Question

In: Accounting

Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of...

Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of Menan's manufacturing facility. Construction was begun on May 1, 2015. Menan made the following payments to Roberts, Inc. during 2015:

Date Payment
May 1, 2015 $34,000,000
August 31, 2015 $56,000,000
December 31, 2015 $31,000,000

In order to help finance the construction, Nolan issued the following during 2015:

1. $12,000,000 of 10-year, 9% bonds payable, issued at par on May 1, 2015, with interest payable annually on May 1.

2. 20,000,000 shares of no-par common stock, issued at $10 per share on May 1, 2015.

In addition to the 9% bonds payable, the only other debt outstanding during 2015 was an $8,000,000, 12% note payable dated January 1, 2012 and due January 1, 2022, with interest payable annually on January 1.

What is the total amount to be debited to the 'Manufacturing Facility' account during the year 2015?

Solutions

Expert Solution

Weighted-average accumulated expenditures qualifying for capitalization of interest cost.
Date Capitalization Expenditures Period Weighted-Average Accumulated Expenditures
May 1, 2015 $ 34,000,000 8/12 $ 22,666,667
August 31, 2015 $ 56,000,000 4/12 $ 18,666,667
December 31, 2015 $ 31,000,000 0 $ 0
$ 41,333,333
Avoidable interest incurred during 2015
Weighted-Average Accumulated Expenditures Appropriate Interest Rate Avoidable Interest
12000000 9% 1,080,000.00
$ 29,333,333 12% 3,520,000.00
$ 41,333,333 4,600,000.00
Actual interest incurred during 2015:
9% bonds payable, $12,000,000*9%*8/12                              720,000.00
12% note payable, $8,000,000*12%                              960,000.00
                          1,680,000.00
Total amount to be debited to the 'Manufacturing Facility' account during the year 2015
Avoidable interest incurred during 2015 4,600,000.00
Less: Actual interest incurred during 2015: -1,680,000
2,920,000.00

Related Solutions

Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2016 and was completed on December 31, 2016 Dobbs made the following payments to Kiner, Inc. during 2016: Date Payment June 1, 2016 $1,680,000 August 31, 2016 2,520,000 December 31, 2016 2,100,000 In order to help finance the construction, Dobbs issued the following during 2016: 1. $1,428,000 of 10-year, 9% bonds payable, issued at par...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $5,856,000 August 31, 2017 9,120,000 December 31, 2017 7,440,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $5,110,000 of 10-year, 9% bonds payable, issued at par...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,440,000 August 31, 2020 3,660,000 December 31, 2020 3,050,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $2,074,000 of 10-year, 9% bonds payable, issued at par...
Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2014 and was completed on December 31, 2014. Dobbs made the following payments to Kiner, Inc. during 2014: Date                                              Payment June 1, 2014                                 $6,000,000 August 31, 2014                             9,000,000 December 31, 2014                        7,500,000 In order to help finance the construction, Dobbs issued the following during 2014: 1.   $5,000,000 of 10-year, 9% bonds payable, issued at...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date                                                Payment June 1, 2017                                 $2,000,000 August 31, 2017                             3,000,000 December 31, 2017                        2,500,000 In order to help finance the construction, Dobbs issued $1,700,000 of 10-year, 9% bonds payable, issued at par on May 31, 2017, with...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2012 and was completed on December 31, 2012. Dobbs made the following payments to Kiner, Inc. during 2012: Date                                              Payment June 1, 2012                                  $4,800,000 August 31, 2012                              7,200,000 December 31, 2012                         6,000,000             In order to help finance the construction, Dobbs issued $4,000,000 of 10-year, 9% bonds payable, issued at par on May 31,...
Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing...
Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing facility for Dobbs. Construction began on June 1, 2019, and was completed on December 31, 2019. Dobbs made the following payments to Kiner during 2019: Date Payment amount June 1, 2019, $6,000,000 August 31, 2019, 9,000,000 December 31, 2019 7,500,000 In order to finance the construction, Dobbs issued a $5,000,000, 10 year, 9% bond, issued at par on May 31, 2019, with interest payable...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing facility. Construction begun on June 1 and completed on December 31, 2019. Tanya made the following expenditures during 2019: Date Payment Jun 1, 2019 $ 3,000,000 Oct 31, 2019 5,400,000 Tanya borrowed $2,000,000 on January 1, 2019, to specifically finance the construction. The loan has a stated interest rate of 8% and a 10-year maturity. In addition, Tanya had the following debt outstanding during...
You are engaged to audit the Ferrick Corporation for the year ended December 31, 2015. Only...
You are engaged to audit the Ferrick Corporation for the year ended December 31, 2015. Only merchandise shipped by the Ferrick Corporation to customers up to and including December 30, 2015, has been eliminated from inventory. The inventory as determined by physical inventory count has been recorded on the books by the company’s controller. No perpetual inventory records are maintained. All sales are made on an FOB–shipping point basis. You are to assume that all purchase invoices have been correctly...
Plantation Homes Company is considering the acquisition of Condominiums, Inc. early in 2015.
Plantation Homes Company is considering the acquisition of Condominiums, Inc. early in 2015. To assess the amount it might be willing to pay, Plantation Homes makes the following computations and assumptions. A. Condominiums, Inc. has identifiable assets with a total fair value of $16,118,000 and liabilities of $9,099,000. The assets include office equipment with a fair value approximating book value, buildings with a fair value 29% higher than book value, and land with a fair value 74% higher than book value....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT