Question

In: Accounting

Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the...

Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the discount rate for both projects is 8 percent.

Year Dry Prepreg Solvent Prepreg
0 –$ 1,810,000 –$ 805,000
1 1,111,000 430,000
2 922,000 710,000
3 761,000 412,000


a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Payback period
Dry Prepreg 1.92 1.92 Incorrect years
Solvent Prepreg 2.20 2.20 Incorrect years


b. What is the NPV for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

NPV
Dry Prepreg $ 94643.09 94643.09 Incorrect
Solvent Prepreg $ 89318.70 89318.70 Incorrect


c. What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)

IRR
Dry Prepreg 19.08 19.08 Incorrect %
Solvent Prepreg 13.69 13.69 Incorrect %


d. Calculate the incremental IRR for the cash flows. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Incremental IRR             Not attempted%

Solutions

Expert Solution

a. The Pay-back Period of the projects are as follows:

  • Project Dry Prepreg: 1.76 years (or) 1 year 9 months 3 days) (approx.)
  • Project Solvent Prepreg: 1.53 years (or) 1 year 6 months 11 days (approx.)

Computations:

Cumulative Cash flows:

Dry Prepreg Solvent Prepreg
Year Cash flows Cumulative Cash flows Cash flows Cumulative Cash flows
      1 $ 1,111,000 $        1,111,000 $   430,000 $ 430,000
     2 $ 922,000 $     2,033,000 $    710,000 $1,140,000
     3 $ 761,000 $     2,794,000 $    412,000 $1,552,000

From the above table, it can be observed that the cash flows exceeds the initial investment in year 2 in both the projects.

The incremental cash flows required to recover the initial investment and proportionate time taken to recover them are as follows:

Dry Prepreg Solvent Prepreg
Initial Investment $      1,810,000 $   805,000
Less: Cash flows in year 1 $       (1,111,000) $ (430,000)
Incremental Cash flows required in year 2 $       699,000 $    375,000
Total Cash flows during the year 2 $        922,000 $    710,000
Time taken to recover the incremental cash flows                  0.76              0.53
Time taken in months                  9.10              6.34
Total Pay-back period                   1.76               1.53

b. The NPV of the projects are as follows:

  • Project Dry Prepreg: $613,276.43
  • Project Solvent Prepreg: $528,971.59

Computation:

Dry Prepreg
Year Cash flows PV factor @ 8% PV of cash flows
1 $ 1,111,000       0.93 $   1,028,703.70
2 $ 922,000       0.86 $    790,466.39
3 $ 761,000       0.79 $     604,106.34
Total PV of cash flows $   2,423,276.43
Less: Initial Investment $      (1,810,000)
NPV of the Project $      613,276.43
Solvent Prepreg
Year Cash flows PV factor @ 8% PV of cash flows
1 $ 430,000       0.93 $      398,148.15
2 $   710,000       0.86 $    608,710.56
3 $   412,000       0.79 $     327,058.88
Total PV of cash flows $    1,333,917.59
Less: Initial Investment $      (805,000)
NPV of the Project $     528,917.59

c. Internal Rate of Return of the projects:

  • Project Dry Prepreg: 27.32% (using excel formula) (or) 27.33% (using interpolation technique)
  • Project Solvent Prepreg: 41.39% (using excel formula) (or) 41.40% (using interpolation technique)

Computation

Internal Rate of return is that level of discount rate at which the NPV of the project will be 0. It should be calculated using the trial and error method.

IRR of project Dry prepreg:

Let the discount rate be 27%. The NPV of the project will be:

Dry Prepreg
Year Cash flows PV factor @ 27% PV of cash flows
1 $        1,111,000                  0.79 $     874,803.15
2 $       922,000                  0.62 $       571,641.14
3 $        761,000                 0.49 $       371,512.55
Total PV of cash flows $    1,817,956.85
Less: Initial Investment $     (1,810,000)
NPV of the Project $        7,956.85

If the discount rate is 28%, the resulting NPV would be:

Dry Prepreg
Year Cash flows PV factor @ 28% PV of cash flows
1 $   1,111,000       0.78 $    867,968.75
2 $ 922,000        0.61 $     562,744.14
3 $   761,000       0.48 $    362,873.08
Total PV of cash flows $   1,793,585.97
Less: Initial Investment $     (1,810,000)
NPV of the Project $      (16,414.03)

From the above 2 tables, it can be observed that the IRR lies somewhere in between 27% and 28%

To find out IRR, we should follow interpolation technique.

Incremental NPV at 27% (a) $        7,956.85
NPV lost when discount rate changed from 27% to 28% (b) $      24,370.88
Incremental IRR to recover the incremental NPV = (a) / (b) 0.33

Total IRR = 27% + 0.33% = 27.33% (approx)

IRR of project Solvent prepreg:

Let discount rate of the project be 41%, then NPV is:

Solvent Prepreg
Year Cash flows PV factor @ 41% PV of cash flows
1 $      430,000           0.71 $    304,964.54
2 $       710,000         0.50 $      357,124.89
3 $       412,000          0.36 $     146,973.78
Total PV of cash flows $    809,063.22
Less: Initial Investment $      (805,000)
NPV of the Project $        4,063.22

Let us assume the discount rate to be 42%, the resulting NPV is:

Solvent Prepreg
Year Cash flows PV factor @ 42% PV of cash flows
1 $ 430,000       0.70 $    302,816.90
2 $   710,000       0.50 $      352,112.68
3 $   412,000       0.35 $     143,890.52
Total PV of cash flows $     798,820.10
Less: Initial Investment $      (805,000)
NPV of the Project $       (6,179.90)

From the above 2 tables, it can be observed that the IRR lies somewhere in between 41% and 42%

To find out IRR, we should follow interpolation technique.

Incremental NPV at 41% (a) $        4,063.22
NPV lost when discount rate changed from 41% to 42% (b) $      10,242.128
Incremental IRR to recover the incremental NPV = (a) / (b) 0.40

Total IRR = 41% + 0.40% = 41.40% (approx)

d. Incremental IRR of the projects is 13.38%

Incremental cash flows:

Year Dry Prepreg Solvent Prepreg Incremental Cash flows
1 $     1,111,000 $ 430,000 $ 681,000
2 $        922,000 $ 710,000 $    212,000
3 $        761,000 $ 412,000 $    349,000
Incremental Initial Investment $    (1,810,000) $(805,000) $ (1,005,000)

Incremental IRR using trial and error method:

Let the discount rate be 13%. The resulting NPV is:

Year Cash flows PV factor @ 13% PV of cash flows
1 $      681,000        0.88 $    602,654.87
2 $       212,000        0.78 $     166,027.10
3 $     349,000        0.69 $      241,874.51
Total PV of cash flows $   1,010,556.47
Less: Initial Investment $    (1,005,000)
NPV of the Project $        5,556.47

Let the discount rate be 14%. The resulting NPV is:

Year Cash flows PV factor @ 14% PV of cash flows
1 $     681,000       0.88 $    597,368.42
2 $      212,000       0.77 $       163,127.12
3 $    349,000       0.67 $    235,565.06
Total PV of cash flows $ 996,060.60
Less: Initial Investment $    (1,005,000)
NPV of the Project $      (8,939.40)

From the above 2 tables, it can be observed that the IRR lies somewhere in between 13% and 14%

To find out IRR, we should follow interpolation technique.

Incremental NPV at 13% (a) $        5,556.47
NPV lost when discount rate changed from 13% to 14% (b) $      14,495.87
Incremental IRR to recover the incremental NPV = (a) / (b) 0.38

Total IRR = 13% + 0.38% = 13.38% (approx)


Related Solutions

Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the discount rate for both projects is 7 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,890,000 –$ 900,000 1 1,119,000 470,000 2 938,000 790,000 3 769,000 428,000 a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period Dry Prepreg years Solvent Prepreg years b. What is the NPV...
Comparing Investment Criteria. Consider the following cash flows of two mutually exclusive projects for Spartan Rubber...
Comparing Investment Criteria. Consider the following cash flows of two mutually exclusive projects for Spartan Rubber company.  Assume the discount rate for both projects is 10 percent. a. Based on the payback period, which project should be taken? b. Based onthe NPV, which project should be taken? c.  Based on the IRR, which project should be taken? d.  Based on the above analysis, is incremental IRR analysis necessary?  If yes, please conduct the analysis. Year Dry Prepreg Solvent Prepreg 0 (1,800,000) (925,000) 1 690,000...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 12 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,800,000 –$ 800,000 1 1,110,000 425,000 2 920,000 700,000 3 760,000 410,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)     b. What is the NPV for both projects? (Do not round intermediate...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 8 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,810,000 –$ 805,000 1 1,111,000 430,000 2 922,000 710,000 3 761,000 412,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)      Payback period   Dry Prepeg years   Solvent Prepeg years          b. What is...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 9 percent. YearDry PrepregSolvent Prepreg 0–$1,850,000 –$825,000 1 1,115,000  450,000 2 930,000  750,000 3 765,000  420,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)     b. What is the NPV for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places,...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 10 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,830,000 –$ 815,000 1 1,113,000 440,000 2 926,000 730,000 3 763,000 416,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)     b. What is the NPV for both projects? (Do not round intermediate...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 7 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,870,000 –$ 835,000 1 1,117,000 460,000 2 934,000 770,000 3 767,000 424,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.) b. What is the NPV for both projects? (Do not round intermediate calculations....
Consider the following cash flows of two mutually exclusive projects for Braisl Rubber Co. Assume the...
Consider the following cash flows of two mutually exclusive projects for Braisl Rubber Co. Assume the discount rate for both projects is 9 Percent. Year Dry PrePreg Solvent PrePreg 0 1,820,000 810,000 1 1,112,000 435,000 2 924,000 720,000 3 762,000 414,000 a. What is the payback period for both projects? Dry PrePreg Years Solvent PrePreg Years b. What is the NPV for both projects? Dry PrePreg Solvent PrePreg c. What is the IRR for both projects? Dry PrePreg % Solvent...
Comparing Investment Criteria. Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber...
Comparing Investment Criteria. Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 8% Year                Deepwater Fishing                  New Submarine Ride 0                      -$1,700,000                             -$750,000 1                      1,100,000                               375,000           2                         900,000                                600,000 3                         750,000                                390,000 b) Based on the NPV, which project should be taken? c) Based on IRR, which project should be taken?
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT