Question

In: Accounting

Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous...

Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows:

Activity Budgeted Activity Cost
Production $489,100
Setup 259,000
Inspection 110,400
Shipping 180,600
Customer service 93,100
Total $1,132,200

The activity bases identified for each activity are as follows:

Activity Activity Base
Production Machine hours
Setup Number of setups
Inspection Number of inspections
Shipping Number of customer orders
Customer service Number of customer service requests

The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows:

Machine Hours Number of
Setups
Number of
Inspections
Number of
Customer Orders
Customer
Service
Requests
Units
White sugar 2,950 180 240 860 70 7,375
Brown sugar 1,880 270 360 2,370 440 4,700
Powdered sugar 1,870 250 600 1,070 190 4,675
Total 6,700 700 1,200 4,300 700 16,750

Each product requires 0.9 machine hour per unit.

Required:

If required, round all per unit amounts to the nearest cent.

1. Determine the activity rate for each activity.

Production $ per machine hour
Setup $ per setup
Inspection $ per move
Shipping $ per cust. ord.
Customer service $ per customer service request

2. Determine the total and per-unit activity cost for all three products.

Total Activity Cost Activity Cost Per Unit
White sugar $ $
Brown sugar
Powdered sugar

3. Why aren’t the activity unit costs equal across all three products since they require the same machine time per unit?

The unit costs are different because the products consume many activities in ratios different from the  .

Solutions

Expert Solution

Answer 1)

Calculation of Activity rate for each Activity

Activity Centre

Cost Driver

Manufacturing overheads (In $)

Total number of events

Activity Rate (Total Costs/ Total number of events) (In $)

Production

Machine hours

               489,100

                                  6,700

                    73.00

Setup

Number of Setups

               259,000

                                      700

                  370.00

Inspection

Number of Inspections

               110,400

                                  1,200

                   92.00

Shipping

Number of Customer Orders

               180,600

                                  4,300

                    42.00

Customer Care

Number of Customer Service

                 93,100

                                      700

                  133.00

Total

           1,132,200

Answer 2)

Calculation of total and per unit activity cost for all three costs

Activity Centre

Cost Driver

Activity Rate (In $)

Total number of Activities Consumed

Assigned Activity Costs (Activity Rates X Activity Consumed)       (In $)

White Sugar

Brown Sugar

Powdered Sugar

White Sugar

Brown Sugar

Powdered Sugar

Production

Machine hours

                   73.00

                                  2,950

                    1,880

                                  1,870

           215,350

    137,240

         136,510

Setup

Number of Setups

                 370.00

                                      180

                        270

                                      250

              66,600

       99,900

           92,500

Inspection

Number of Inspections

                   92.00

                                      240

                        360

                                      600

              22,080

       33,120

           55,200

Shipping

Number of Customer Orders

                   42.00

                                      860

                    2,370

                                  1,070

              36,120

       99,540

           44,940

Customer Care

Number of Customer Service

                 133.00

                                        70

                        440

                                      190

                9,310

       58,520

           25,270

Total (A)

           349,460

    428,320

         354,420

Number of units manufactured (B)

                7,375

         4,700

             4,675

Manufacturing overheads per unit (A)/ (B)

                47.38

         91.13

             75.81

Answer 3)

Machine hours consumed by each product

White Sugar = Total machine hours consumed/ number of units manufactured

                        = 2,950 machine hours/ 7,375 units

                        = 0.40 machine hour per unit

Brown Sugar = Total machine hours consumed/ number of units manufactured

                        = 1,880 machine hours/ 4,700 units

                        = 0.40 machine hour per unit

Powdered Sugar = Total machine hours consumed/ number of units manufactured

                        = 1,870 machine hours/ 4,675 units

                        = 0.40 machine hour per unit

Even though each product consumes 0.40 machine hours per unit, still the activity unit costs are different. It is because under Activity Based costing, Activity costs (Overheads) are allocated on the basis of different activity rates (unlike in case of Traditional costing where single predetermined rate is used for allocation of overheads). Since the activities consumed by each product are different, if overheads are allocated on the basis of activity rates for different activities, the total and per unit activity costs are different for the three products.


Related Solutions

Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous...
Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: 1 Activity Budgeted Activity Cost 2 Production $500,000.00 3 Setup 144,000.00 4 Inspection 44,000.00 5 Shipping 115,000.00 6 Customer service 84,000.00 7 Total $887,000.00 The activity bases identified for each activity are...
Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous...
Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $466,200 Setup 219,500 Inspection 106,600 Shipping 133,200 Customer service 48,000 Total $973,500 The activity bases identified for each activity are as follows: Activity Activity Base Production Machine...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: ActivityBudgeted Activity Cost Production $448,900 Setup 130,200 Inspection 94,600 Shipping 136,400 Customer service 79,800 Total $889,900 The activity bases identified for each activity are as follows: ActivityActivity Base ProductionMachine...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: ActivityBudgeted Activity Cost Production $448,900 Setup 130,200 Inspection 94,600 Shipping 136,400 Customer service 79,800 Total $889,900 The activity bases identified for each activity are as follows: ActivityActivity Base ProductionMachine...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $465,000 Setup 189,500 Inspection 105,300 Shipping 159,600 Customer service 58,500 Total $977,900 The activity bases identified for each activity are as follows: Activity Activity...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $444,600 Setup 190,000 Inspection 91,200 Shipping 151,200 Customer service 52,800 Total $929,800 The activity bases identified for each activity are as follows: Activity Activity...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $444,600 Setup 190,000 Inspection 91,200 Shipping 151,200 Customer service 52,800 Total $929,800 The activity bases identified for each activity are as follows: Activity Activity...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $427,000 Setup 187,000 Inspection 120,000 Shipping 131,200 Customer service 80,400 Total $945,600 The activity bases identified for each activity are as follows: Activity Activity...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $427,000 Setup 187,000 Inspection 120,000 Shipping 131,200 Customer service 80,400 Total $945,600 The activity bases identified for each activity are as follows: Activity Activity...
Activity-Based Costing Pure Cane Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
Activity-Based Costing Pure Cane Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Activity Costs Production $247,500 Setup 48,000 Inspection 12,500 Shipping 69,300 Customer service 27,600     Total $404,900 The activity bases identified for each activity are as follows: Activity Activity Base...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT