Question

In: Accounting

Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...

  1. Activity-Based Product Costing

Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows:

Activity

Budgeted Activity Cost

Production

$444,600

Setup

190,000

Inspection

91,200

Shipping

151,200

Customer service

52,800

Total

$929,800

The activity bases identified for each activity are as follows:

Activity

Activity Base

Production

Machine hours

Setup

Number of setups

Inspection

Number of inspections

Shipping

Number of customer orders

Customer service

Number of customer service requests

The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows:

Machine Hours

Number of
Setups

Number of
Inspections

Number of
Customer Orders

Customer
Service
Requests

Units

White sugar

3,430

130

240

720

40

8,575

Brown sugar

2,180

190

360

1,980

250

5,450

Powdered sugar

2,190

180

600

900

110

5,475

Total

7,800

500

1,200

3,600

400

19,500

Each product requires 0.9 machine hour per unit.

Required:

If required, round all per unit amounts to the nearest cent.

1. Determine the activity rate for each activity.

Production

$ per machine hour

Setup

$ per setup

Inspection

$ per move

Shipping

$ per cust. ord.

Customer service

$ per customer service request

2. Determine the total and per-unit activity cost for all three products.

Total Activity Cost

Activity Cost Per Unit

White sugar

$

$

Brown sugar

Powdered sugar

3. Why aren’t the activity unit costs equal across all three products since they require the same machine time per unit?

The unit costs are different because the products consume many activities in ratios different from the .

    Solutions

    Expert Solution

    Activity

    Budgeted Activity Cost [A] cost driver

    Total activity [B]

    Activity rates [A]/[B]

    Production

    $444,600

    Machine hours

                         7,800

    $57

    per machine hour

    Setup

    190,000

    Number of set ups

    500

    $380

    per setup

    Inspection

    91,200

    Number of inspection

    1200

    $76

    per move

    Shipping

    151,200

    Number of customer order

    3,600

    $42

    per cust. ord.

    Customer service

    52,800

    customer service requiest 400

    $132

    per customer service request

    $929,800

    2)Total aCTIVITY COST

    working note:

    Activity Rate White sugar brown sugar Powdered sugar Total

    Production

    $57

    $195,510[$57*3430] $124,260[$57*2180] $124,830[$57*2190] $444,600

    Setup

    $380

    $49,400[$380*130 $72,200[$380*190 $68,400[$380*180 $190,000

    Inspection

    $76

    $18,240[$76*240] $27,360[$76*360 $45,600[$76*600] $91,200

    Shipping

    $42

    $30,240[$42*720] $83,160[$42*1980] $37,800[$42*900] $151,200

    Customer service

    $132

    $5,280[$132*40] $33,000[$132*250] $14,520[$132*110] $52,800
    Total product cost $298,670 $339,980 $291,150 $929,800
    Number of units 8,575 5,450 5,475
    Per unit cost $34.83[$298,670/8575] $62.38 $53.18

    Total Activity Cost

    Activity Cost Per Unit

    White sugar

    $298,670

    $34.83

    Brown sugar

    $339,980

    $62.38

    Powdered sugar

    $291,150

    $53.18

    3. The unit costs are different because the products consume many activities in ratios different from the machine hour per unit consumption

    Please upvote if you find this helpful.Incase of query please comment.


    Related Solutions

    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: ActivityBudgeted Activity Cost Production $448,900 Setup 130,200 Inspection 94,600 Shipping 136,400 Customer service 79,800 Total $889,900 The activity bases identified for each activity are as follows: ActivityActivity Base ProductionMachine...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: ActivityBudgeted Activity Cost Production $448,900 Setup 130,200 Inspection 94,600 Shipping 136,400 Customer service 79,800 Total $889,900 The activity bases identified for each activity are as follows: ActivityActivity Base ProductionMachine...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $465,000 Setup 189,500 Inspection 105,300 Shipping 159,600 Customer service 58,500 Total $977,900 The activity bases identified for each activity are as follows: Activity Activity...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $444,600 Setup 190,000 Inspection 91,200 Shipping 151,200 Customer service 52,800 Total $929,800 The activity bases identified for each activity are as follows: Activity Activity...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $427,000 Setup 187,000 Inspection 120,000 Shipping 131,200 Customer service 80,400 Total $945,600 The activity bases identified for each activity are as follows: Activity Activity...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Product Costing Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $427,000 Setup 187,000 Inspection 120,000 Shipping 131,200 Customer service 80,400 Total $945,600 The activity bases identified for each activity are as follows: Activity Activity...
    Activity-Based Costing Pure Cane Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar)...
    Activity-Based Costing Pure Cane Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Activity Costs Production $247,500 Setup 48,000 Inspection 12,500 Shipping 69,300 Customer service 27,600     Total $404,900 The activity bases identified for each activity are as follows: Activity Activity Base...
    Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous...
    Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: 1 Activity Budgeted Activity Cost 2 Production $500,000.00 3 Setup 144,000.00 4 Inspection 44,000.00 5 Shipping 115,000.00 6 Customer service 84,000.00 7 Total $887,000.00 The activity bases identified for each activity are...
    Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous...
    Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $466,200 Setup 219,500 Inspection 106,600 Shipping 133,200 Customer service 48,000 Total $973,500 The activity bases identified for each activity are as follows: Activity Activity Base Production Machine...
    Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous...
    Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Budgeted Activity Cost Production $489,100 Setup 259,000 Inspection 110,400 Shipping 180,600 Customer service 93,100 Total $1,132,200 The activity bases identified for each activity are as follows: Activity Activity Base Production Machine...
    ADVERTISEMENT
    ADVERTISEMENT
    ADVERTISEMENT