Question

In: Accounting

Colina Production Company uses a standard costing system. The following information pertains to the current year....

Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products.

Actual production 5,500 units
Actual factory overhead costs ($16,500 is fixed) $40,125
Actual direct labor costs (11,250 hours) $131,625
Standard direct labor for 5,500 units:
Standard hours allowed 11,000 hours
Labor rate $12.00


The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost data for 5,000 units is as follows:

Variable factory overhead $22,500
Fixed factory overhead 13,500
Total factory overhead $36,000


What is the fixed overhead volume variance for Colina Production Company?

a.$3,600 (F)

b.$1,350 (U)

c.$4,125 (U)

d.$1,350 (F)

Solutions

Expert Solution

Answer : d. $1350 (F)

CALCULATION:

FIXED OVERHEAD VOLUME VARIANCE:

Step 1: Calculation of Standard rate per hour:

Standard fixed overhead = $13500

Budgeted hours = 10000 hours

Standard rate per hour = $13500 / 10000 hours = $1.35 per hour

Step 2: Fixed overhead volume variance:

Fixed overhead volume variance = (standard hours allowed * standard rate per hour) - Budgeted fixed overheads

                                                             = (11000 * $1.35) - $13500

                                                             = $14850 - $13500

Fixed overhead volume variance = $1350 Favorable

Alternatively,

Fixed overhead volume variance can be calculated as follows,

Step 1: Calculation of Standard rate per unit:

Standard fixed overhead = $13500

Budgeted units = 5000 units

Standard rate per unit = $13500 / 5000 units = $2.7 per unit

Step 2: Fixed overhead volume variance:

Fixed overhead volume variance = (Actual output * standard rate per Unit) - Budgeted fixed overheads

                                                             = 5500 units * $2.7 per unit - $13500

                                                             = $14850 - $13500

Fixed overhead volume variance = $1350 Favorable

All the best....


Related Solutions

McAllister, Inc., employs a normal costing system. The following information pertains to the year just ended.
McAllister, Inc., employs a normal costing system. The following information pertains to the year just ended.Total manufacturing costs were $1,320,000.Cost of goods manufactured was $1,286,000.Applied manufacturing overhead was 30 percent of total manufacturing costs.Manufacturing overhead was applied to production at a rate of 80 percent of direct-labor cost.Work-in-process inventory on January 1 was 75 percent of work-in-process inventory on December 31.Required:Compute the following to support the preparation of financial statements.1. Compute the total direct-labor cost for the year.2. Compute the...
The Rogers Company uses a standard cost accounting system and estimates production for the year to...
The Rogers Company uses a standard cost accounting system and estimates production for the year to be 60,000 units. At this volume, the company's variable overhead costs are $0.50 per direct labor hour. The company's single product has a standard cost of $30.00 per unit. Included in the $30.00 is $13.20 for direct materials (3 yards) and $12.00 of direct labor (2 hours). Production information for the month of March follows: Number of units produced 6,000 Materials purchased (18,500 yards)...
The Wolf Company uses a standard cost accounting system and estimates production for the year to...
The Wolf Company uses a standard cost accounting system and estimates production for the year to be 60,000 units. At this volume, the company's variable overhead costs are $0.50 per direct labor hour. The company's single product has a standard cost of $30.00 per unit. Included in the $30.00 is $13.20 for direct materials (3 yards) and $12.00 of direct labor (2 hours) and $4.80 for overhead. The company's variable overhead costs are $0.50 per direct labor hour. Production information...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria adopted the following standards: Inputs Total Direct materials 3 kg @ $2.50 per kg $7.50 Direct labour 5 hrs @ $7.50 per hr 37.50 Factory overhead: Variable $3.00 per direct labour hour 15.00 Fixed $4.00 per direct labour hour 20.00 Standard cost per unit $80.00 Alexandria’s July 2019 budget was based on the denominator volume of 40,000 direct labour hours. Alexandria’s actual July production...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria adopted the following standards: Inputs Total Direct materials 3 kg @ $2.50 per kg $7.50 Direct labour 5 hrs @ $7.50 per hr 37.50 Factory overhead: Variable $3.00 per direct labour hour 15.00 Fixed $4.00 per direct labour hour 20.00 Standard cost per unit $80.00 Alexandria’s July 2019 budget was based on the denominator volume of 40,000 direct labour hours. Alexandria’s actual July production...
The following is information related to X Company, a company that uses a standard cost system:...
The following is information related to X Company, a company that uses a standard cost system: Standard cost card for 1 unit of Product A: Direct materials – Raw Material A   (1 kilogram @ $ 20/kg.)           $ 20 Direct materials – Raw Material B   (1 kilogram @$ 10/kg.)         $ 10 Direct labour       (1 hour @ $15/hr.)                                 $ 15 Variable overhead       (1 hour @ $ 5/hr.)                                  $   5 Fixed overhead    (1 hour @ $ 10/hr.)                                       $ 10 Total budgeted fixed...
The following is information related to X Company, a company that uses a standard cost system:...
The following is information related to X Company, a company that uses a standard cost system: Standard cost card for 1 unit of Product A: Direct materials – Raw Material A   (1 kilogram @ $ 20/kg.)           $ 20 Direct materials – Raw Material B   (1 kilogram @$ 10/kg.)         $ 10 Direct labour       (1 hour @ $15/hr.)                                 $ 15 Variable overhead       (1 hour @ $ 5/hr.)                                  $   5 Fixed overhead    (1 hour @ $ 10/hr.)                                       $ 10 Total budgeted fixed...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year,...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company’s inventory balances were as follows:      Raw materials $ 25,500   Work in process $ 13,800   Finished goods $ 31,900 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 37,900 machine-hours and incur $151,600 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year,...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company’s inventory balances were as follows:      Raw materials $ 17,500   Work in process $ 9,760   Finished goods $ 29,280 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 36,300 machine-hours and incur $159,720 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year,...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company’s inventory balances were as follows:      Raw materials $ 17,500   Work in process $ 9,760   Finished goods $ 29,280 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 36,300 machine-hours and incur $159,720 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT