Question

In: Civil Engineering

During the construction phase of a health-care project, delays not attributed to the contractor were experienced,...

During the construction phase of a health-care project, delays not attributed to the

contractor were experienced, but the contractor was delayed in submitting all delay

information required by the contract until 7 days before the contractual completion date,

can the architect issue an extension of time prior to the completion date? Explain.

Solutions

Expert Solution


Extension of time EOT in construction contracts

Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).

When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay.

If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.

Relevant events may include:

  • Variations.
  • Exceptionally adverse weather.
  • Civil commotion or terrorism.
  • Failure to provide information.
  • Delay on the part of a nominated sub-contractor.
  • Statutory undertaker’s work.
  • A delay in giving the contractor possession of the site.
  • Force majeure (such as an epidemic or an 'act of God').
  • Loss from a specified peril such as flood.
  • The supply of materials and goods by the client.
  • Strikes.
  • Changes in statutory requirements.
  • Delays in receiving permissions that the contractor has taken reasonable steps to avoid.

The contractor is required to prevent or mitigate the delay and any resulting loss, even where the fault is not their own.

Assessing claims for an extension of time can be complicated and controversial. There may be multiple or concurrent delays, some of which are the contractor's fault and some not. There are many occasions where contractors contribute to delay themselves by their performance during design periods, when producing drawings, mock ups and samples or in inter-facing with sub-contractors.

Crucial in assessing applications for extension of time is the quality of the information provided and records available

Construction contracts generally allow the construction period to be extended when there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).

When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay.

It is typical for the contractor to notify the project manager when the schedule may be affected by an issue. A formal letter is addressed to the contract administrator requesting the extension of time, presenting the reasons, and referencing the contract clause that allows the request.

Sometimes, contracts may specify the submission of requests within a specific time frame, otherwise they will be rejected. This letter is then assessed by the contract administrator (perhaps with input from the consultant team) before approval or rejection. If it is approved, the letter is given a written answer, and a change order is issued.

Proving delay and/or disruption can be a complicated and time-consuming process, and the quality of the information provided and the records available are often the key to successful claims. The time-extension claim should adequately establish both causation and liability, as well as the extent of the damages/disruption experienced by the contractor as a direct result of the delay.

To be able to do this effectively, the contractor should produce an accurate baseline programme before work begins, for progress to be monitored. The programme should show the planned productivity rates for the different work activities and the various benchmarks. As construction projects are naturally dynamic and subject to change, the programme should be continually updated and revised to reflect the current project conditions.

This can enable the contractor to determine what effect a delay is likely to have on their ability to complete activities, making it easier to prepare their claim


Related Solutions

Amazon experienced shipping delays as sales increased during the coronavirus pandemic. How do these delays impact...
Amazon experienced shipping delays as sales increased during the coronavirus pandemic. How do these delays impact Amazon’s marginal production cost and Amazon’s average cost of production? In the answer explain the difference between marginal cost and average cost?
What are some of the reasons for increased health care costs that are attributed to the...
What are some of the reasons for increased health care costs that are attributed to the providers of medical care? Answer should be one page long.
A construction project is carried out by a general contractor with the following descriptions: Project Duration:...
A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract Amount: 20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181 Budget Amount: 100,936+200,081+300,685 Contract Terms and Conditions Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Assume that the general contractor during the contract bidding phase notices a critical element of the...
Assume that the general contractor during the contract bidding phase notices a critical element of the wall section detail for the building is omitted. Further assume, the general contractor knows that the missing element is necessary for a successful project, required by code and will increase the cost of the project. The general contractor with knowledge of the error fails to disclose it or raise any question or request for information and bids the project believing they will be entitled...
You are a construction engineer working for a large utility contractor. The project you are working...
You are a construction engineer working for a large utility contractor. The project you are working on is in New York City (Manhattan). You are installing approximately 1,000 L.F. of 48” dia. RCP for storm drains. Invert elevation ranges from 9’ to 14’ below grade. Pay lines for the trench are indicated in the attached specification. Soil characteristics range from SM to SC, based on the Unified Soil Classification. What considerations would you make with regards to a trenching &...
1. A contractor needs water at a remote construction site for a five year project. A...
1. A contractor needs water at a remote construction site for a five year project. A pipeline from a river,six miles away, will supply the water. The cost of the pipeline and the cost of pumping the water will vary with pipe size. See table below. The contractor uses a MARR of 7%. The contractor plans to work 2000 hours per year, and that is the time the pump will run each year. At the end of five years the...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
1 What are some barriers to health care experienced by lesbians? What are some barriers experienced...
1 What are some barriers to health care experienced by lesbians? What are some barriers experienced by physical challenged women? 2 Name a disease or chronic health problem relevant to someone you know. Give one example each of a healthful primary, secondary, and tertiary prevention strategy for coping with the disease or condition. 3 Name two health-related difficulties resulting from aging and describe how they can make independent living difficult or dangerous. 4 How can parents, healthcare providers, and health...
how can u partner in a 2 storey construction project as a general contractor? describe the...
how can u partner in a 2 storey construction project as a general contractor? describe the extent to which any other person or group maybe partnering on project. what are challenges and benefits to any partnering that is occuring? what is preventing any further partnering?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT