Question

In: Accounting

Madtack Company uses a job-order costing system and started the month of March with three jobs...

Madtack Company uses a job-order costing system and started the month of
March with three jobs in process. The cost of beginning work in process
plus the costs added during March are shown below:

                                  Job #359      Job #360      Job #361
beginning work in process .....    $4,800        $3,500        $5,300

COSTS ADDED DURING MARCH:
direct materials ..............    $4,100        $3,000        $6,400
direct labor ..................     5,000         3,900         4,000

Madtack applies overhead to jobs at a rate of 80% of direct materials
used. During March, Madtack completed and sold Job #361. Job #359 was
also completed but was not sold by the end of March. Job #360 was not
completed by the end of March. Madtack's actual overhead cost for the
month of March totaled $11,500.

Calculate Madtack's cost of goods sold for March after the overhead
variance is closed.

Solutions

Expert Solution


Related Solutions

Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Propane Company uses a job-order costing system and started the month of March with three jobs...
Propane Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Propane applies overhead to jobs based on a percentage of direct materials used. During March, Propane...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Daniel J Company uses a job-order costing system and started the month of March with three...
Daniel J Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Daniel J applies overhead to jobs based on a percentage of direct materials used. During...
ABC Company uses a job order costing system and had three jobs in process at the...
ABC Company uses a job order costing system and had three jobs in process at the beginning of the month. The beginning balance in the WIP account was $145,400, made up of $42,400, $65,100, and $37,900 as shown on the cost sheets for Jobs 921, 922, and 923 respectively. During the month, ABC added the following materials and labor costs to each job. Inventory Materials used for Month Labor Dollars used for Month Job 921 12,200 30,000 Job 922 13,400...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT