Question

In: Statistics and Probability

            The Fukushima Power plant is planning construction of a new plant to generate electricity four...

            The Fukushima Power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows:

Level of Demand

Probability

High

0.30

Medium

0.55

Low

0.15

In the following, all the future costs and earnings have been adjusted to their present worth:

  1. If a large plant is built and demand is high, the plant’s net present value (NPV) is estimated to be $180 million. If the demand is medium, however, the NPV of a large plant will drop to $100 million. If the demand is low the NPV will be loss of $200 million.
  2. A medium sized plant will have an NPV of $120 million if demand is high or medium and a loss of $5 million if demand is low. If demand is high, a medium-sized plant can be enlarged at a cost of $40 million to generate an additional $80 million in earnings.
  3. The capacity of a small plant would limit its NPV to $60 million regardless of demand. If demand is medium, a small plant can be enlarged a moderate amount at a cost of $20 million. Its NPV would then be $110 million less the cost of $20 million for the expansion. If demand is high, a small plant can be enlarged greatly in size at a cost of $80 million. Its NPV would then be $170 million less the cost of $80 million for the expansion. On the contrary, if demand is high, a small plant can be enlarged a moderate amount to increase its NPV to $140 million less the cost of $40 million for the expansion

Conduct a decision-tree analysis on Excel to determine the size of the power-generating plant the company should build now. What size of the power-generating plant the company should build now? Briefly discuss your answer.

Solutions

Expert Solution

Solution:

Given

Level of Demand

Probability

High

0.30

Medium

0.55

Low

0.15

Decision Tree:

Expected NPV of Small plant = 0.15*60+0.55*90+0.30*100

= $ 88.5 million

Expected NPV  of Medium plant = 0.15*(-5)+0.55*120+0.30*(120+40)

= $ 113.25 million

Expected NPV of Large plant = 0.15*(-200)+0.55*100+0.30*180

= $ 79 million

Expected NPV  of Medium plant is the highest.

   The company should build a Medium sized plant now and if the demand is high, then the plant should be expanded .

===============================================================

Decision tree using the new probabilities:

In the above decision tree,

we see that Expected NPV of build medium plant is the highest.

   The company should build a medium sized plant now, and if demand is high, then Expand .

Expected NPV of this decision strategy = $ 105 million

Please give upvote.

Thank you.


Related Solutions

A power plant is planning construction of a new plant to generate electricity four years hence...
A power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15             In the following, all the future costs and earnings have been adjusted to their present worth: The capacity of...
If a coal-fired power plant burns 2 kg of coal to produce electricity, and the electricity...
If a coal-fired power plant burns 2 kg of coal to produce electricity, and the electricity is used to power an elevator motor that is 60% efficient, how high can the elevator and passengers be lifted up if their total mess is 1500 kg? and then How many human workers using muscle power('energy servants") would be needed to lift the elevator up to the same height, if they had one minute to do so? Assuming that one energy servant is...
Consider the case of a power plant that, in the process of generating electricity, it also...
Consider the case of a power plant that, in the process of generating electricity, it also emits noxious pollutants. It has been argued that this situation represents a market failure. a. Briefly explain, using a graph, what are the economic foundations of this argument? b. Using the graph in (a) show what are the economic implications of this case c. What economic mechanism would you suggest to correct for this market failure? d. In general, why market forces, do not...
Planning is underway for a new hydroelectric power plant, and you have been asked to provide...
Planning is underway for a new hydroelectric power plant, and you have been asked to provide an engineering opinion on the best site for the power plant to be located. Two main sites have been identified for the plant. Site 1 is located at the base of a dam wall, with the waterline located 70 m above the turbine. The location has good accessibility for the construction crew, meaning that they are able to bring in a state-of-the-art turbine-generator system....
Suppose that an electricity provider would build a power plant at the cost of $50 million....
Suppose that an electricity provider would build a power plant at the cost of $50 million. Once the plant is built, it would cost the plant $0.07 per kilowatt hour of electricity that it produces. Over its lifetime, the plant is expected to generate 100 million kilowatt hours. Suppose that the regulators believe that the investors who put up capital to build the plant should be able to recoup its investment plus a 300% return throughout the life of the...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would cost $269.63 million,...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT