Question

In: Accounting

1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0...

1)you've estimated the following cash flows (in$) for a project
A. B
year. cash flow
0 -5,300
1 1,325
2 2,148
3 2,209
what is the IRE for the project


2)you've estimated the following cash flows (in$) for 2 projects:
A. B. C.   
year. ProjectA. ProjectB
0. -78 -261
1 15 50
2 21 73
3 29 82
4 35 127
the required return is 7% for both projects
What is the IRR for project B?
What is the NVP of project B?
If the projects are mutually exclusive which project you choose? project B, based on the IRR; project A, based on IRR; project A, based on IRR; project B based on NVP?

3) wh smith company is evaluating three projects: A,B,C with cash flows as given in the table. each project requires an initial investment of $97,000 and has requirement return of 7%
year. A. B. C
1 50,000 0 20,000
2 40,000 50,000 40,000
3 20,000 50,000 40,000
4 10,000 40,000 40,000
What is the payback period for a project A(in years)?

Solutions

Expert Solution

(1) IRR calculation-

Year Cash flow
0 -5300
1 1325
2 2148
3 2209
Total 382

at IRR the NPV of the project will be zero. Current Value of the project without discounting = $382 in 3 years ($127.33) per year

Hence Dummy IRR = $127.33/$5300*100 =2.40%

Lets take IRR between 3% to 4%

Year Cash flow PVF@3% PV of cash flow PVF@4% PV of cash flow
0 -5300 1 -5300 1 -5300
1 1325 0.97087 1286 0.96154 1274
2 2148 0.94260 2025 0.92456 1986
3 2209 0.91514 2022 0.88900 1964
NPV 32.65 -76.22

NPV at IRR 3% = $32.65

NPV at IRR 4% =$-76.22

Applying Interpolation IRR= 3% +[1%/(32.65-(-76.22)]*32.65 = 3.296%

---------------------------------------------------------------------------------------------------------

(2)

Year Project-A Project-B
0 -78 -261
1 15 50
2 21 73
3 29 82
4 35 127

# Requirement -1(IRR of project-B)-

Lets take IRR between 8-9% for project B

Year Project-B CASH FLOW pvf@8% PV of cash flows PVF@9% PV of the cash flow
0 -261 1 -261 1 -261
1 50 0.9259 46.30 0.917 45.87
2 73 0.8573 62.59 0.842 61.44
3 82 0.7938 65.09 0.772 63.32
4 127 0.7350 93.35 0.708 89.97
NPV 6.33 -0.40

By applying Interpolation IRR of project -B = 8%+[1%/(6.33-(-0.40)]*6.33 = 8.940%

-------------

#Requirement-2(NPV of project-B)

Year Project-B CASH FLOW pvf@7% PV of cash flows
0 -261 1 -261
1 50 0.9346 46.73
2 73 0.8734 63.76
3 82 0.8163 66.94
4 127 0.7629 96.89
NPV 13.31

NPV of the project B = $13.31

----------------

#Requirement-3(Which project to be shown)

Year Project-A pvf@7% PV of cash flows
0 -78 1 -78
1 15 0.9346 14.02
2 21 0.8734 18.34
3 29 0.8163 23.67
4 35 0.7629 26.70
NPV 4.73

NPV of the project A =$4.73

NPV of Project B = $13.31

If projects are mutually exclusive then the project having highest NPV should be choosen.

Hence project B should be choosen based on NPV

--------------------------------------------------------------------------------------

(3)

(i)Normal pay back period-

Normal pay back period = A +(B/C)

Where,
A is the last period number with a negative cumulative cash flow;
B is the absolute value (i.e. value without negative sign) of cumulative net cash flow at the end of the period A; and
C is the total cash inflow during the period following period A

Year Cash Inflows(project -A) Cumulative
0 -97000 -97000
1 50000 -47000
2(A) 40000 -7000(B)
3 20000(C) 13000
4 10000 23000

Hence normal pay back period = 2 + (7000/20000) = 2.35 years

(ii) Discounted pay back period-

Discounted pay back period = A +(B/C)

Where,
A = Last period with a negative discounted cumulative cash flow;
B = Absolute value of discounted cumulative cash flow at the end of the period A; and
C = Discounted cash flow during the period after A.

Year Cash Inflows(project -A) PVF@7% PV of cash flow Cumulative
0 -97000 1 -97000 -97000
1 50000 0.93458 46729 -50271
2(A) 40000 0.87344 34938 -15333(B)
3 20000 0.81630 16326(C) 992
4 10000 0.76290 7629 8621

Discounted pay back period = 2 + (15333/16326) = 2.94 years.


Related Solutions

There is a project with the following cash flows : Year Cash Flow 0 −$21,800 1...
There is a project with the following cash flows : Year Cash Flow 0 −$21,800 1 6,300 2 7,350 3 6,750 4 4,400 What is the payback period? Multiple Choice a. 4.00 years b. 3.32 years c. 3.74 years d. 3.56 years e. 2.79 years
There is a project with the following cash flows : Year Cash Flow 0 −$23,700 1...
There is a project with the following cash flows : Year Cash Flow 0 −$23,700 1 7,000 2 7,700 3 7,100 4 5,100 What is the payback period? Multiple Choice 2.73 years 4.00 years 3.81 years 3.63 years 3.37 years
A project has the following cash flows:    Year Cash Flow 0 $ 43,500 1 –  ...
A project has the following cash flows:    Year Cash Flow 0 $ 43,500 1 –   22,500 2 –   33,500    a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project, if the required return is 12 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
A project has the following cash flows: Year Cash Flow 0 $ 40,000 1 – 19,000...
A project has the following cash flows: Year Cash Flow 0 $ 40,000 1 – 19,000 2 – 30,000 What is the IRR for this project? What is the NPV of this project, if the required return is 11 percent? What is the NPV of the project if the required return is 0 percent? What is the NPV of the project if the required return is 22 percent?
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000...
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000 2 – 37,000 What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project has the following cash flows: Year Cash Flow 0 $ 42,000 1 – 21,000...
A project has the following cash flows: Year Cash Flow 0 $ 42,000 1 – 21,000 2 – 32,000 What is the IRR for this project? (Round your answer to 2 decimal places. (e.g., 32.16)) IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) NPV $ What is...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -29 -45 1 30 45 2 40 50 3 50 50 The appropriate discount rate is 9%. Part 1 What is the NPV of project A (in $ million)? Part 2 What is the NPV of project B (in $ million)?
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1...
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1 -80,500 2 138,425 3 -105,455 4 30,030 Required: 1.1.Fill in the following table: Cost of Capital (%) Project NPV 0 5 10 15 20 25 30 35 50 1.2.Use the values developed in part (1.1) to draw an NPV profile for this project. 1.3.What is the IRR for this project? 1.4.Describe the conditions under which the company should accept this project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT