In: Accounting
At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows:
2013 |
2014 |
2015 |
|||
Cost incurred during the year |
$2,300,000 |
$3,600,000 |
$2,100,000 |
||
Estimated costs to complete |
5,300,000 |
2,000,000 |
0 |
||
Billings during the year |
1,700,000 |
4,000,000 |
4,300,000 |
||
Cash collections during the year |
1,600,000 |
3,600,000 |
4,300,000 |
Calculate the following:
Gross profit recognized: |
Percentage of completion Method |
Completed contract Method |
||
2013 |
||||
2014 |
||||
2015 |
||||
Total gross profit: |
Solution
Gross profit recognized: | Percentage of completion Method | Completed contract Method |
2013 | $ 726,316 | |
2014 | $ 842,039 | |
2015 | $ 431,646 | $ 2,000,000 |
Total gross profit | $ 2,000,000 | $ 2,000,000 |
Working
Working | 2013 | 2014 | 2015 | |
A | Contract Price | $ 10,000,000 | $ 10,000,000 | $ 10,000,000 |
B | Cost Incurred to Date | $ 2,300,000 | $ 5,900,000 | $ 8,000,000 |
C | Estimated cost yet to be incurred to complete the contract | $ 5,300,000 | $ 2,000,000 | $ 0 |
D = B+C | Total Cost | $ 7,600,000 | $ 7,900,000 | $ 8,000,000 |
E = (D/B) x 100 | % of Complition | 30% | 75% | 100% |
F = A x E | Revenue to date | $ 3,026,316 | $ 7,468,354 | $ 10,000,000 |
G | Revenue of Previous year | $ 0 | $ 3,026,316 | $ 7,468,354 |
H = F - G | Net Revenue this year | $ 3,026,316 | $ 4,442,039 | $ 2,531,646 |
I | Cost to date | $ 2,300,000 | $ 5,900,000 | $ 8,000,000 |
J | Cost to date of previous year | $ 0 | $ 2,300,000 | $ 5,900,000 |
K = I - J | Net Cost for the year | $ 2,300,000 | $ 3,600,000 | $ 2,100,000 |
L = H - K | Gross Profits | $ 726,316 | $ 842,039 | $ 431,646 |
Under completion of contract method no profit will be recognized until completion
In Year 3 total revenue - Total cost = Profit recognized........(10,000,000-8,000,000=$2,000,000 Gross profit)