Question

In: Economics

Here’s a table giving the benefits and costs of a project in each period and stuff....

Here’s a table giving the benefits and costs of a project in each period and stuff.

Period

0

1

2

3

Benefits

$0

$250

$250

$250

Costs

$400

$25

$25

$300

A. Calculate the net present value of this project using a discount rate of 3%.

B. Calculate the net present value of this project using a discount rate of 7%.

C. Calculate the benefit cost ratio of this project using a discount rate of 5%.

D. Based on your answers to A, B and C, make a guess as to the internal rate of return for this project.

E. Discuss whether this project should be done, based on your answers to the above questions.

Solutions

Expert Solution

Period

0

1

2

3

Benefits

$0

$250

$250

$250

Costs

$400

$25

$25

$300

Net Cash Flow

-400

225

225

-50

A. Calculate the net present value of this project using a discount rate of 3%.

NPW = -400 + 225 (P/A, 3%, 2) – 50(P/F, 3%, 3)

NPW = -400 + 225 (1.91347) – 50(.91514) = -15.22

B. Calculate the net present value of this project using a discount rate of 7%.

NPW = -400 + 225 (P/A, 7%, 2) – 50(P/F, 7%, 3)

NPW = -400 + 225 (1.80802) – 50(.81630) = -34

C. Calculate the benefit cost ratio of this project using a discount rate of 5%.

PW of Cost = 400 + 25 (P/A, 5%, 2) + 300 (P/F, 5%, 3)

PW of Cost = 400 + 25 (1.85941) + 300 (.86384) = 706

PW of Revenues = 250(P/A, 5%, 3)

PW of Revenues = 250(2.72325) = 681

Benefit Cost Ratio = PW of Benefits / PW of Cost

Benefit Cost Ratio = 681 / 706 = .96

D. Based on your answers to A, B and C, make a guess as to the internal rate of return for this project.

Based on the Present Worth calculations the IRR must be below 3%. At 3% the NPW is negative, and we need to reduce it to get a positive NPW, so that we can use the interpolation formula. Hence, the IRR must be below 3%.

E. Discuss whether this project should be done, based on your answers to the above questions.

The project should be rejected. In the benefit cost ratio also, its coming less than one. The project should not be done.


Related Solutions

Create a table to identify some costs and benefits for microcredit
Create a table to identify some costs and benefits for microcredit
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0...
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000 2 1,000 3 1,000 4 2,000 5 2,000 Assuming an interest rate of 10%, the project's simple payback period is most nearly _________. A. 2 years B. 4 years C. 6 years D. 5 years E. 7 years Using the information from the problem above and linear interpolation, the project's discounted payback period is most nearly ___________. A. 3.62 years B....
What were the anticipated costs and benefits for each participant in the proposed joint venture? Fill in the following table.
Case Study 2-3Case Source: https://www.homeworkmarket.com/sites/default/files/q3/05/11/levis.pdfQuestion:What were the anticipated costs and benefits for each participant in the proposed joint venture? Fill in the following table.FirmFinancial CostsProposed Financial BenefitsProposed Strategic Business BenefitsLevisCCTC
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
The following is a payoff table giving costs for various situations. What decision would an optimist...
The following is a payoff table giving costs for various situations. What decision would an optimist make? State 1 State 2 State 3 Alternative 1 45 37 83 Alternative 2 16 59 72 Alternative 3 23 65 91 Alternative 4 44 33 55
The given table contains values of Total Benefits and Total Costs for a period of five years. Calculate all other values and fill the table. Use the provided excel file.
The given table contains values of Total Benefits and Total Costs for a period of five years. Calculate all other values and fill the table. Use the provided excel file. 
Imagine a project that has benefits that accrue over a long period of time. You are...
Imagine a project that has benefits that accrue over a long period of time. You are in charge of conducting a cost-benefit analysis for the project. Describe what considerations you would take into account when choosing the discount rate for the project. subject: environmental and natural resource economics
Please use the payback period analysis technique to analyze the cost and benefits of this project....
Please use the payback period analysis technique to analyze the cost and benefits of this project. With discount factor of 10%, the project will recover the investment in year three. please provide the numbers in the table. Cash Flow Year 0 Year 1 Year 2 Year 3 Year 4 Cost 1 10,000 Cost 2 5000 Discount factor 10% Total costs 15000 Benefit 1 Benefit 2 Total Benefits Present Value Total Costs Present Value Total Benefits NPV (PV benefits- PV costs)
Perform a Financial Analysis for a project XY. Assume the projected costs and benefits for this...
Perform a Financial Analysis for a project XY. Assume the projected costs and benefits for this project are spread over five years as follows: •   Estimated costs are $225,000 in Year 1, $50,000 in Year 2 , 52,500 in Year 3, 55,000 in Year 4 and 57,500 in Year 5 •   Estimated benefits are $0 in Year 1 and $182,500 each year in Years 2, 3, 4 and 5 •   Use a 9 percent discount rate, and round the discount...
The following table shows the costs and benefits of 4 alternatives. What is the shortest pay...
The following table shows the costs and benefits of 4 alternatives. What is the shortest pay back period among all four alternatives if MARR =7%? Year A B C D 0 -$9,000 -$12,000 -$10,000 -$12,000 1 2,000 3,500 0 0 2 2,000 0 1,000 -2,000 3 2,000 3,000 2,000 0 4 2,000 3,500 3,000 18,000 5 1,000 0 4,000 0 6 3,000 3,000 5,000 0
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT