Question

In: Operations Management

Explain and illustrate the following terms: Critical Path Analysis Program Evaluation and Review Technique Forward and...

Explain and illustrate the following terms:

Critical Path Analysis

Program Evaluation and Review Technique

Forward and Backward Passes

Slack Time

Project Crashing

Solutions

Expert Solution

Critical Path Analysis - Critical path analysis is the method used to calculate the minimum duration of the project as well as the amount of schedule flexibility on the logical project network based on relationship between activities and their sequencing.

Program Evaluation and Review Technique - PERT is the technique which is used to calculate realistic time required for completion of a project based on various duration provided for each activity (Optimistic, Most likely, Pessimistic) and their probabilities of completion and deviation if any.

Forward and Backward Passes - Forward passes and backward passes are used to calculate early start, early finish, late start and late finish of activities in project network.

Slack Time - The amount of time an activity can be delayed in called float or slack time

Project Crashing - The reduction in time of activities of the project using additional resources ultimately leading to reduction in overall project duration is called project crashing


Related Solutions

Question 1: Compare and contrast the project evaluation and review technique (PERT) with the critical path...
Question 1: Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM). Question 2: Explain in detail Eliyahu Goldratt’s Theory of Constraints with a brief note on its application in Project Management.
Using the Program Evaluation Review Technique, what is the probability of completing the project on or before 60 days?
Using the Program Evaluation Review Technique, what is the probability of completing the project on or before 60 days?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
How does process evaluation and continuous improvement effect project management and the critical path? Apply "Real-World"...
How does process evaluation and continuous improvement effect project management and the critical path? Apply "Real-World" examples you may have experienced.
Describe the following terms in reference to flow cytometry analysis of immune cells: hydrodynamic focusing, forward...
Describe the following terms in reference to flow cytometry analysis of immune cells: hydrodynamic focusing, forward light scatter, side light scatter, 2 dimensional scatter plot, threshold, bandpass filter, fluorophore, and CD marker?
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
Define the following terms , and explain them with some examples to illustrate them : Fiscal...
Define the following terms , and explain them with some examples to illustrate them : Fiscal policy , Monetary policy ?
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
how does program evaluation differ from other types of analysis
how does program evaluation differ from other types of analysis
Diverse Policy Analysis Methods What differentiates the value critical analysis from the analytic descriptive method evaluation?...
Diverse Policy Analysis Methods What differentiates the value critical analysis from the analytic descriptive method evaluation? Note at least three differences. Identify the commitments inherent in the value critical approach. Which process would be best for analyzing the social issue you identified in the first discussion
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT