Question

In: Finance

​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $502...

​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $502 ​million, and will operate for20 years. OpenSeas expects annual cash flows from operating the ship to be $68.9 million and its cost of capital is 11.4%.

a. Prepare an NPV profile of the purchase.

b. Identify the IRR on the graph.

c. Should OpenSeas proceed with the​ purchase?

d. How far off could​ OpenSeas' cost of capital estimate be before your purchase decision would​ change?

Solutions

Expert Solution

Answer a)

NPV or the net present value method is a famous method to evaluate alternatives by determining the the current value of the alternatives.

NPV is the current (present) value of all the future cashflows (in the lifecycle of the project) discounted to the present. So, if we discount all future cashflow and find their present value and sum them, we get the NPV.

Using excel we can find it directly

Cashflows:

NPV Profile:

Finding the same uptill 100%

Discount Rate NPV of Cashflow (OpenSeas Inc.)
0% $876.00
1% $741.34
2% $624.61
3% $523.06
4% $434.37
5% $356.65
6% $288.28
7% $227.93
8% $174.47
9% $126.96
10% $84.58
11% $46.67
11.4% $32.63
12% $12.64
12.40% $0.00
13% -$17.99
14% -$45.67
15% -$70.73
16% -$93.50
17% -$114.25
19% -$150.55
21% -$181.15
22% -$194.69
23% -$207.20
24% -$218.80
25% -$229.58
26% -$239.61
27% -$248.96
28% -$257.69
29% -$265.87
30% -$273.54
31% -$280.75
32% -$287.52
33% -$293.91
34% -$299.93
35% -$305.63
36% -$311.02
37% -$316.13
38% -$320.97
39% -$325.58
40% -$329.96
41% -$334.13
42% -$338.10
43% -$341.89
44% -$345.52
45% -$348.98
46% -$352.29
47% -$355.47
48% -$358.51
49% -$361.44
50% -$364.24
51% -$366.94
52% -$369.53
53% -$372.03
54% -$374.43
55% -$376.75
56% -$378.98
57% -$381.14
58% -$383.22
59% -$385.23
60% -$387.18
61% -$389.06
62% -$390.88
63% -$392.64
64% -$394.35
65% -$396.00
66% -$397.61
67% -$399.17
68% -$400.68
69% -$402.15
70% -$403.57
71% -$404.96
72% -$406.31
73% -$407.62
74% -$408.89
75% -$410.13
76% -$411.34
77% -$412.52
78% -$413.67
79% -$414.79
80% -$415.88
81% -$416.94
82% -$417.98
83% -$418.99
84% -$419.98
85% -$420.94
86% -$421.88
87% -$422.80
88% -$423.70
89% -$424.58
90% -$425.44
91% -$426.29
92% -$427.11
93% -$427.91
94% -$428.70
95% -$429.47
96% -$430.23
97% -$430.97
98% -$431.69
99% -$432.40
100% -$433.10

Plotting on graph

Answer b)

IRR is the rate at which NPV = 0

From the graph we can easily see that for NPV = 0, rate is near to 12.4%

Also using formula:

IRR 12.4002%

-------------------------------------------

Answer c)

Since, we have IRR > WACC (11.4%), company should accept the project as per IRR rule.

As per IRR rule, if the IRR > WACC, accept the project else reject

-----------------------------------------

Answer d)

Our choice of acceptance of the project will change when IRR < WACC.

Hence, as soon as cost of capital > 12.4002%, our decision will change.

It is supported by the fact that at 13% rate, NPV is negative.


Related Solutions

​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $ 495 million and will operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $ 69.8 million and its cost of capital is 12.1 %. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas go ahead with the​ purchase? d. How far off could​ OpenSeas's cost of capital estimate be...
​ ​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost...
​ ​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $ 500$500 ​million, and will operate for 2020 years. OpenSeas expects annual cash flows from operating the ship to be $ 70.0$70.0 million and its cost of capital is 12.0 %12.0%. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas proceed with the​ purchase? d. How far off could​ OpenSeas' cost of capital estimate be...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $ 495 ​million, and will operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $ 70.7 million and its cost of capital is 12.1 %. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas proceed with the​ purchase? d. How far off could​ OpenSeas' cost of capital estimate be before...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $499...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $499 ​million, and will operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $69.9 million and its cost of capital is 12.2%. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas proceed with the​ purchase? d. How far off could​ OpenSeas' cost of capital estimate be before your purchase decision...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $497...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $497 ​million, and will operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $68.1 million and its cost of capital is 11.7%. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas proceed with the​ purchase? d. How far off could​ OpenSeas' cost of capital estimate be before your purchase decision...
OpenSeas, Inc., is evaluating the purchase of a new cruise ship. The ship will cost $500...
OpenSeas, Inc., is evaluating the purchase of a new cruise ship. The ship will cost $500 million, and will operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $70 million and its cost of capital is 12%. a. Prepare a NPV profile of the purchase. Do from rate 0% to 20% (please show me the formula you use, I have been trying to figure it out and cant) b. Identify the IRR on the...
OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $497...
OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $497 ​million, and will operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $70.1 million and its cost of capital is 12.1%. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas proceed with the​ purchase? d. How far off could​ OpenSeas' cost of capital estimate be before your purchase decision...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $495...
​OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship will cost $495 million, and will operate for 20years. OpenSeas expects annual cash flows from operating the ship to be $71.4 million and its cost of capital is 12.3%. a. Prepare an NPV profile of the purchase. b. Identify the IRR on the graph. c. Should OpenSeas proceed with the​ purchase? d. How far off could​ OpenSeas' cost of capital estimate be before your purchase decision would​...
OpenSeas, Inc., is evaluating the purchase of a new cruise ship. The ship would cost $400...
OpenSeas, Inc., is evaluating the purchase of a new cruise ship. The ship would cost $400 million today. OpenSeas expects annual cash flows from the new ship to be $70 million and these cash flows will last forever. The cost of capital is 16%. What is the IRR of the new cruise ship? Please make your answer in the unit of percent. ______% Following question 4, suppose the company has a desired payback period of 5 years. Which statement is...
OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship would cost $505...
OpenSeas, Inc. is evaluating the purchase of a new cruise ship. The ship would cost $505 ?million, but would operate for 20 years. OpenSeas expects annual cash flows from operating the ship to be $70.1 million? (at the end of each? year) and its cost of capital is 11.9% a. Prepare an NPV profile of the purchase using discount rates of 2.0%?, 11.5% and 17.0%. b. Identify the IRR on a graph. c. Is the purchase attractive based on these?...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT