In: Accounting
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson completed both Job #2 and Job #3. Job #1 was not completed by the end of March. Job #2 consisted of 1,700 units; some of these units were sold during March. None of the units from Job #3 were sold in March. Johnson Company's accounting records for March disclosed the following information: Work in process inventory balance at March 31 .......... $15,880 Actual overhead cost for the month of March ............ $ 8,500 Cost of goods sold for March ........................... $11,830 Finished goods inventory balance at March 31 ........... $18,870 The cost of goods sold number above represents the cost of goods sold for March after the overhead variance has been closed for March. Calculate the number of units from Job #2 that were sold during March. Simply enter your answer as a number. Do not type the word units after your answer.
Answer:
First let us find applied overhead rate:
Job 1 was not completed by end of March and from information given is the only job which is in 'Work in process' at the end March.
Given Work in process (WIP) balance at March 31 = $15,800
Hence total cost of Job 1 as at March 31 = $15,800
Overhead applied to Job 1 = total cost of Job 1 as at March 31 - Beginning WIP of Job 1 - March Direct material cost of Job 1 - March Direct labor cost of Job 1
= 15880 - 4930 - 3400 - 5000
= $2,550
Johnson applies overhead to jobs based on a percentage of direct material.
Hence:
Overhead rate is = 2550 / 3400 = 75% of direct material
Now let us calculate per unit cost of Job 2:
Total cost of production of Job 2 = 4970 + 4200 + 4000 + 4200 * 75% = $16320
Job 2 consisted of 1700 units
Job 2 per unit cost = 16320 / 1700 = $9.60
Overhead variance = Actual overhead - Applied overhead = 8500 - (3400 + 4200 + 4600) * 75% = $650 Over-applied
Only job sold in March is Job 2.
Un-adjusted cost of goods sold =11830 + 650 = $12,480
Number of Job 2 units sold = Un-adjusted Cost of goods sold / per unit cost = 12480 / 9.60 = 1,300
Hence:
Number of units from Job # 2 that were sold during March = 1,300