Question

In: Finance

Suppose for a project X, it is estimated to have the following financials in Year 0...

Suppose for a project X, it is estimated to have the following financials in Year 0 and Year 1. Suppose the project requires to buy a new piece of equipment which costs $9,000. It has a useful life of three years and a salvage value of $0 at the end of 3rd year. The changes in NWC (NOT the cash effect of change in NWC) at Year 0 and Year 1 are $5,000 and $2,000 respectively. The free cash flow (FCF) at Year 1 is $____

(HINT: pay attention to the signs).

Year 0 Year 1
Unlevered net income 0 20,000
Depreciation 0 3,000
Change in Net Working Capital 5,000 2,000
Captial Expenditure 9,000 0

Solutions

Expert Solution

Year 0 Year 1
Unlevered net income 0 20,000
Depreciation 0 3,000
Change in Net Working Capital 5,000 2,000
Captial Expenditure 9,000 0

So the income is stated to be 20000 at year 1.

depreciation will be 3000.

change is working capital is year 0 5000 and year 1 is 2000.

capital expenditure is 9000.

to find the answer we need to deduct the year 0 cash outflow and year 1 cash inflow - outflow.

particulars year 0 year 1

uneveled net income 0 20000

Less: depreciation 0 (3000)

change in working capital (5000) 2000

capital expenditure (9000) 0

Total Cash flow     ( 14000) 19000

The free cash flow (FCF) at Year 1 is $ 5000.

Note working capital at year 0 was 5000 . but we utilised 3000 in year 1 which brought down the working capital to 2000.

so to adjust the balance we use accounting by -5000 ( initial provision) + 2000 ( remaing balance)

its give use a cash utilisation of -3000.


Related Solutions

A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 123,422.00 123,422.00 123,422.00 123,422.00 123,422.00 Cost of Goods 69,079.00 69,079.00 69,079.00 69,079.00 69,079.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 22,072.20 22,072.20 22,072.20 22,072.20 22,072.20 Investment in NWC 1,152.00 540.00 540.00 540.00 540.00 540.00 Investment in Gross PPE 110,361.00 The firm has a capital structure of 48.00% debt and 52.00% equity. The cost of debt is 9.00%, while the cost of...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 136,856.00 136,856.00 136,856.00 136,856.00 136,856.00 Cost of Goods 62,752.00 62,752.00 62,752.00 62,752.00 62,752.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 20,519.20 20,519.20 20,519.20 20,519.20 20,519.20 Investment in NWC 1,171.00 542.00 542.00 542.00 542.00 542.00 Investment in Gross PPE 102,596.00 The firm has a capital structure of 33.00% debt and 67.00% equity. The cost of debt is 8.00%, while the cost of...
A firm has projected the following financials for a possible project: Year 0 1 2 3...
A firm has projected the following financials for a possible project: Year 0 1 2 3 4 5 Sales 128,086 128,086 128,086 128,086 128,086 COGS 60,876 60,876 60,876 60,876 60,876 S&A 30,000 30,000 30,000 30,000 30,000 Depreciation 22,696.80 22,696.80 22,696.80 22,696.80 22,696.80 Investment in NWC 1,126.00 598 598 598 598 598 Investment in Gross PPE 113,484.00 The firm has a capital structure of 36.00% debt and 64.00% equity. The cost of debt is 10.00%, while the cost of equity is...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 123,751.00 123,751.00 123,751.00 123,751.00 123,751.00 Cost of Goods 69,125.00 69,125.00 69,125.00 69,125.00 69,125.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 20,811.80 20,811.80 20,811.80 20,811.80 20,811.80 Investment in NWC 1,108.00 576.00 576.00 576.00 576.00 576.00 Investment in Gross PPE 104,059.00 The firm has a capital structure of 43.00% debt and 57.00% equity. The cost of debt is 10.00%, while the cost of...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3...
A firm has projected the following financials for a possible project: YEAR 0 1 2 3 4 5 Sales 124,757.00 124,757.00 124,757.00 124,757.00 124,757.00 Cost of Goods 65,261.00 65,261.00 65,261.00 65,261.00 65,261.00 S&A 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 Depreciation 20,786.40 20,786.40 20,786.40 20,786.40 20,786.40 Investment in NWC 1,197.00 559.00 559.00 559.00 559.00 559.00 Investment in Gross PPE 103,932.00 The firm has a capital structure of 34.00% debt and 66.00% equity. The cost of debt is 10.00%, while the cost of...
A capital budget project is estimated to have the following after-tax cash flows, by year: 0...
A capital budget project is estimated to have the following after-tax cash flows, by year: 0 1 2 3 4 -$35,000 $13,000 $15,000 $17,000 $19,000 Use the information in the table above for the following questions 11a. through 11f. The company utilizes a discount rate of 9% to evaluate capital projects. You may have rounding errors in your calculations so choose the closest answer. 1. Find NPV, IRR, MIRR, and PI for the project shown above 2. Find Payback and...
We have the following two projects: Year Project X     Project Y 0   -29,500....... -45,000 1   9,000...
We have the following two projects: Year Project X     Project Y 0   -29,500....... -45,000 1   9,000 ...............0 2   9,000............... 0 3   9,000 .............. 0 4   9,000 ...............0 5   9,000........... $84,000 a) Show each project on the time-line. b) What is payback period? What are payback period values for projects X & Y? How do you interpret them? Given a threshold of 3 years which project or projects should you choose if they are independent? What if they are mutually exclusive?...
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0...
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0 -5,300 1 1,325 2 2,148 3 2,209 what is the IRE for the project 2)you've estimated the following cash flows (in$) for 2 projects: A. B. C.    year. ProjectA. ProjectB 0. -78 -261 1 15 50 2 21 73 3 29 82 4 35 127 the required return is 7% for both projects What is the IRR for project B? What is the...
Glasgow company has the following financial data for project X (3-year project): Year 0 Year 1...
Glasgow company has the following financial data for project X (3-year project): Year 0 Year 1 Year 2 Year 3 CF -10,000 5,000 4,000 4,000 The company’s capital structure is distributed equally between debt, preferred stock and common stock. It has also the following information: 1- After tax cost of debt: 5.8%. Tax rate: 40% 2- Preferred stocks are selling at $65 per share and pay a dividend of $8 per share 3- Common stocks are selling at $40 per...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$552,600 −$521,000 1 217,700 207,400 2 227,600 217,200 3 234,800 225,100 4 194,500 185,900 What is the crossover rate for these two projects?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT