Question

In: Finance

The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...

The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum.

Years

Project X

Project Y

0

-$300,000

-$350,000

1

$150,000

$150,000

2

$150,000

$150,000

3

$250,000

$200,000

4

$80,000

$200,000

5

$80,000

$200,000

IRR

42.2%

39.3%

1. Calculate the projects’ net present value (NPV). Identify which project should be accepted under the rule of NPV. Explain your answer.      

2. What is the decision based on the internal rate of return (IRR)?

3. Calculate the crossover rate/incremental IRR, at which the NPV profiles for Projects A and B intersect.

4. Which project should be accepted based on your answer in part (iii)? Explain your answer.

Solutions

Expert Solution

Question 1:

Question 2:

IRR of Project A is 42.2%

IRR of Project B is 39.3%

Project A should be accepted since IRR of Project A is higher than Project B

Question 3:


Related Solutions

The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% Calculate the crossover rate/incremental IRR, at which the NPV profiles for Projects A and B intersect. 2.Which project should be accepted based on your...
Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The...
Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The firm's cost of capital is 12.25 percent.                                                                               Year                Project A             Project B                                                    0                       (600)                                      (600)                                                    1                           200                                        400                                                    2                           310                                        260                                                      3                           400                                        100                                                                 NPV?                     _____                                   _____                                                                 IRR?                       _____                                   _____                 Calculate the NPVs and IRRs for Projects A and B. Project A's NPV is $107.02, and Project B's...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Consider the cash flows from two mutually exclusive projects
Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive projects: Cash FlowYearProject AProject B0-$420,000-$420,0001$140,000$400,0002$230,000$110,0003$331,000$140,000The appropriate discount rate is 8.5%.Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows                                                                                                                              Time      Project A              Project B                                                                                                              0              ($400)                 ($700)                                                                                                    1              ($280)                   $201                                                                                                      2              ($200)                   $202                                                                                                      3              ($100)                   $203                                                                                                      4              $600                      $204                                                                                                      5              $600                      $205                                                                                                      6              $925                      $206                                                                                                      7              ($170)                   $207 In your report, identify which project would be selected (assuming they...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows                                                                                                                              Time      Project A              Project B                                                                                                              0              ($400)                 ($700)                                                                                                    1              ($280)                   $201                                                                                                      2              ($200)                   $202                                                                                                      3              ($100)                   $203                                                                                                      4              $600                      $204                                                                                                      5              $600                      $205                                                                                                      6              $925                      $206                                                                                                      7              ($170)                   $207 In your report, identify which project would be selected (assuming they...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows                                                                                                                              Time      Project A              Project B                                                                                                              0              ($400)                 ($700)                                                                                                    1              ($280)                   $201                                                                                                      2              ($200)                   $202                                                                                                      3              ($100)                   $203                                                                                                      4              $600                      $204                                                                                                      5              $600                      $205                                                                                                      6              $925                      $206                                                                                                      7              ($170)                   $207 In your report, identify which project would be selected (assuming they...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows                                                                                                                              Time      Project A              Project B                                                                                                              0              ($400)                 ($700)                                                                                                    1              ($280)                   $201                                                                                                      2              ($200)                   $202                                                                                                      3              ($100)                   $203                                                                                                      4              $600                      $204                                                                                                      5              $600                      $205                                                                                                      6              $925                      $206                                                                                                      7              ($170)                   $207 In your report, identify which project would be selected (assuming they...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Flower Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows                                                                                                                              Time      Project A              Project B                                                                                                              0              ($400)                 ($700)                                                                                                    1              ($280)                   $201                                                                                                      2              ($200)                   $202                                                                                                      3              ($100)                   $203                                                                                                      4              $600                      $204                                                                                                      5              $600                      $205                                                                                                      6              $925                      $206                                                                                                      7              ($170)                   $207 In your report, identify which project would be selected (assuming they...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT