Question

In: Economics

Consider the case of a power plant that, in the process of generating electricity, it also...

Consider the case of a power plant that, in the process of generating electricity, it also emits noxious pollutants. It has been argued that this situation represents a market failure.
a. Briefly explain, using a graph, what are the economic foundations of this argument?
b. Using the graph in (a) show what are the economic implications of this case
c. What economic mechanism would you suggest to correct for this market failure?
d. In general, why market forces, do not provide an efficient solution in such cases?

Solutions

Expert Solution

a)

Here, the power plant generates electricity but in order to do so it also emits noxious pollutants. Thus, it creates a negative externality where the social costs are higher than the private costs.The marginal benefit for such externality is same for the private and social levels. The following diagram depicts the situation,

Here, SMB : Social Marginal Benefit

PMB : Private Marginal Benefit

SMC: Social Marginal Cost

PMC : Private Marginal Cost

The economically optimum output will be at that point where the demand equals to the Private social cost.

b)

Since, a negative externality is observed here. So, the demand is equal to Social Marginal Benefit and Private Marginal Benefit i.e SMB=PMB

Here, the Social Marginal Cost is greater than the Private Marginal Cost i.e SMC>PMC. Since the production of electricity bears a social cost with pollution which is not beared by the Private Electricity producing companies.

The Private companies will produce to that point where D=PMC. At this point, the output is not socially optimum.

The social optimum output is upto that point where D=SMC. And in this case . So, there involves a deadweight loss.This creates a market failure.

c)

To correct such market failure I would suggest to implement some neccessary regulations in the factories to control pollution such as installation of pollution control filters . This will increase the private cost of the firm upto that point where PMC = SMC . Thus, SMC and PMC curve will ultimately coincide with each other. And the output obtained by such interaction of Demand and Marginal cost(SMC=PMC) will be economically and socially optimum.

d)

In general, the market mechanism fails under the presence of externality. In the presence of externality, there is either underutilisation of resources or overutilisation of resources. In this case, there is overutilisation of resources. In the presence of externality, the economically optimum output is never equal to social optimum output and the output is never efficient. There is always a deadweight loss associated with such mechanism. Hence, market always fails under such mechanism.


Related Solutions

Consider two 50 MW power generating plants. One plant is fueled by combustion of coal, the...
Consider two 50 MW power generating plants. One plant is fueled by combustion of coal, the other by solar energy. Using the concept of exergy, explain why the ecological impacts of the solar power process are lower than the coal fired process. Use words and diagrams in your answer
If price of electricity doubles due to power generating capacity is unable to keep up with...
If price of electricity doubles due to power generating capacity is unable to keep up with the fast growing demand for recharging electric vehicles: 1. initially which determinant of demand or supply (pick one or the other) for household-owned electric cars will be primarily affected? 2. will the demand or supply (picked from #1) of electric cars increase or decrease? 3. briefly explain why that is or draw a diagram 4. as a result of this increase in electricity prices,...
CASE study Electricity Generation Case study 8.1: Electricity generation Electricity Generation Here and now Distributed power...
CASE study Electricity Generation Case study 8.1: Electricity generation Electricity Generation Here and now Distributed power generation will end the long-distancetyranny of the grid. For decades, control over energy has been deemed too important to be left to the markets. Politicians and officials have been dazzled by the economies of scale promised by ever bigger power plants, constructed a long way from consumers. They have put up with the low efficiency of those plants, and the environmental harm they do,...
If a coal-fired power plant burns 2 kg of coal to produce electricity, and the electricity...
If a coal-fired power plant burns 2 kg of coal to produce electricity, and the electricity is used to power an elevator motor that is 60% efficient, how high can the elevator and passengers be lifted up if their total mess is 1500 kg? and then How many human workers using muscle power('energy servants") would be needed to lift the elevator up to the same height, if they had one minute to do so? Assuming that one energy servant is...
            The Fukushima Power plant is planning construction of a new plant to generate electricity four...
            The Fukushima Power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15 In the following, all the future costs and earnings have been adjusted to their present worth: If a...
A power plant is planning construction of a new plant to generate electricity four years hence...
A power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15             In the following, all the future costs and earnings have been adjusted to their present worth: The capacity of...
The following system is a small power generating plant which contains a boiler, a superheater, a...
The following system is a small power generating plant which contains a boiler, a superheater, a turbine and a condenser. Describe each part of the system with reference to the equations required in terms of heat transfer and work transfer. The feed water flows at 1 tonne/hr at 50°C. The output pressure is 6 bar with a dryness fraction is 0.9 and the efficiency of the boiler is 75%. The calorific value of the fuel is 38MJ/kg. Determine the fuel...
Power is generated at 24 kV at a generating plant located 55km from a town that...
Power is generated at 24 kV at a generating plant located 55km from a town that requires 60MW of power at 12 kV. Two transmission lines from the plant to the town each have a resistance of 0.11?/km . What should the output voltage of the transformer at the generating plant be for an overall transmission efficiency of 97.8%, assuming a perfect transformer?
Consider a gas turbine engine, fueled by natural gas, for generating electricity. A.) Calculate the adiabatic...
Consider a gas turbine engine, fueled by natural gas, for generating electricity. A.) Calculate the adiabatic flame temperature for this system, assuming we’ll use about 110% TA. B.) Estimate (calculate) the power output for this turbine, per lbm or kg of air. C.) If I’d like to provide the generator with 12,000 shp (shaft horsepower), what air mass flow do I need? D.) If this is an open cycle turbine, the exhaust gas has considerable remaining energy. How much heat...
Suppose that an electricity provider would build a power plant at the cost of $50 million....
Suppose that an electricity provider would build a power plant at the cost of $50 million. Once the plant is built, it would cost the plant $0.07 per kilowatt hour of electricity that it produces. Over its lifetime, the plant is expected to generate 100 million kilowatt hours. Suppose that the regulators believe that the investors who put up capital to build the plant should be able to recoup its investment plus a 300% return throughout the life of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT