Question

In: Accounting

There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has...

There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has several common variations. It is not unusual for any specific contract to have special terms and agreements, so the basic contract is just the starting point. The project manager is most interested in the terms that define and help to control costs, schedule, and quality.

Among the different types of contracts, which contracts do you think would be easiest for ADC to manage, and why? Which contracts would be the most difficult for ADC to manage, and why?

Examples of the contract types include the following:

  • Firm fixed price
  • Fixed price with targets
  • Fixed price at cost
  • Time and materials
  • Cost sharing
  • Cost plus

Solutions

Expert Solution

1. Types of Contracts

A Construction Contract is any contract which is entered into specifically for construction of an asset or a combination of assets that are closely inter-linked or inter-dependent w.r.t. their technology/design/function or the nature of their ultimate purpose or use.

A. Fixed Price Contract

A contract in which the contractor agrees to a fixed contract price. In some cases, there may be an element of cost escalation clause in the contract which is mutually agreed to between the parties.

For example, the parties agree to include a clause in the contract for adjusting the Contract price on the basis of an increase in the cost of raw materials.

B. Cost-plus Contract

A contract in which the contractor is reimbursed for costs incurred or agreed costs, plus a percentage of these costs of a fixed fee.

2. Combining and Segmenting of Construction Contracts

I. Combining of Construction contracts – A group of contracts, either with one or more customers, shall be considered as a single construction contract when all the contracts are negotiated as a single package, are inter-linked and form part of a single project and are performed in a continuous sequence. F

or example, a contract for construction of three similar buildings (similar in all aspects) on a single plot negotiated all at once.

II. Segmenting of Construction contracts – Where a contract includes more than one asset, the construction of each asset should be treated as a separate construction contract when separate proposals have been given for each asset, each asset has been separately negotiated and the costs and revenues of each asset can be identified separately.

For example, a contract for construction of three different buildings on the same plot with different specifications and each building is separately negotiated with the contractor.

3. Revenue from a Contract

The revenue from a contract includes the following to the extent it is probable of generating revenue and is measurable:

i. The initial amount of revenue agreed in the contract;

ii. Claims and incentives on account of variations in contract work;

4. Costs of a Contract

The cost of a contract includes the following:

i. Directly related costs that to the specific contract

ii. Costs which are generally attributable and allocated to the contract activities

iii. Other costs which are specifically chargeable to the customer under the terms of the contract

5. Recognition of Revenue and Cost from a Contract

Where the result or outcome of any contract for construction can be projected, the related contract revenue and contract costs shall be recognized by taking into account the stage of completion of such contract. Expected losses shall be recognized immediately as expenses.

I. In case of a fixed price contract, the outcome can be estimated in a reliable manner when all the following conditions are satisfied:

i. The entire revenue from a contract can be reliably measured

ii. It is apparent that the economic benefits of such contract will flow to the organization

iii. Both contract costs and stage of completion can be measured

iv. Contract costs can be clearly identified for a comparison between actual costs and prior estimates

II. In case of a cost-plus contract, the outcome can be estimated in a reliable manner when all the following conditions are satisfied:

i. It is probable that economic benefits of the contract will flow to the organization

ii. Contract costs attributable to the contract can be identified and measured clearly

III. Percentage of completion method – This method defines the recognition of revenue and cost taking into account the stage of completion of a contract. Under this method, revenue and cost are recognized in the statement of profit and loss in the accounting periods in which the work is performed.

IV. Contract work-in-progress – A contractor may incur costs that relate to future activity in a contract. Such costs are recognized as an asset if it is probable that they will be recovered.

6. Determination of the stage of completion

The stage of completion of a contract may be determined in different ways. Depending on the nature of the contract, the methods may include:

I. The proportion of contract cost incurred w.r.t. the total estimated cost of contract; (for example: if the total cost of the contract is Rs. 30 lakhs and the cost incurred till date is Rs. 15 lakhs, the stage of completion is regarded as 50% complete i.e. 15 lakhs / 30 lakhs)

II. Surveys of work performed; (for example: in a contract for construction of a bridge, the site inspector can do a survey and with regards to the technicalities of the project, inform how much work has been completed)

III. Completion of a physical proportion of contract work (for example: in a contract for construction of a five storey building, if three stories are complete, the stage of completion for the same is regarded as 60% i.e. 3 stories/5 stories)

When the outcome of a construction contract cannot be estimated, the revenue and cost should be recognized only to the extent of contract costs incurred whose recovery is probable.

7. Recognition of Expected Losses

In a situation where it is expected that the total contract costs will exceed total revenue from such contract, the expected losses should be immediately recognized as expenses. The number of such losses shall be determined irrespective of the following:

i. The work has commenced on the contract or not

ii. The stage of completion

iii. The number of profits expected to arise on other contracts which are segmented as explained above

8. Disclosures required in financial statements

An organization should disclose:

i. Contract revenue recognized during the accounting period

ii. The methods used to determine the contract revenue recognized in the period

iii. The methods used to determine the stage of completion of contracts in progress

Following disclosures w.r.t. contracts in progress shall also be given at the reporting date:

i. An aggregate cost incurred and net profits recognized

ii. The amount received as advances

iii. The amount kept retentions

Note:

Advances are amounts received by the contractor before the related work is performed.

Retention is such amounts which are paid only after satisfying the conditions specified in the contract for payment of such amounts.

An organization should present:

i. The gross amount due from customers for contract work as an asset;

ii. The gross amount due to customers for contract work as a liability.

9. Major Differences between Ind AS (IAS) 11 and AS 7

As per Ind AS (IAS) 11

As per AS 7

No mention of borrowing costs specifically Specifically includes borrowing costs under expenses
Requires contract revenue to be measured at fair value of the consideration received/receivable Requires contract revenue recognition at a value of the consideration received/receivable
Deals with Service Concession Arrangements which is in respect of infrastructure projects on a build-operate-transfer pattern between a public and private enterprise

Does not deal with Service Concession Arrangements

Please give the Good Feedback (Thumbup)


Related Solutions

Contract types are often associated with two broad categories: fixed-price contracts and cost-reimbursable contracts. Briefly identify...
Contract types are often associated with two broad categories: fixed-price contracts and cost-reimbursable contracts. Briefly identify the factors to consider when determining which type is most appropriate for a planned contract.
A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform...
A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform some work for you. The contract parameters include: Estimated Cost: $100,000 Fixed Fee: $10,000 If the seller is able to complete the work for a cost of $80,000, what will be the final price paid to the seller? B. You have signed a cost plus percentage cost (CPPC) contract with a supplier to perform some work for you. The contract parameters include the following:...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to construct an electric generator for Blue Spruce Corporation. At the contract date, Larkspur estimated that it would take two years to complete the project at a cost of $2,440,000. The fixed fee stipulated in the contract was $549,000. Larkspur appropriately accounts for this contract under the percentage-of-completion method. During 2020, Larkspur incurred costs of $976,000 related to this project. The estimated cost at December...
Define output contract and requirements contract. What is the subject matter of these types of contracts?...
Define output contract and requirements contract. What is the subject matter of these types of contracts? Provide an example of each. Why are these contracts not enforceable under the common law?
Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000.
Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000. The project is complete, and the buyer has agreed that the costs were, in fact, $200,000. Because the seller's costs came in lower than the estimated costs, the seller shares in the savings: 80% to the buyer and 20% to the seller. Calculate the final fee and final price.The answer is :Fee $27,000Price: $227,000
Provide a definition of the following types of contracts, as it pertains to construction contracts: Cost...
Provide a definition of the following types of contracts, as it pertains to construction contracts: Cost Plus Fee Contract
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the point of total assumption.$183,333
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the final price.$200,000
What type of contract is the seller most concerned with regarding scope? Fixed Price Cost +...
What type of contract is the seller most concerned with regarding scope? Fixed Price Cost + fixed fee Make or Buy decisions Time & Material
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT