In: Finance
Brian Cliff is evaluating two mutually exclusive projects
               
   (expected cash flows shown below). The firm's cost of
capital is 12.25
percent.                              
                                               
Year      
         Project
A   
         Project B
                                               
  
0          
           
(600)                         
           
(600)
                                               
  
1                          
200                                       
400
                                               
  
2                          
310                                       
260  
                                               
  
3                          
400                                       
100
                                                               
NPV?                    
_____                                  
_____
                                                               
IRR?                      
_____                                  
_____
               
Calculate the NPVs and IRRs for Projects A and B.
Project A's NPV is $107.02, and Project B's NPV is $33.40.
Project A's NPV is greater than Project B's NPV by 76.04.
Project A's NPV is greater than Project B's NPV by 72.43.
Project A's IRR is 21.27 percent, and Project B's IRR is 18.70 percent.
| Project A | ||||
| Discount rate | 0.1225 | |||
| Year | 0 | 1 | 2 | 3 | 
| Cash flow stream | -600 | 200 | 310 | 400 | 
| Discounting factor | 1 | 1.1225 | 1.260006 | 1.414357 | 
| Discounted cash flows project | -600 | 178.1737 | 246.0305 | 282.814 | 
| NPV = Sum of discounted cash flows | ||||
| NPV Project A = | 107.02 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project B | ||||
| Discount rate | 0.1225 | |||
| Year | 0 | 1 | 2 | 3 | 
| Cash flow stream | -600 | 400 | 260 | 100 | 
| Discounting factor | 1 | 1.1225 | 1.260006 | 1.414357 | 
| Discounted cash flows project | -600 | 356.3474 | 206.3482 | 70.70351 | 
| NPV = Sum of discounted cash flows | ||||
| NPV Project B = | 33.4 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project A | ||||
| IRR is the rate at which NPV =0 | ||||
| IRR | 0.212697674 | |||
| Year | 0 | 1 | 2 | 3 | 
| Cash flow stream | -600 | 200 | 310 | 400 | 
| Discounting factor | 1 | 1.212698 | 1.470636 | 1.783436 | 
| Discounted cash flows project | -600 | 164.9216 | 210.7932 | 224.2861 | 
| NPV = Sum of discounted cash flows | ||||
| NPV Project A = | 0.000869733 | |||
| Where | ||||
| Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| IRR= | 21.27% | |||
| Project B | ||||
| IRR is the rate at which NPV =0 | ||||
| IRR | 0.162659007 | |||
| Year | 0 | 1 | 2 | 3 | 
| Cash flow stream | -600 | 400 | 260 | 100 | 
| Discounting factor | 1 | 1.162659 | 1.351776 | 1.571655 | 
| Discounted cash flows project | -600 | 344.039 | 192.3396 | 63.62722 | 
| NPV = Sum of discounted cash flows | ||||
| NPV Project B = | 0.005743172 | |||
| Where | ||||
| Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| IRR= | 16.27% | |||
