Question

In: Accounting

Propane Company uses a job-order costing system and started the month of March with three jobs...

Propane Company uses a job-order costing system and started the month of
March with three jobs in process. The cost of beginning work in process
plus the costs added during March are shown below:

                                   Job #1        Job #2        Job #3
beginning work in process .....    $4,930        $4,970        $2,840

COSTS ADDED DURING MARCH:
direct materials ..............    $3,400        $4,200        $4,600
direct labor ..................    $5,000        $4,000           ?

Propane applies overhead to jobs based on a percentage of direct materials
used. During March, Propane completed both Job #2 and Job #3. Job #1 was
not completed by the end of March. Job #2 consisted of 1,700 units; some
of these units were sold during March. None of the units from Job #3 were
sold in March. Propane Company's accounting records for March disclosed
the following information:

Work in process inventory balance at March 31 ..........  $15,880
Actual overhead cost for the month of March ............  $ 8,500
Cost of goods sold for March ...........................  $11,830
Finished goods inventory balance at March 31 ...........  $18,870

The cost of goods sold number above represents the cost of goods sold for
March after the overhead variance has been closed for March.

Calculate the direct labor cost added during March for Job #3 and cost of goods manufactured for March.

Solutions

Expert Solution


Related Solutions

Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Daniel J Company uses a job-order costing system and started the month of March with three...
Daniel J Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Daniel J applies overhead to jobs based on a percentage of direct materials used. During...
ABC Company uses a job order costing system and had three jobs in process at the...
ABC Company uses a job order costing system and had three jobs in process at the beginning of the month. The beginning balance in the WIP account was $145,400, made up of $42,400, $65,100, and $37,900 as shown on the cost sheets for Jobs 921, 922, and 923 respectively. During the month, ABC added the following materials and labor costs to each job. Inventory Materials used for Month Labor Dollars used for Month Job 921 12,200 30,000 Job 922 13,400...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT