Question

In: Accounting

Edwards Company contracted on 4/1/17 to construct a building for $4,800,000. The project was completed in...

Edwards Company contracted on 4/1/17 to construct a building for $4,800,000. The project was completed in 2019. Additional data follow: 2017 2018 2019 Costs incurred to date $1,120,000 $2,700,000 $3,800,000 Estimated cost to complete 2,080,000 900,000 — Billings to date 1,000,000 3,800,000 4,800,000 Collections to date 800,000 2,600,000 4,400,000 Instructions (a) Calculate the income recognized by Edwards under the percentage-of-completion method of accounting in each of the years 2017, 2018, and 2019. (b) Prepare all necessary entries for the year 2018. (c) Present the balance sheet disclosures at December 31, 2018. Proper headings or subheadings must be indicated.

Solutions

Expert Solution

SOLUTION

(A)

Year Actual costs ($) Estimated costs ($) Estimated total costs ($) % complete to date
2017 1,120,000 2,080,000 3,200,000 35%
2018 2,700,000 900,000 3,600,000 75%
2019 3,800,000 0 3,800,000 100%

2017-

Particulars To date Recognized in prior years ($) Recognized in current year ($)
Construction revenue 1,000,000 0 1,000,000
Construction expense (1,120,000) 0 (1,120,000)
Gross profit / (loss) (120,000) 0 (120,000)

2018-

Particulars To date Recognized in prior years ($) Recognized in current year ($)
Construction revenue 3,800,000 1,000,000 2,800,000
Construction expense (2,700,000) (1,120,000) (1,580,000)
Gross profit / (loss) (1,100,000) (120,000) 1,220,000

2019-

Particulars To date Recognized in prior years ($) Recognized in current year ($)
Construction revenue 4,800,000 3,800,000 1,000,000
Construction expense (3,800,000) (2,700,000) (1,100,000)
Gross profit / (loss) (1,000,000) 1,100,000 (100,000)

(B) Journal Entry-

Year Accounts titles and Explanation Debit ($) Credit ($)
2018 Construction in progress 1,580,000
   Various accounts 1,580,000
Accounts receivables 2,800,000
   Bolling on contsruction contract 2,800,000
Cash 1,800,000
   Accounst receivables 1,800,000
Cost of construction 1,580,000
Contruction in progress 1,220,000
   Revenue from long term contract 2,800,000

(C) Balance sheet-

Amount ($)
Current assets-
   Accounts receivables 1,200,000
   Cost and profit in excess of billings
Current liabilities-
    Billings in excess of costs less loss 1,100,000

Related Solutions

On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...
On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                                                                                                                                    2020                                    2021                      2022 Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000 Estimated costs to complete the contract at Dec 31          ...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700 2,117,000 –0– Billings...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract Costs Incurred during the year $2,208,000 $2,230,000 $2,190,000 Estimated Costs to Complete the Contract at 12/31 $3,520,000 $2,190,000 -0- Billings...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,410,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,916,400 $2,079,200 $2,244,400 Estimated costs to complete the contract at 12/31 3,423,600 2,244,400 –0– Billings...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher’s accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5 Construction costs incurred during the year, $180,000; estimated costs to complete, $630,000; progress billings during the year, $153,000; and collections, $140,000. 20X6...
Problem 18-10 On March 1, 2017, Sandhill Construction Company contracted to construct a factory building for...
Problem 18-10 On March 1, 2017, Sandhill Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,310,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,871,000 $2,304,900 $2,114,100 (2019 Row) Estimated costs to complete the contract at 12/31...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016 and was completed in 2017. Data relating to the contract are summarized below:                                                                                    2016                  2017       Costs incurred during the year.................      $   360,000         $1,650,000       Estimated costs to complete as of 12/31.        1,560,000                   -             Billings during the year ..........................           430,000         2,170,000       Cash collections during the year..............           320,000         2,280,000 Required: 1.   Compute the amount of gross...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT