Question

In: Finance

Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000.


Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000. The project is complete, and the buyer has agreed that the costs were, in fact, $200,000. Because the seller's costs came in lower than the estimated costs, the seller shares in the savings: 80% to the buyer and 20% to the seller. Calculate the final fee and final price.

The answer is :

Fee $27,000
Price: $227,000

Solutions

Expert Solution

Estimated Cost: $210,00)

Actual cost; $200,000

Therefore, cost saving= Estimated cost - Actual Cost= $210,000-200,000 = $10,000

It is agreed that 80% of the cost saving will be passed on to the buyer which is 80% of $10,000= $8,000

Therefore, cost to be added to the fee (Sellers share)= $10,000-$8,000 = $2,000

Therefore, Total Fee= Agreed fee + seller's share of cost savings = $25,000+$2,000 = $27,000

Total Price= Actual Cost + Total Fee = $200,000+$27,000 = $227,000


Related Solutions

Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the point of total assumption.$183,333
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the final price.$200,000
1) Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $9,000,000 and the target fee is $850,000.
1) Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $9,000,000 and the target fee is $850,000. The project is over, and the buyer has that the costs were, in fact, $8,000,000. Because the seller's cost came in lower than the estimated costs, the seller shares in the savings: 70% to the buyer and 30% to the seller. The ceiling price is $12,500,000. Calculate the final fee and final priceFee $1,150,000...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000,...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000, and a fixed fee of $1,000. Any cost overruns or underruns will be shared between the buyer and the seller by 50% and 50%, respectively. When the actual cost of $8,000 is incurred, how much will the supplier get paid in total?
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000,...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000, and a fixed fee of $1,000. Any cost overruns or underruns will be shared between the buyer and the seller by 50% and 50%, respectively. When the actual cost of $8,000 is incurred, how much will the supplier get paid in total?
A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform...
A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform some work for you. The contract parameters include: Estimated Cost: $100,000 Fixed Fee: $10,000 If the seller is able to complete the work for a cost of $80,000, what will be the final price paid to the seller? B. You have signed a cost plus percentage cost (CPPC) contract with a supplier to perform some work for you. The contract parameters include the following:...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to construct an electric generator for Blue Spruce Corporation. At the contract date, Larkspur estimated that it would take two years to complete the project at a cost of $2,440,000. The fixed fee stipulated in the contract was $549,000. Larkspur appropriately accounts for this contract under the percentage-of-completion method. During 2020, Larkspur incurred costs of $976,000 related to this project. The estimated cost at December...
There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has...
There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has several common variations. It is not unusual for any specific contract to have special terms and agreements, so the basic contract is just the starting point. The project manager is most interested in the terms that define and help to control costs, schedule, and quality. Among the different types of contracts, which contracts do you think would be easiest for ADC to manage, and...
Pricing is based on a cost-plus formula where costs are estimated then contracts are priced at...
Pricing is based on a cost-plus formula where costs are estimated then contracts are priced at 50% above cost. What would happen if Maya picked the “wrong” cost driver to set target costs and prices? What other implications may result from choosing the wrong cost driver?
Hardhat has a contract to construct a $5,000,000 bridge at an estimated cost of $4,000,000. The...
Hardhat has a contract to construct a $5,000,000 bridge at an estimated cost of $4,000,000. The contract is to start in 2016 and will be completed in 2018. Below is the data for 2016-18: 2016                          2017                         2018 Costs to date                                               1,000,000 2,900,000                 4,100,000 Est. costs to complete                              3,000,000                 1,200,000 - Progress billings during year                   900,000                    2,400,000                 1,700,000 Cash collected during year                      750,000                    2,250,000                 2,000,000 Compute the percentage of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT