Question

In: Operations Management

A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform...

A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform some work for you. The contract parameters include: Estimated Cost: $100,000 Fixed Fee: $10,000 If the seller is able to complete the work for a cost of $80,000, what will be the final price paid to the seller?

B. You have signed a cost plus percentage cost (CPPC) contract with a supplier to perform some work for you. The contract parameters include the following: Estimated Cost: $100,000 Fee Percentage: 10% The supplier with your authorization is able to complete the work for a cost of $120,000. There is no change in scope. What is the final price paid to the supplier?

Solutions

Expert Solution

Answer A: Final price= $80000+ Fixed cost= 80000+ 10000= $90,000

Answer B: because we agreed to pay 10% extra of the cost price

Final price= work completion cost + 10% of work completion cost= 120,000 + 120000*0.1 = $132,000


Related Solutions

Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000.
Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000. The project is complete, and the buyer has agreed that the costs were, in fact, $200,000. Because the seller's costs came in lower than the estimated costs, the seller shares in the savings: 80% to the buyer and 20% to the seller. Calculate the final fee and final price.The answer is :Fee $27,000Price: $227,000
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to construct an electric generator for Blue Spruce Corporation. At the contract date, Larkspur estimated that it would take two years to complete the project at a cost of $2,440,000. The fixed fee stipulated in the contract was $549,000. Larkspur appropriately accounts for this contract under the percentage-of-completion method. During 2020, Larkspur incurred costs of $976,000 related to this project. The estimated cost at December...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000,...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000, and a fixed fee of $1,000. Any cost overruns or underruns will be shared between the buyer and the seller by 50% and 50%, respectively. When the actual cost of $8,000 is incurred, how much will the supplier get paid in total?
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000,...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000, and a fixed fee of $1,000. Any cost overruns or underruns will be shared between the buyer and the seller by 50% and 50%, respectively. When the actual cost of $8,000 is incurred, how much will the supplier get paid in total?
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the point of total assumption.$183,333
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the final price.$200,000
1) Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $9,000,000 and the target fee is $850,000.
1) Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $9,000,000 and the target fee is $850,000. The project is over, and the buyer has that the costs were, in fact, $8,000,000. Because the seller's cost came in lower than the estimated costs, the seller shares in the savings: 70% to the buyer and 30% to the seller. The ceiling price is $12,500,000. Calculate the final fee and final priceFee $1,150,000...
There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has...
There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has several common variations. It is not unusual for any specific contract to have special terms and agreements, so the basic contract is just the starting point. The project manager is most interested in the terms that define and help to control costs, schedule, and quality. Among the different types of contracts, which contracts do you think would be easiest for ADC to manage, and...
28. In a fixed price contract, the fee or profit is: A. Unknown B. Part of...
28. In a fixed price contract, the fee or profit is: A. Unknown B. Part of the negotiation involved in paying every invoice C. Applied as line item to every invoice D. Determined with the other party at the end of the project 29. All of the following are generally part of the contract documents except. 1. Proposal 2. Scope of work 3. Terms and conditions 4. Negotiation process
An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a...
An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a given day the contractor is faced with three electrical jobs associated with various projects. Each subcontractor will have enough time to work on up to two projects during the day. Each project should be completed by exactly two subcontractors. Given below are the distances between the subcontractors and the projects a. Draw a network to represent the possible subcontractor-project assignments. b. Develop a linear...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT