Question

In: Finance

Net present value. Independent projects Using a 14% cost of capital, calculate the net present value...

Net present value. Independent projects Using a 14% cost of capital, calculate the net present value for each of the independent projects shown in the following table, and indicate whether each is acceptable.

Project A Project B Project C Project D Project E
Initial investment $26,000 $500,000 $170,000 $950,000 $80,000
Year Cash inflows
1 $4,000 $100,000 $20,000 $230,000 $ 0
2 4,000 120,000 19,000 230,000 0
3 4,000 140,000 18,000 230,000 0
4 4,000 160,000 17,000 230,000 20,000
5 4,000 180,000 16,000 230,000 30,000
6 4,000 200,000 15,000 230,000 0
7 4,000 14,000 230,000 50,000
8 4,000 13,000 230,000 60,000
9 4,000 12,000 70,000
10 4,000 11,000
Solution
Project A
Discount rate 14%
Number of years 10
CF0 -$26,000
CF1-10 $4,000
PV of cash inflows
NPV of project A
The project will be
Project B
Discount rate 14%
CF0 -$500,000
CF1 $100,000
CF2 $120,000
CF3 $140,000
CF4 $160,000
CF5 $180,000
CF6 $200,000
PV of cash inflows
NPV of project B
The project will be
Project C
Discount rate 14%
CF0 -$170,000
CF1 $20,000
CF2 $19,000
CF3 $18,000
CF4 $17,000
CF5 $16,000
CF6 $15,000
CF7 $14,000
CF8 $13,000
CF9 $12,000
CF10 $11,000
PV of cash inflows
NPV of project C
The project will be

Solutions

Expert Solution

Accept projects with positive NPV

workings in excel as follows


Related Solutions

Net present value. Independent projects Using a 14% cost of capital, calculate the net present value...
Net present value. Independent projects Using a 14% cost of capital, calculate the net present value for each of the independent projects shown in the following table, and indicate whether each is acceptable. Project A Project B Project C Project D Project E Initial investment $26,000 $500,000 $170,000 $950,000 $80,000 Year Cash inflows 1 $4,000 $100,000 $20,000 $230,000 $ 0 2 4,000 120,000 19,000 230,000 0 3 4,000 140,000 18,000 230,000 0 4 4,000 160,000 17,000 230,000 20,000 5 4,000...
Net present value Using a cost of capital of 11​%, calculate the net present value for...
Net present value Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, Initial investment ​(CF 0CF0​) negative 1 comma 143 comma 000−1,143,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 $81,000 2 $138,000 3 $193,000 4 $258,000 5 $311,000 6 $377,000 7 $270,000 8 $98,000 9 $45,000 10 $29,000 The net present value​ (NPV) of the project is _____​$ ​(Round to the nearest​...
Using a cost of capital of 13​%, calculate the net present value for the project shown...
Using a cost of capital of 13​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, LOADING.... The net present value​ (NPV) of the project is ​$ Initial investment   -1,151,000 Year   Cash inflows 1   84,000 2   136,000 3   192,000 4   255,000 5   318,000 6   382,000 7   277,000 8   100,000 9   42,000 10   25,000
 Using a cost of capital of 11​%, calculate the net present value for the project shown...
 Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, Initial investment ​(CF 0CF0​) negative $−$1149 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) in thousands 1 ​$8080 2 ​$130 3 ​$189 4 ​$256 5 ​$312 6 ​$376 7 ​$280 8 ​$102 9 ​$42 10 ​$20 The net present value​ (NPV) of the project is ​$-75,817.60.  ​(Round to the nearest​ cent.) Is the project​ acceptable?
Using a cost of capital of 11​%, calculate the net present value for the project shown...
Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable Initial investment ​(CF 0CF0​) -$1149 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) in thousands 1 ​$80 2 ​$130 3 ​$189 4 ​$256 5 ​$312 6 ​$376 7 ​$280 8 ​$102 9 ​$42 10 ​$20
Using a cost of capital of 15​%, calculate the net present value for the project shown...
Using a cost of capital of 15​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable Initial investment   $-1,145 Year   Cash inflows 1   $76 2   $132 3   $185 4   $256 5   $316 6   $383 7   $277 8   $98 9   $43 10   $25 The net present value​ (NPV) of the project is $_____ Please show all work and what inputs would be in a financial calculator
Evaluate the following projects, using the Net Present Value (NPV). Assume a cost of capital of...
Evaluate the following projects, using the Net Present Value (NPV). Assume a cost of capital of 6%.    Project A    Project B Initial Cash Outflow $200,000 $160,000 Year 1 Cash flow 69,000 80,000 Year 2 Cash flow 71,000 80,000 Year 3 Cash flow 85,000 50,000 Calculate the NPV for each project. Which project would you accept according to the NPV?
Using a discount rate of 14 percent, calculate the net present value (NPV) of the proposed investment.
Beacon Company is considering automating its production facility. The initial investment in automation would be $9.40 million, and the equipment has a useful life of 8 years with a residual value of $1,000,000. The company will use straight-line depreciation. Beacon could expect a production increase of 38,000 units per year and a reduction of 20 percent in the labor cost per unit.   Current (no automation) Proposed (automation)   77,000 units 115,000 units Production and sales volume Per Unit Total...
Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value...
Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows: Product Line Expansion Distribution Facilities Computer Network Amount to be invested $790,052 $535,506 $310,018 Annual net cash flows: Year 1 413,000 301,000 186,000 Year 2 384,000 271,000 128,000 Year 3 351,000 241,000 93,000 Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2...
First United Bank Inc. is evaluating three capital investment projects using the net present value method....
First United Bank Inc. is evaluating three capital investment projects using the net present value method. Relevant data related to the projects are summarized as follows: Branch Office Expansion Computer System Upgrade ATM Kiosk Expansion Amount to be invested $750,769 $459,475 $219,567 Annual net cash flows: Year 1 287,000 198,000 123,000 Year 2 267,000 178,000 85,000 Year 3 244,000 158,000 62,000 Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT