered in cash flow of second year:
Now Payback period will be calculated as:
=Year 1 + (1830000-1113000)/926000
= 1+ ( 717000/926000)
=1.774 years
(1830000-1113000) signifies additional cash flow required to recover initial investment and it is divided by $ 926000 i.e. cash flow earned in year 2 assuming it is earned uniformly over period
Project Solvent | ||
Year | Annual Cash Flow | Cummulative Cash Flow |
1 | 440000 | 440000 |
2 | 730000 | 1170000 |
3 | 416000 | 1586000 |
In the given project, you can see that initial investment is $ 815000, which can be recovered in cash flow of second year:
Now Payback period will be calculated as:
=Year 1 + (815000-440000)/730000
= 1+ ( 375000/730000)
=1.514 years
(b) Calculation of NPV of both projects
Net Present Value technique is a discounted cash flow technique that calculates the present value of cash flow earned from investment and compare it with Present Value of Cash outflow and If NPV is 0 or greater than 0 than it is accepted as required rate of return is achieved.
Calculation of NPV of both projects are as follow:
Project Dry | |||
Year | Annual Cash Flow (a) | Present Value Factor @ 10% (b) | Present Value (a*b) |
0 | -1830000 | 1 | -1830000 |
1 | 1113000 | 0.909 | 1011717 |
2 | 926000 | 0.826 | 764876 |
3 | 763000 | 0.751 | 573013 |
Total | 519606 | ||
Project Solvent | |||
Year | Annual Cash Flow (a) | Present Value Factor @ 10% (b) | Present Value (a*b) |
0 | -815000 | 1 | -815000 |
1 | 440000 | 0.909 | 399960 |
2 | 730000 | 0.826 | 602980 |
3 | 416000 | 0.751 | 312416 |
Total | 500356 |
NPV of Both Projects are positive in this case.
(c) Calculation of IRR of both Projects:
IRR technique determines the discount rate at which Present Value of Cash Inflow is equal to Present Value of Cash Outflow. Therefore it is not necessary that calculated discount rate is equal to desired discount rate. If our desired rate of return is achieved, then project is accepted.
Calculation is as follow:
Lower Rate + ((NPV at Lower Rate/ (NPV at Lower Rate- NPV at Higher Rate))*(HR-LR))
Project Dry
Assume discount rate @ 25% | |||
Project Dry | |||
Year | Annual Cash Flow (a) | Present Value Factor @ 25% (b) | Present Value (a*b) |
0 | -1830000 | 1 | -1830000 |
1 | 1113000 | 0.800 | 890400 |
2 | 926000 | 0.640 | 592640.00 |
3 | 763000 | 0.512 | 390656.00 |
Total | 43696.00 |
Assume discount rate @ 30% | |||
Project Dry | |||
Year | Annual Cash Flow (a) | Present Value Factor @ 30% (b) | Present Value (a*b) |
0 | -1830000 | 1 | -1830000 |
1 | 1113000 | 0.769 | 855897.00 |
2 | 926000 | 0.592 | 548192.00 |
3 | 763000 | 0.455 | 347165.00 |
Total | -78746.00 |
IRR = 25 +((43296/(43296-(-78746))*(30-25))
= 25+(43296/122042)*5
= 25+ 1.77
= 26.77 % approx
Project Solvent:
Assume discount rate @ 40% | |||
Project Solvent | |||
Year | Annual Cash Flow (a) | Present Value Factor @ 40% (b) | Present Value (a*b) |
0 | -815000 | 1 | -815000 |
1 | 440000 | 0.714 | 314160 |
2 | 730000 | 0.510 | 372300.00 |
3 | 416000 | 0.364 | 151424.00 |
Total | 22884.00 |
Assume discount rate @ 45% | |||
Project Solvent | |||
Year | Annual Cash Flow (a) | Present Value Factor @ 45% (b) | Present Value (a*b) |
0 | -815000 | 1 | -815000 |
1 | 440000 | 0.690 | 303600 |
2 | 730000 | 0.476 | 347480.00 |
3 | 416000 | 0.328 | 136448.00 |
Total | -27472.00 |
= 40 +((22884/(22884-(-27472))*(45-40))
= 40 +(22884/50356)*5
= 40 + 2.27
= 42.27 % approx
(d) Calculation of Incremental IRR
This technique is used, when there are two investment opportunties which are competitive in nature and further it involves different amount of investment.
Calculation is as follow:
Year | Annual Cash Flow Project Dry | Annual Cash Flow Project Solvent | Difference in Cash Flow |
0 | -1830000 | -815000 | -1015000 |
1 | 1113000 | 440000 | 673000 |
2 | 926000 | 730000 | 196000 |
3 | 763000 | 416000 | 347000 |
Assume Disc Rate 10% | |||
Year | Differential Cash Flow (a) | Present Value Factor @ 10% (b) | Present Value (a*b) |
0 | -1015000 | 1 | -1015000 |
1 | 673000 | 0.909 | 611757.00 |
2 | 196000 | 0.826 | 161896.00 |
3 | 347000 | 0.751 | 260597.00 |
Related SolutionsConsider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive
projects for Tokyo Rubber Company. Assume the discount rate for
both projects is 12 percent.
Year
Dry Prepreg
Solvent Prepreg
0
–$
1,800,000
–$
800,000
1
1,110,000
425,000
2
920,000
700,000
3
760,000
410,000
a.
What is the payback period for both projects? (Do not
round intermediate calculations. Round your answers to 2 decimal
places, e.g., 32.16.)
b.
What is the NPV for both projects? (Do not round
intermediate...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive
projects for Tokyo Rubber Company. Assume the discount rate for
both projects is 8 percent.
Year
Dry Prepreg
Solvent Prepreg
0
–$
1,810,000
–$
805,000
1
1,111,000
430,000
2
922,000
710,000
3
761,000
412,000
a.
What is the payback period for both projects? (Do not
round intermediate calculations. Round your answers to 2 decimal
places, e.g., 32.16.)
Payback
period
Dry Prepeg
years
Solvent Prepeg
years
b.
What is...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...Consider the following cash flows of two mutually exclusive
projects for Tokyo Rubber Company. Assume the discount rate for
both projects is 9 percent.
YearDry PrepregSolvent Prepreg
0–$1,850,000 –$825,000
1 1,115,000 450,000
2 930,000 750,000
3 765,000 420,000
a.
What is the payback period for both projects? (Do not round
intermediate calculations. Round your answers to 2 decimal places,
e.g., 32.16.)
b.
What is the NPV for both projects? (Do not round intermediate
calculations. Round your answers to 2 decimal places,...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive
projects for Tokyo Rubber Company. Assume the discount rate for
both projects is 7 percent.
Year
Dry Prepreg
Solvent Prepreg
0
–$
1,870,000
–$
835,000
1
1,117,000
460,000
2
934,000
770,000
3
767,000
424,000
a.
What is the payback period for both projects? (Do not
round intermediate calculations. Round your answers to 2 decimal
places, e.g., 32.16.)
b.
What is the NPV for both projects? (Do not round
intermediate calculations....
Comparing Investment Criteria. Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber...Comparing Investment Criteria. Consider the following cash flows
of two mutually exclusive projects for Tokyo Rubber Company. Assume
the discount rate for both projects is 8%
Year
Deepwater
Fishing
New Submarine Ride
0
-$1,700,000
-$750,000
1
1,100,000
375,000
2
900,000
600,000
3
750,000
390,000
b) Based on the NPV, which project should be taken?
c) Based on IRR, which project should be taken?
Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the...Consider the following cash flows of two mutually exclusive
projects for Spartan Rubber Company. Assume the discount rate for
both projects is 7 percent.
Year
Dry Prepreg
Solvent Prepreg
0
–$
1,890,000
–$
900,000
1
1,119,000
470,000
2
938,000
790,000
3
769,000
428,000
a. What is the payback period for each project?
(Do not round intermediate calculations and round your
answers to 2 decimal places, e.g., 32.16.)
Payback period
Dry Prepreg
years
Solvent Prepreg
years
b. What is the NPV...
Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the...Consider the following cash flows of two mutually exclusive
projects for Spartan Rubber Company. Assume the discount rate for
both projects is 8 percent.
Year
Dry Prepreg
Solvent Prepreg
0
–$
1,810,000
–$
805,000
1
1,111,000
430,000
2
922,000
710,000
3
761,000
412,000
a. What is the payback period for each project?
(Do not round intermediate calculations and round your
answers to 2 decimal places, e.g., 32.16.)
Payback period
Dry Prepreg
1.92 1.92
Incorrect years
Solvent Prepreg
2.20 2.20
Incorrect...
Consider the following cash flows of two mutually exclusive projects for Braisl Rubber Co. Assume the...Consider the following cash flows of two mutually exclusive
projects for Braisl Rubber Co. Assume the discount rate for both
projects is 9 Percent.
Year
Dry PrePreg
Solvent PrePreg
0
1,820,000
810,000
1
1,112,000
435,000
2
924,000
720,000
3
762,000
414,000
a. What is the payback period for both
projects?
Dry PrePreg
Years
Solvent PrePreg
Years
b. What is the NPV for both projects?
Dry PrePreg
Solvent PrePreg
c. What is the IRR for both projects?
Dry PrePreg
%
Solvent...
Comparing Investment Criteria. Consider the following cash flows of two mutually exclusive projects for Spartan Rubber...Comparing Investment Criteria. Consider the following cash flows
of two mutually exclusive projects for Spartan Rubber
company. Assume the discount rate for both projects is
10 percent.
a. Based on the payback period, which project should be
taken?
b. Based onthe NPV, which project should be taken?
c. Based on the IRR, which project should be
taken?
d. Based on the above analysis, is incremental IRR
analysis necessary? If yes, please conduct the
analysis.
Year
Dry Prepreg
Solvent Prepreg
0
(1,800,000)
(925,000)
1
690,000...
Consider the following two mutually exclusive projects and their Cash Flows ($)Consider the following two mutually exclusive projects and their
Cash Flows ($)Project
C0 C1 C2
C3K
–$100
+$45 +$45 +$60 W
–$150
+$45 +$45 +$125Which statement is correct based on the above information about
Projects K and W?a. If the discount rate is 7.5%, accept project W because the
cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have
the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
ADVERTISEMENT
ADVERTISEMENT
Latest Questions
ADVERTISEMENT
|