In: Operations Management
Assume on your project, you have a requested but
unresolved change as you provided direction to the seller to take
action. You consider this change to be one that is—
a. A claim
b. A constructive change to the contract
c. One that requires the need to negotiate a settlement
d. An undefinitized contractual action
(b) A constructive change to the contract.
Explanation - The situation is a constructive change to the contract, The changes can be disagreed by one party and lead to claim against the other party. These changes are documented by project correspondence and are uniquely identified