Question

In: Accounting

Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing...

Early in 2019, Dobbs Corporation engaged Kiner Construction, Inc. to design and construct a new manufacturing facility for Dobbs. Construction began on June 1, 2019, and was completed on December 31, 2019. Dobbs made the following payments to Kiner during 2019: Date Payment amount June 1, 2019, $6,000,000 August 31, 2019, 9,000,000 December 31, 2019 7,500,000 In order to finance the construction, Dobbs issued a $5,000,000, 10 year, 9% bond, issued at par on May 31, 2019, with interest payable annually on May 31. In addition to the $5,000,000 bond issue, Dobbs also had the following additional debt outstanding during 2019: $1,250,000 note payable, the interest rate of 12%, a maturity date of January 1, 2020, interest payable annually on January 1st. $1,000,000 loan payable, the interest rate of 7%, maturing on January 1, 2025, with interest payable quarterly. Requirements Compute the following amounts: 1. Weighted-average accumulated expenditures qualifying for capitalization of interest cost in 2019. 2. Maximum interest incurred during 2019. 3. Total amount of interest cost to be capitalized (i.e., included in the total cost of the manufacturing facility) for 2019. 4. The total cost of the facility.

Solutions

Expert Solution

Amounts are in $

Answer is inserted as a picture

Note :

As we have no information of which loan was used for this purpose mainly other than the bond. We have taken average interest rate of these two loans and used it for capitalisation.

In practice, we know which loan (note or general loan) which is used for paying this construction and we can capitalise interest of such loan


Related Solutions

Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2016, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2016 and was completed on December 31, 2016 Dobbs made the following payments to Kiner, Inc. during 2016: Date Payment June 1, 2016 $1,680,000 August 31, 2016 2,520,000 December 31, 2016 2,100,000 In order to help finance the construction, Dobbs issued the following during 2016: 1. $1,428,000 of 10-year, 9% bonds payable, issued at par...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $5,856,000 August 31, 2017 9,120,000 December 31, 2017 7,440,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $5,110,000 of 10-year, 9% bonds payable, issued at par...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,440,000 August 31, 2020 3,660,000 December 31, 2020 3,050,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $2,074,000 of 10-year, 9% bonds payable, issued at par...
Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2014 and was completed on December 31, 2014. Dobbs made the following payments to Kiner, Inc. during 2014: Date                                              Payment June 1, 2014                                 $6,000,000 August 31, 2014                             9,000,000 December 31, 2014                        7,500,000 In order to help finance the construction, Dobbs issued the following during 2014: 1.   $5,000,000 of 10-year, 9% bonds payable, issued at...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date                                                Payment June 1, 2017                                 $2,000,000 August 31, 2017                             3,000,000 December 31, 2017                        2,500,000 In order to help finance the construction, Dobbs issued $1,700,000 of 10-year, 9% bonds payable, issued at par on May 31, 2017, with...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2012 and was completed on December 31, 2012. Dobbs made the following payments to Kiner, Inc. during 2012: Date                                              Payment June 1, 2012                                  $4,800,000 August 31, 2012                              7,200,000 December 31, 2012                         6,000,000             In order to help finance the construction, Dobbs issued $4,000,000 of 10-year, 9% bonds payable, issued at par on May 31,...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing...
Early in 2019, Tanya Corporation engaged a contractor Chavis, Inc. to design and construct Tanya's manufacturing facility. Construction begun on June 1 and completed on December 31, 2019. Tanya made the following expenditures during 2019: Date Payment Jun 1, 2019 $ 3,000,000 Oct 31, 2019 5,400,000 Tanya borrowed $2,000,000 on January 1, 2019, to specifically finance the construction. The loan has a stated interest rate of 8% and a 10-year maturity. In addition, Tanya had the following debt outstanding during...
Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of...
Early in 2015, Menan Corporation engaged Roberts, Inc. to design and construct a complete modernization of Menan's manufacturing facility. Construction was begun on May 1, 2015. Menan made the following payments to Roberts, Inc. during 2015: Date Payment May 1, 2015 $34,000,000 August 31, 2015 $56,000,000 December 31, 2015 $31,000,000 In order to help finance the construction, Nolan issued the following during 2015: 1. $12,000,000 of 10-year, 9% bonds payable, issued at par on May 1, 2015, with interest payable...
Boots, Inc. is a ā€œCā€ corporation engaged in the shoe manufacturing business. Boots is a calendar...
Boots, Inc. is a ā€œCā€ corporation engaged in the shoe manufacturing business. Boots is a calendar year, accrual method taxpayer with two equal shareholders, Emil and Betty, who are unrelated cash method taxpayers. In answering the questions below, assume for convenience that Emil and Betty each are taxable at acombined federal and state flat rate of 40% on ordinary income and a combined flat rate of 20% on qualified dividends and long-term capital gains.During the current year, Boots has the...
Beta Inc. wants to construct a manufacturing plant in Brazil. The construction will cost 900 million...
Beta Inc. wants to construct a manufacturing plant in Brazil. The construction will cost 900 million Brazilian Real. Beta intends to operate the plant for 3 years. During the 3 years of operation, Real (BRL) cash flows are expected to be 300 million BRL, 300 million BRL, and 200 million BRL, respectively. Operating cash flows will begin 1 year from today and are remitted back to the Canadian parent at the end of each year. At the end of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT