Question

In: Accounting

Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2014 and was completed on December 31, 2014. Dobbs made the following payments to Kiner, Inc. during 2014:

Date                                              Payment

June 1, 2014                                 $6,000,000

August 31, 2014                             9,000,000

December 31, 2014                        7,500,000

In order to help finance the construction, Dobbs issued the following during 2014:

1.   $5,000,000 of 10-year, 9% bonds payable, issued at par on May 31, 2014, with interest payable annually on May 31.

2.   1,000,000 shares of no-par common stock, issued at $10 per share on October 1, 2014.

In addition to the 9% bonds payable, the only debt outstanding during 2014 was a $1,250,000, 12% note payable dated January 1, 2010 and due January 1, 2020, with interest payable annually on January 1.

Instructions

Compute the amounts of each of the following:

1.   Weighted-average accumulated expenditures qualifying for capitalization of interest cost.

2.   Avoidable interest incurred during 2014.

3.   Total amount of interest cost to be capitalized during 2014.

Solutions

Expert Solution

Solution

1. Weighted-average accumulated expenditures $

   Weighted-average accumulated expenditures will be calculated as follow.Construction was begun on June 1, 2014 and was completed on December 31, 2014.So it is period of 7 months.Dobbs made the following payments to Kiner, on frequent date so calculation is as follow.

Date Capitalization

expenditure

period Weighted Avg

accumulted exp

1-June 60,00,000 7/12 35,00,000
31-Aug 90,00,000 4/12 30,00,000
31-Dec 75,00,000 0 0
65,00,000

2. Avoidable interest incurred during 2014

Avoidable interest incurred during 2014  will be calculated as follow.

Weighted Avg

Accumulted Exp

Interest rate Avoidable interest
50,00000 .09 450,000
15,00,000 .12 180,000
65,00,000 630,000

3. Total amount of interest cost to be capitalized during 2014

The calculation of total amount of interest cost to be capitalized during 2014 will as follow

Actual interest incurred during 2014

9% bonds payable, $50,00,000 × .09 × 7/12 = $262,500

12% note payable, $1,250,000 × .12 = $150,000

Total 412,500

The interest cost to be capitalized is $412,500 (the lesser of the $630,000 avoidable interestand the $412,500 actual interest cost).

Please give thumbs up :-)


Related Solutions

Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2016 and was completed on December 31, 2016 Dobbs made the following payments to Kiner, Inc. during 2016: Date Payment June 1, 2016 $1,680,000 August 31, 2016 2,520,000 December 31, 2016 2,100,000 In order to help finance the construction, Dobbs issued the following during 2016: 1. $1,428,000 of 10-year, 9% bonds payable, issued at par...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $5,856,000 August 31, 2017 9,120,000 December 31, 2017 7,440,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $5,110,000 of 10-year, 9% bonds payable, issued at par...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,440,000 August 31, 2020 3,660,000 December 31, 2020 3,050,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $2,074,000 of 10-year, 9% bonds payable, issued at par...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date                                                Payment June 1, 2017                                 $2,000,000 August 31, 2017                             3,000,000 December 31, 2017                        2,500,000 In order to help finance the construction, Dobbs issued $1,700,000 of 10-year, 9% bonds payable, issued at par on May 31, 2017, with...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2012 and was completed on December 31, 2012. Dobbs made the following payments to Kiner, Inc. during 2012: Date                                              Payment June 1, 2012                                  $4,800,000 August 31, 2012                              7,200,000 December 31, 2012                         6,000,000             In order to help finance the construction, Dobbs issued $4,000,000 of 10-year, 9% bonds payable, issued at par on May 31,...
Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing...
Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing facility for Dobbs. Construction began on June 1, 2019, and was completed on December 31, 2019. Dobbs made the following payments to Kiner during 2019: Date Payment amount June 1, 2019, $6,000,000 August 31, 2019, 9,000,000 December 31, 2019 7,500,000 In order to finance the construction, Dobbs issued a $5,000,000, 10 year, 9% bond, issued at par on May 31, 2019, with interest payable...
Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of...
Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of Menan's manufacturing facility. Construction was begun on May 1, 2015. Menan made the following payments to Roberts, Inc. during 2015: Date Payment May 1, 2015 $34,000,000 August 31, 2015 $56,000,000 December 31, 2015 $31,000,000 In order to help finance the construction, Nolan issued the following during 2015: 1. $12,000,000 of 10-year, 9% bonds payable, issued at par on May 1, 2015, with interest payable...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing facility. Construction begun on June 1 and completed on December 31, 2019. Tanya made the following expenditures during 2019: Date Payment Jun 1, 2019 $ 3,000,000 Oct 31, 2019 5,400,000 Tanya borrowed $2,000,000 on January 1, 2019, to specifically finance the construction. The loan has a stated interest rate of 8% and a 10-year maturity. In addition, Tanya had the following debt outstanding during...
An independent accounting firm has been engaged to audit the 2014 financial statements of a corporation...
An independent accounting firm has been engaged to audit the 2014 financial statements of a corporation which has never undergone an audit. During the audit, it is concluded that the 2014 ending inventory presented by management is in error. The inventory cannot be counted because much of it has been sold as of the time of the audit. Therefore, a "test of reasonableness" of the inventory is performed by using the following data from the 2014 income statement prepared by...
Variances In early 2014, JAX Inc. had budgeted for the production and sales of 6,000 units...
Variances In early 2014, JAX Inc. had budgeted for the production and sales of 6,000 units at a sales price of $20 per unit. The following information is available regarding the standards for each unit: Direct Materials:   2 pounds @ $3.00 per pound Direct Labor:   30 minutes of assembly @ $0.25 per minute Actual results for 2014 were determined to be: Number of units produced and sold:   6,800 Sales Revenue:   $149,600 ($22 / unit) Direct Materials   $43,384 (14,960 lbs purchased...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT