In: Finance
Brian Cliff is evaluating two mutually exclusive projects
(expected cash flows shown below). The firm's cost of
capital is 12.25
percent.
Year
Project
A
Project B
0
(600)
(600)
1
200
400
2
310
260
3
400
100
NPV?
_____
_____
IRR?
_____
_____
Calculate the NPVs and IRRs for Projects A and B.
Project A's NPV is $107.02, and Project B's NPV is $33.40.
Project A's NPV is greater than Project B's NPV by 76.04.
Project A's NPV is greater than Project B's NPV by 72.43.
Project A's IRR is 21.27 percent, and Project B's IRR is 18.70 percent.
Project A | ||||
Discount rate | 0.1225 | |||
Year | 0 | 1 | 2 | 3 |
Cash flow stream | -600 | 200 | 310 | 400 |
Discounting factor | 1 | 1.1225 | 1.260006 | 1.414357 |
Discounted cash flows project | -600 | 178.1737 | 246.0305 | 282.814 |
NPV = Sum of discounted cash flows | ||||
NPV Project A = | 107.02 | |||
Where | ||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
Discounted Cashflow= | Cash flow stream/discounting factor | |||
Project B | ||||
Discount rate | 0.1225 | |||
Year | 0 | 1 | 2 | 3 |
Cash flow stream | -600 | 400 | 260 | 100 |
Discounting factor | 1 | 1.1225 | 1.260006 | 1.414357 |
Discounted cash flows project | -600 | 356.3474 | 206.3482 | 70.70351 |
NPV = Sum of discounted cash flows | ||||
NPV Project B = | 33.4 | |||
Where | ||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
Discounted Cashflow= | Cash flow stream/discounting factor | |||
Project A | ||||
IRR is the rate at which NPV =0 | ||||
IRR | 0.212697674 | |||
Year | 0 | 1 | 2 | 3 |
Cash flow stream | -600 | 200 | 310 | 400 |
Discounting factor | 1 | 1.212698 | 1.470636 | 1.783436 |
Discounted cash flows project | -600 | 164.9216 | 210.7932 | 224.2861 |
NPV = Sum of discounted cash flows | ||||
NPV Project A = | 0.000869733 | |||
Where | ||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||
Discounted Cashflow= | Cash flow stream/discounting factor | |||
IRR= | 21.27% | |||
Project B | ||||
IRR is the rate at which NPV =0 | ||||
IRR | 0.162659007 | |||
Year | 0 | 1 | 2 | 3 |
Cash flow stream | -600 | 400 | 260 | 100 |
Discounting factor | 1 | 1.162659 | 1.351776 | 1.571655 |
Discounted cash flows project | -600 | 344.039 | 192.3396 | 63.62722 |
NPV = Sum of discounted cash flows | ||||
NPV Project B = | 0.005743172 | |||
Where | ||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||
Discounted Cashflow= | Cash flow stream/discounting factor | |||
IRR= | 16.27% | |||