Question

In: Accounting

Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2016 and was completed on December 31, 2016 Dobbs made the following payments to Kiner, Inc. during 2016:

Date Payment
June 1, 2016 $1,680,000
August 31, 2016 2,520,000
December 31, 2016 2,100,000


In order to help finance the construction, Dobbs issued the following during 2016:

1. $1,428,000 of 10-year, 9% bonds payable, issued at par on May 31, 2016, with interest payable annually on May 31.
2. 300,000 shares of no-par common stock, issued at $10 per share on October 1, 2016.


In addition to the 9% bonds payable, the only debt outstanding during 2016 was a $357,000, 12% note payable dated January 1, 2012 and due January 1, 2019, with interest payable annually on January 1.

Compute the amounts of each of the following:

1. Weighted-average accumulated expenditures qualifying for capitalization of interest cost.
2. Avoidable interest incurred during 2016.
3. Total amount of interest cost to be capitalized during 2016.
1. Weighted-average accumulated expenditures $
2. Avoidable interest $
3. Amount of interest cost to be capitalized $

Solutions

Expert Solution

Please find below table useful to compute desired results: -

End results would be as follows: -


Related Solutions

Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $5,856,000 August 31, 2017 9,120,000 December 31, 2017 7,440,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $5,110,000 of 10-year, 9% bonds payable, issued at par...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,440,000 August 31, 2020 3,660,000 December 31, 2020 3,050,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $2,074,000 of 10-year, 9% bonds payable, issued at par...
Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2014 and was completed on December 31, 2014. Dobbs made the following payments to Kiner, Inc. during 2014: Date                                              Payment June 1, 2014                                 $6,000,000 August 31, 2014                             9,000,000 December 31, 2014                        7,500,000 In order to help finance the construction, Dobbs issued the following during 2014: 1.   $5,000,000 of 10-year, 9% bonds payable, issued at...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date                                                Payment June 1, 2017                                 $2,000,000 August 31, 2017                             3,000,000 December 31, 2017                        2,500,000 In order to help finance the construction, Dobbs issued $1,700,000 of 10-year, 9% bonds payable, issued at par on May 31, 2017, with...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2012 and was completed on December 31, 2012. Dobbs made the following payments to Kiner, Inc. during 2012: Date                                              Payment June 1, 2012                                  $4,800,000 August 31, 2012                              7,200,000 December 31, 2012                         6,000,000             In order to help finance the construction, Dobbs issued $4,000,000 of 10-year, 9% bonds payable, issued at par on May 31,...
Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing...
Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing facility for Dobbs. Construction began on June 1, 2019, and was completed on December 31, 2019. Dobbs made the following payments to Kiner during 2019: Date Payment amount June 1, 2019, $6,000,000 August 31, 2019, 9,000,000 December 31, 2019 7,500,000 In order to finance the construction, Dobbs issued a $5,000,000, 10 year, 9% bond, issued at par on May 31, 2019, with interest payable...
Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of...
Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of Menan's manufacturing facility. Construction was begun on May 1, 2015. Menan made the following payments to Roberts, Inc. during 2015: Date Payment May 1, 2015 $34,000,000 August 31, 2015 $56,000,000 December 31, 2015 $31,000,000 In order to help finance the construction, Nolan issued the following during 2015: 1. $12,000,000 of 10-year, 9% bonds payable, issued at par on May 1, 2015, with interest payable...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing facility. Construction begun on June 1 and completed on December 31, 2019. Tanya made the following expenditures during 2019: Date Payment Jun 1, 2019 $ 3,000,000 Oct 31, 2019 5,400,000 Tanya borrowed $2,000,000 on January 1, 2019, to specifically finance the construction. The loan has a stated interest rate of 8% and a 10-year maturity. In addition, Tanya had the following debt outstanding during...
Millco, Inc., acquired a machine that cost $600,000 early in 2016. The machine is expected to...
Millco, Inc., acquired a machine that cost $600,000 early in 2016. The machine is expected to last for eighth years, and its estimated salvage value at the end of its life is $80,000. Required: a. Using straight-line depreciation, calculate the depreciation expense to be recognized in the first year of the machine's life and calculate the accumulated depreciation after the fifth year of the machine's life. b. Using declining-balance depreciation at twice the straight-line rate, calculate the depreciation expense for...
Millco, Inc., acquired a machine that cost $544,000 early in 2016. The machine is expected to...
Millco, Inc., acquired a machine that cost $544,000 early in 2016. The machine is expected to last for eighth years, and its estimated salvage value at the end of its life is $75,000. Required: a. Using straight-line depreciation, calculate the depreciation expense to be recognized in the first year of the machine's life and calculate the accumulated depreciation after the fifth year of the machine's life. Depreciation expense Accumulated depreciation b. Using declining-balance depreciation at twice the straight-line rate, calculate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT