1. A _________ schedule identifies major types of activities and approximate start and end dates for use in decision making about the scope of the project.

Chapter  8  Project Time Management

·         Types of Schedules

·         Elements of Time Management

·         Critical Path and Float

·         Managing the Schedule

·         Project Scheduling Software

1. A _________ schedule identifies major types of activities and approximate start and end dates for use in decision making about the scope of the project.

2. A schedule of activities that is prepared every two weeks is the _______ schedule.

3. How does a conceptual schedule differ from a master schedule?

4. If two activities are concurrent and they have the same completion date, they have a _______-_______ relationship.

5. A calendar that shows when a person, facility, or key piece of equipment is available is a __________ calendar.

6. The path through the network diagram that has trnal site.he longest total duration is the __________ path.

7. The difference between the sum of the activity durations along the critical path and the project completion date is the project _______.

8. If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called _________ time.

Solutions

Expert Solution

1. A Master schedule identifies major types of activities and approximate start and end dates for use in decision making about the scope of the project.

2. A schedule of activities that is prepared every two weeks is the Detail schedule.

3. How does a conceptual schedule differ from a master schedule?

The primary difference between master schedule and conceptual schedule is:

  • Conceptual schedule is the simple schedule, which defines the major activities or tasks of the project as well as defines the start and end of the project.
  • Master schedule is created after the project gets finalized. This schedule gets included in the contract signed between the 2 parties.

4. If two activities are concurrent and they have the same completion date, they have a finish-finish relationship.

5. A calendar that shows when a person, facility, or key piece of equipment is available is a resource calendar.

6. The path through the network diagram that has trnal site.he longest total duration is the critical path.

7. The difference between the sum of the activity durations along the critical path and the project completion date is the project slack.

8. If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called lead time.


Related Solutions

Discribe the three major decision-making research perspectives.How are they important to understand the three major types...
Discribe the three major decision-making research perspectives.How are they important to understand the three major types of decision-making approaches.
Lead me through a decision-making process on a major project you've completed.
Lead me through a decision-making process on a major project you've completed.
Draft a project proposal about AN agricultural project that you are about to start. Project 1:...
Draft a project proposal about AN agricultural project that you are about to start. Project 1: Goats farming (start with 100 Goats) Project 2: Crop farming (about 2.5 hectares), not fenced yet The proposal must be formal, well formatted and well articulated.
Use the FIVE-STEP decision making is shown in the answer. You are manager of IT project...
Use the FIVE-STEP decision making is shown in the answer. You are manager of IT project that involves two dozen offshore outsource worker who will do program development and testing. IDENTIFY several potential issues that could arise due to the outsourcing arrangement. What SPECIFIC STEPS would you take to improve the likelihood for success of the project?
The following table contains information related to the major activities of a research project. Use the...
The following table contains information related to the major activities of a research project. Use the information to do the following: a. Compute the expected duration, variance, and standard deviation for each activity b. What is the probability that the project finishes in less than 60 days? Activity Predecessor To Tm Tp A - 3 7 12 B A 8 11 17 C B 7 13 16 D B 7 10 13 E C 14 17 23 F D 12...
Instructions: Use the 6 step rational choice decision making process (Attached) to make a decision about...
Instructions: Use the 6 step rational choice decision making process (Attached) to make a decision about the following issue. Abdulla is in charge of scheduling the work for the service department of a car dealership. Recently, many of the sales representatives have been taking phone calls from their regular customers, and promising that their car repairs can be completed on certain days or at certain times. Things are not going well, and today it seems like everyone is unhappy –...
Question 1 <Budget & Schedule> Budget Start Week End Week Task1 93,019 1 10 Task2 140,853...
Question 1 <Budget & Schedule> Budget Start Week End Week Task1 93,019 1 10 Task2 140,853 1 10 Task3 183,921 1 10 Task4 205,017 1 10 <Cost Loaded Schedule> Week1 Week2 Week3 Week4 Week5 Task1 10% of Budget 10% of Budget 10% of Budget 10% of Budget 10% of Budget Task2 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget Task3 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15%...
1- Explain three types of biases people often exhibit in financial decision making and give an...
1- Explain three types of biases people often exhibit in financial decision making and give an example of each.
1.Define the three primary types of decision making systems and how robots in the workplace could...
1.Define the three primary types of decision making systems and how robots in the workplace could affect each. Provide examples to support your answer. 2.Describe the difference between transactional and analytical information, and determine how robots could affect each for a grocery store such as Safeway. 3. Robots are better than humans in all business capacities. Do you agree or disagree with this statement? Why? 4.What are the capabilities associated with digital dashboards? Provide two examples from your workplace, organization...
1. Please list the main types of approaches to decision making. How decisions CAN be made...
1. Please list the main types of approaches to decision making. How decisions CAN be made and what CAN influence the decision making process? Maximum: 200 words (fewer is better). Bullet-list format for key points and figures preferred, if applicable. 2. Please describe the views and assumptions about a "good" decision making process in the West. Who should be making the decision and how the process should go, as believed by the majority of the people in the West? Maximum:...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT