Question

In: Finance

Net present value Using a cost of capital of 11​%, calculate the net present value for...

Net present value Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable,

Initial investment

​(CF 0CF0​)

negative 1 comma 143 comma 000−1,143,000

Year

​(t​)

Cash inflows

​(CF Subscript tCFt​)

1

$81,000

2

$138,000

3

$193,000

4

$258,000

5

$311,000

6

$377,000

7

$270,000

8

$98,000

9

$45,000

10

$29,000

The net present value​ (NPV) of the project is _____​$ ​(Round to the nearest​ cent.)

Is the project​ acceptable?  ​

Solutions

Expert Solution

Solution:-

To Calculate NPV of the Project-

The Project is not accepted as Net Present value of the Project is Negative. Project is accepted when NPV of the project is greater than or equal to zero. Hence, Project are not acceptable.

If you have any query related to question then feel free to ask me in a comment.Thanks. Please rate.


Related Solutions

 Using a cost of capital of 11​%, calculate the net present value for the project shown...
 Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, Initial investment ​(CF 0CF0​) negative $−$1149 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) in thousands 1 ​$8080 2 ​$130 3 ​$189 4 ​$256 5 ​$312 6 ​$376 7 ​$280 8 ​$102 9 ​$42 10 ​$20 The net present value​ (NPV) of the project is ​$-75,817.60.  ​(Round to the nearest​ cent.) Is the project​ acceptable?
Using a cost of capital of 11​%, calculate the net present value for the project shown...
Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable Initial investment ​(CF 0CF0​) -$1149 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) in thousands 1 ​$80 2 ​$130 3 ​$189 4 ​$256 5 ​$312 6 ​$376 7 ​$280 8 ​$102 9 ​$42 10 ​$20
Net present value. Independent projects Using a 14% cost of capital, calculate the net present value...
Net present value. Independent projects Using a 14% cost of capital, calculate the net present value for each of the independent projects shown in the following table, and indicate whether each is acceptable. Project A Project B Project C Project D Project E Initial investment $26,000 $500,000 $170,000 $950,000 $80,000 Year Cash inflows 1 $4,000 $100,000 $20,000 $230,000 $ 0 2 4,000 120,000 19,000 230,000 0 3 4,000 140,000 18,000 230,000 0 4 4,000 160,000 17,000 230,000 20,000 5 4,000...
Net present value. Independent projects Using a 14% cost of capital, calculate the net present value...
Net present value. Independent projects Using a 14% cost of capital, calculate the net present value for each of the independent projects shown in the following table, and indicate whether each is acceptable. Project A Project B Project C Project D Project E Initial investment $26,000 $500,000 $170,000 $950,000 $80,000 Year Cash inflows 1 $4,000 $100,000 $20,000 $230,000 $ 0 2 4,000 120,000 19,000 230,000 0 3 4,000 140,000 18,000 230,000 0 4 4,000 160,000 17,000 230,000 20,000 5 4,000...
Using a cost of capital of 13​%, calculate the net present value for the project shown...
Using a cost of capital of 13​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, LOADING.... The net present value​ (NPV) of the project is ​$ Initial investment   -1,151,000 Year   Cash inflows 1   84,000 2   136,000 3   192,000 4   255,000 5   318,000 6   382,000 7   277,000 8   100,000 9   42,000 10   25,000
Using a cost of capital of 15​%, calculate the net present value for the project shown...
Using a cost of capital of 15​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable Initial investment   $-1,145 Year   Cash inflows 1   $76 2   $132 3   $185 4   $256 5   $316 6   $383 7   $277 8   $98 9   $43 10   $25 The net present value​ (NPV) of the project is $_____ Please show all work and what inputs would be in a financial calculator
Evaluate the following projects, using the Net Present Value (NPV). Assume a cost of capital of...
Evaluate the following projects, using the Net Present Value (NPV). Assume a cost of capital of 6%.    Project A    Project B Initial Cash Outflow $200,000 $160,000 Year 1 Cash flow 69,000 80,000 Year 2 Cash flow 71,000 80,000 Year 3 Cash flow 85,000 50,000 Calculate the NPV for each project. Which project would you accept according to the NPV?
Evaluate the following projects, using the net present value criteria. Assume a cost of capital of...
Evaluate the following projects, using the net present value criteria. Assume a cost of capital of 9%.    Project M    Project N Initial Cash Outflow -$260,000 -$260,000 Year 1 Cash flow       19,000     185,000 Year 2 Cash flow     121,000       85,000 Year 3 Cash flow     185,000       55,000 a. What are the NPVs for the projects and what do these numbers tell you? b. If the projects are independent, which would you accept according to the...
Calculate the Net Present Value of the cash flows depicted in the table below using a...
Calculate the Net Present Value of the cash flows depicted in the table below using a cost of capital of {r81d}percent. year Cash Flow 0 -60 1 40 2 40 3 0
Given the following information, calculate the Net Present Value for a capital budget proposal? Show your...
Given the following information, calculate the Net Present Value for a capital budget proposal? Show your work. Machine Cost: $6,000,000 Salvage Value: $50,000 Setup Costs: $45,000 Training Costs: $25,000 Annual maintenance costs: $45,000 Anticipated annual savings: $560,000 Annual labor savings: $25,000 Expected useful life in years: 12 Overhaul costs in year 4: $50,000 Annual operating costs: $25,000 Hurdle rate: 8%
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT