Question

In: Finance

Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The...

Brian Cliff is evaluating two mutually exclusive projects
                   (expected cash flows shown below). The firm's cost of capital is 12.25 percent.                              
                                                Year                Project A             Project B
                                                   0                       (600)                                      (600)
                                                   1                           200                                        400
                                                   2                           310                                        260  
                                                   3                           400                                        100
                                                                NPV?                     _____                                   _____

                                                                IRR?                       _____                                   _____

                Calculate the NPVs and IRRs for Projects A and B.

Project A's NPV is $107.02, and Project B's NPV is $33.40.

Project A's NPV is greater than Project B's NPV by 76.04.

Project A's NPV is greater than Project B's NPV by 72.43.

Project A's IRR is 21.27 percent, and Project B's IRR is 18.70 percent.

Solutions

Expert Solution

Project A
Discount rate 0.1225
Year 0 1 2 3
Cash flow stream -600 200 310 400
Discounting factor 1 1.1225 1.260006 1.414357
Discounted cash flows project -600 178.1737 246.0305 282.814
NPV = Sum of discounted cash flows
NPV Project A = 107.02
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 0.1225
Year 0 1 2 3
Cash flow stream -600 400 260 100
Discounting factor 1 1.1225 1.260006 1.414357
Discounted cash flows project -600 356.3474 206.3482 70.70351
NPV = Sum of discounted cash flows
NPV Project B = 33.4
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
IRR is the rate at which NPV =0
IRR 0.212697674
Year 0 1 2 3
Cash flow stream -600 200 310 400
Discounting factor 1 1.212698 1.470636 1.783436
Discounted cash flows project -600 164.9216 210.7932 224.2861
NPV = Sum of discounted cash flows
NPV Project A = 0.000869733
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 21.27%
Project B
IRR is the rate at which NPV =0
IRR 0.162659007
Year 0 1 2 3
Cash flow stream -600 400 260 100
Discounting factor 1 1.162659 1.351776 1.571655
Discounted cash flows project -600 344.039 192.3396 63.62722
NPV = Sum of discounted cash flows
NPV Project B = 0.005743172
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 16.27%


Related Solutions

The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% Calculate the crossover rate/incremental IRR, at which the NPV profiles for Projects A and B intersect. 2.Which project should be accepted based on your...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% 1. Calculate the projects’ net present value (NPV). Identify which project should be accepted under the rule of NPV. Explain your answer.       2. What...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -25,000 15,000 35,000 6,000 Project B Cash Flow -35,000 15,000 25,000 55,000 Use the discounted payback decision rule to evaluate...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -38,000 28,000 48,000 19,000   Project B Cash Flow -48,000 28,000 38,000 68,000 Use the discounted payback decision rule to evaluate...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 9 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -21,000 11,000 31,000 2,000 Project B Cash Flow -31,000 11,000 21,000 51,000 Use the discounted payback decision rule to evaluate...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -20,000 10,000 30,000 1,000 Project B Cash Flow -30,000 10,000 20,000 50,000 Use the NPV decision rule to evaluate these...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. time 0 1 2 3 project A cash flow -25,000 15,000 35,000 6,000 project B cash flow -35,000 15,000 25,000 55,000 Time: 0 1 2 3 Project A Cash...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -27,000 17,000 37,000 8,000   Project B Cash Flow -37,000 17,000 27,000 57,000 Use the PI decision rule to evaluate these...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -39,000 29,000 49,000 20,000 Project B Cash Flow -49,000 29,000 39,000 69,000 Use the PI decision rule to evaluate these...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT