Question

In: Accounting

3. A two-workstation cell uses a kanban system to produce 200,000 parts per year. Expected leadtime...

3. A two-workstation cell uses a kanban system to produce 200,000 parts per year. Expected leadtime to replenish a container is 0.75 hours (i.e. 45 minutes). Parts cost $100 and have an inventory opportunity cost of 15%. There are three material handling options available:

            Manual - annual fixed cost of $25,000, cost per trip = $0.10, Max load size = 5;

            Push Cart - annual fixed cost of $25,000 + $5,000 initial investment (must be amortized over 5 years), cost per trip = $0.15, Max load size = 50; and

            Forklift - annual fixed cost of $25,000 + $60,000 initial investment (must be amortized over 8 years), cost per trip = $0.50, Max load size = 1000.

    Note: The company uses a MARR of 20% for all investments.

a) (25%) Specify the following system design parameters: container size, material handling type, # kanban that will be feasible and minimize material handling cost.

b) (5%) How would the system be different if it was controlled by CONWIP versus Kanban? Provide a conceptual example.

Solutions

Expert Solution

Particulars Manual Push Cart Forklift
Annual Fixed Cost (A)     25,000      25,000     25,000
Initial Investment              -          5,000     60,000
No. Of Years (Life)                5               8
Annual Depreciation (B)              -          1,000       7,500
Total Production 2,00,000 2,00,000 2,00,000
Load Size               5              50        1,000
No. oF trips     40,000        4,000           200
Cost Per Trip          0.10          0.15          0.50
Total Cost of Trips ©       4,000           600           100
Total Cost     29,000      26,600     32,600

Cost of Push Card Option is least. Hence, it is feasible with the minimal cost.


Related Solutions

Telstar Communications is going to purchase an asset for $420,000 that will produce $200,000 per year...
Telstar Communications is going to purchase an asset for $420,000 that will produce $200,000 per year for the next four years in earnings before depreciation and taxes. The asset will be depreciated using the three-year MACRS depreciation schedule in Table 12–12. (This represents four years of depreciation based on the half-year convention.) The firm is in a 30 percent tax bracket. Fill in the schedule below for the next four years. Earnings before depreciation and taxes year 1 year 2...
A project requires an initial investment of $200,000 in a machine and is expected to produce...
A project requires an initial investment of $200,000 in a machine and is expected to produce cost savings of $120,000 each year for two years. The tax rate is 30%. The machine will be depreciated using the MACRS 3-year schedule (first year 33%, second year 45%, third year 15% and fourth year 7%). The machine can be sold for $50,000 after two years. The project’s required return is 11%. (1)   What is the initial cash flow at t=0? (2)   What are the...
The two parts of the adaptive immune system are humoral immunity and cell-mediated immunity. Which of...
The two parts of the adaptive immune system are humoral immunity and cell-mediated immunity. Which of the following is true about cell-mediated immunity?(Check all that apply). A.It is primarily used to fight viruses. B. targets pathogens that have infected, and are inside of, cells. C. It involves T cells destroying infected cells D. It is primarily used to fight fungi. It involves the production of antigens by B cells
How do all the parts of the cell work together to produce proteins.
How do all the parts of the cell work together to produce proteins.
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years. Project Q costs $30,000 and is expected to produce cash flows of $9,250 per year for five years. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?
Deshaun uses a periodic inventory system. During the current year DWE reported beginning inventory of $200,000;...
Deshaun uses a periodic inventory system. During the current year DWE reported beginning inventory of $200,000; purchases of $2,500,000; cash sales of $1,000,000; credit sales (on account) of $3,500,000; and ending inventory of $150,000. The journal entries DWE would make during the year would include
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) modified internal rate of return (MIRR). The firm’s required rate of return is 14 percent. If the projects are independent, which project (s) should be selected? If...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
What are the main communicating cells of the nervous system? Describe the parts of the cell...
What are the main communicating cells of the nervous system? Describe the parts of the cell and the function of each part.
Cougar Athletics is soliciting bids on a 3-year contract to produce 3,000 t-shirts per year to...
Cougar Athletics is soliciting bids on a 3-year contract to produce 3,000 t-shirts per year to be given away at athletic events. You have decided to bid on the contract. It will cost you $3 per shirt in variable costs (buying plain t-shirts and paying an employee to imprint them) and $5,000 per year in fixed costs. A t-shirt printing machine will cost $7,500. The machine will be depreciated to zero over its 3-year life and it will not have...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT