In: Accounting
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson completed both Job #2 and Job #3. Job #1 was not completed by the end of March. Job #2 consisted of 1,700 units; some of these units were sold during March. None of the units from Job #3 were sold in March. Johnson Company's accounting records for March disclosed the following information: Work in process inventory balance at March 31 .......... $15,880 Actual overhead cost for the month of March ............ $ 8,500 Cost of goods sold for March ........................... $11,830 Finished goods inventory balance at March 31 ........... $18,870 The cost of goods sold number above represents the cost of goods sold for March after the overhead variance has been closed for March. Calculate the number of units from Job #2 that were sold during March. Simply enter your answer as a number. Do not type the word units after your answer.
Step 1. Calculation of % of overhead based on material with the help of job 1.
Since only the job 1 is pending at the end of month hence cost shown as work in process on March 31 will consist of only job 1.
So cost of job 1 = $15880
Opening WIP + Material added + labor added + overhead = $15880
$4930 + $3400 + $5000 + overhead = $15880
Overhead = $15880 - $13330 = $2550
Overhead % based on material = $2550/$3400*100 = 75%
Step 2. Calculation of total applied overhead
Total material in all three jobs = $3400 + $4200 + $4600
= $12200
Total overhead applied = $12200 * 75%
= $9150
Step 3 calculation of variation in overhead
Variation = Actual - applied
= $8500 - $9150
= $650 overapplied
Step 4 calculation of cost of goods sold without adjusting variable
= $11830 + $650
= $12480
Step 5 calculation of cost per unit of job 2
Cost of job 2 = $4970 + $4200 + $4000 + ($4200*75%)
= $16320
Units of job 2 = $1700
Cost per unit = $16320/1700 = $9.60 per unit
Step 6 calculation of units sold
= Cost of goods sold without variation / cost per unit
= $12480/9.6
= 1300 units