Question

In: Accounting

Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in...

Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2019. As bid, the statistics were as follows: Contract price $4,000,000 Estimated costs $3,000,000 At the end of the first year, the following was the status of the contract: Billings to date $2,250,000 Costs incurred to date 1,200,000 Latest forecast total cost 3,000,000 Instructions

(a) Compute the percentage of completion on the contract at the end of 2019.

(b) Indicate the amount of gross profit that would be reported on this contract at the end of 2019.

(c) Make the journal entry to record the income (loss) for 2019 on Dobson's books.

Solutions

Expert Solution

(a) Computation of the percentage of completion on the contract at the end of 2019:-
Percentage of completion = Cost incurred to date
Total Estimated Cost
Percentage of completion = $1,200,000
$3,000,000
= 40%
(b) Computation of amount of gross profit that would be reported on this contract at the end of 2019:-
2019
Cost incurred during the year $                    1,200,000
Add: Cost incurred in earlier years $ -  
Cost incurred to date $                    1,200,000
Total Estimated Cost (A) $                    3,000,000
Contract Revenue (B) $                    4,000,000
Total Estimated Gross Profit (B-A) $                    1,000,000
Percentage of completion 40%
Revenue to be recognized to date             (% complete * Contact revenue ) $                    1,600,000
Less: Revenue recognized in earlier years $ -  
Revenue to be recognized for the year $                    1,600,000
Gross Profit to be recognized to date (% complete * Total Estimated Gross Profit ) $                        400,000
Less: Income recognized in earlier years $ -  
Gross Profit to be recognized at the end of 2019 $                       400,000
(c) Journal entry to record the income (loss) for 2019 on Dobson's books:-
Date Particulars Debit Credit
Construction in progress (gross profit) $                        400,000
Cost of Construction (actual costs) $                    1,200,000
              Revenue from Long term contracts (cost +profit) $   1,600,000
(To record gross profit)
Billings on Construction Contract (account balance) $                    2,250,000
              Construction in progress (account balance) $   2,250,000
(To record amount billed)

Feel free to ask any clarification, if required. Please provide feedback by thumbs up, if satisfied. It will be highly appreciated. Thank you.


Related Solutions

Continent Construction Company is a building contractor specializing in small commercial buildings. The company has the...
Continent Construction Company is a building contractor specializing in small commercial buildings. The company has the opportunity to accept one of two jobs; it cannot accept both because they must be performed at the same time and Continent does not have the necessary labor force for both jobs. Indeed, it will be necessary to hire a new supervisor if either job is accepted. Furthermore, additional insurance will be required if either job is accepted. The revenue and costs associated with...
Rooney Construction Company is a building contractor specializing in small commercial buildings. The company has the...
Rooney Construction Company is a building contractor specializing in small commercial buildings. The company has the opportunity to accept one of two jobs; it cannot accept both because they must be performed at the same time and Rooney does not have the necessary labor force for both jobs. Indeed, it will be necessary to hire a new supervisor if either job is accepted. Furthermore, additional insurance will be required if either job is accepted. The revenue and costs associated with...
You are a project manager at a construction company that specializes in building office buildings. You...
You are a project manager at a construction company that specializes in building office buildings. You were approached by a representative of a company that was interested in your company’s services. He told you that their company was growing and they decided to build a new office building to address their needs. Then he told you that they already started the process with another construction company. They signed a contract with the other construction company and they started the building...
During the construction phase of a health-care project, delays not attributed to the contractor were experienced,...
During the construction phase of a health-care project, delays not attributed to the contractor were experienced, but the contractor was delayed in submitting all delay information required by the contract until 7 days before the contractual completion date, can the architect issue an extension of time prior to the completion date? Explain.
Commercial buildings and industrial facilities account for a major share of a company's environmental impact. Identify...
Commercial buildings and industrial facilities account for a major share of a company's environmental impact. Identify one business that has implemented green building standards and describe the advantages they have gained from their efforts.
A contractor bought a crane for erecting tall buildings. It was invoiced from Japan CIF (cost,...
A contractor bought a crane for erecting tall buildings. It was invoiced from Japan CIF (cost, insurance, freight) Manila at P2,500,000. Brokerage, bank, customs’ duties, permits, etc. total P1,200,000. At the end of 10years, he expects to sell it for P500,000. Determine the book value at the beginning of year 5 using the: A)Straight-Line Method. B) Sinking Fund Method at 12%. C) Matheson Formula Method. D) Double Declining Balance Method. E) Sum of the Years Digit Method.
A contractor bought a crane for erecting tall buildings. It was invoiced from JapanCIF (cost, insurance,...
A contractor bought a crane for erecting tall buildings. It was invoiced from JapanCIF (cost, insurance, freight) Manila at P2,500,000. Brokerage, bank, customs’duties, permits, etc. total P1,200,000. At the end of 10 years, he expects to sell itfor P500,000. Construct a schedule of the book value at the end of each year usingthe following methods: (a) Straight-Line Formula, (b) Sinking Fund Formula at 12%,(c) Matheson Formula (d) Double Declining Method and (e) SYD Method Show complete solution. answe a, b,c,d,e.
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Advise when a contractor will not be in breach of a construction contract as defined under...
Advise when a contractor will not be in breach of a construction contract as defined under the Housing Grants Construction and Regeneration Act 1996, if he wants to stop work on a project due to non-payment.
A small industrial contractor purchased a warehouse building for storing equipment and materials that are not...
A small industrial contractor purchased a warehouse building for storing equipment and materials that are not immediately needed at construction job sites. The cost of the building was $100,000 and the contractor has just made an agreement with the seller to finance the purchase over a 5-year period. The agreement state that monthly payments will be made based on a 30-year amortization, but the balance owed at the end of year 5 must be paid in a lump-sum "balloon" payment....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT